to:tbrother@utilicorp.com means Troy Brothers (tbrother@utilicorp.com).
-
11 May 2001
Susan T Turpin to abenton@utilicorp.com, anita.reubens@swgas.com, bblanar@coral-energy.com and 80 more
NWP System Notice - 01-241 June 2001 Monthly Maintenance
Post Date: May 11, 2001 Category: MAINTENANCE Subcategory: NWP MONTHLY MAINTENANCE Subject: 01-241 June 2001 Monthly Maintenance Notice Text: All Shippers Letter 01-241??…
-
10 May 2001
Melanie Hunter to jadams2@enron.com, gascontroller@aec.ca, carol_airey@altagas.ca and 260 more
PG&E Gas Transmission-NW Kingsgate Capacity Limitation
Due to system high pressure and inventory balancing, PG&E Gas Transmission-Northwest is limiting the Kingsgate capacity to 2335 MMcf/d effective Gas Day Thursday, May 10,…
-
9 May 2001
Melanie Hunter to abshirek@epenergy.com, jadams2@enron.com, gascontroller@aec.ca and 261 more
PG&E GTN Unscheduled Station 14 Maintenance
PG&E Gas Transmission-Northwest will be performing unscheduled maintenance at Station 14 on Friday, May 11, to replace a dry seal on the Station 14 A-unit. The maintenanc…
-
3 May 2001
Miki Bode to abenton@utilicorp.com, anita.reubens@swgas.com, bblanar@coral-energy.com and 59 more
NWP System Notice - 01-239 NWP Available Capacity
Post Date: May 03, 2001 Category: SHORT-TERM FIRM CAPACITY Subcategory: NWP OFFERS Subject: 01-239 NWP Available Capacity Notice Text: All Shippers Notification:? 01-239?…
-
2 May 2001
Melanie Hunter to Derek Aberle, abshirek@epenergy.com, jadams2@enron.com and 261 more
PG&E GTN Station 3 Maintenance Update
The Station 3 maintenance will continue for gas day Thursday, May 3rd. Therefore, the Kingsgate receipt capacity will remain limited to 2280 MMcf/d until further notice. …
-
30 Apr 2001
Melanie Hunter to Derek Aberle, abshirek@epenergy.com, jadams2@enron.com and 261 more
PG&E Gas Transmission-NW: Kingsgate Capacity Restriction Extended
Maintenance at Station 3 has not been completed as scheduled. As the Station 3 maintenance continues, the Kingsgate capacity will remain limited to 2280 MMcf/d until furt…
-
27 Apr 2001
Melanie Hunter to Derek Aberle, abshirek@epenergy.com, jadams2@enron.com and 261 more
PG&E GTN Kingsgate Capacity Increased
As the Station 3 maintenance proceeds, the throughput capabilities have improved through Kingsgate. Therefore, the Kingsgate capacity will be increased to 2280 MMcf/day e…
-
26 Apr 2001
Miki Bode to abenton@utilicorp.com, anita.reubens@swgas.com, bblanar@coral-energy.com and 59 more
NWP System Notice - 01-237 Soliciting Electronic Bids
Post Date: April 26, 2001 Category: SHORT-TERM FIRM CAPACITY Subcategory: NWP OFFERS Subject: 01-237 Soliciting Electronic Bids Notice Text: All Shippers Notification: 01…
-
26 Apr 2001
-
26 Apr 2001
Melanie Hunter to Derek Aberle, abshirek@epenergy.com, jadams2@enron.com and 265 more
PG&E Gas Transmission-NW: Restriction at Kingsgate
The scheduled Station 3 maintenance has caused a restriction greater than anticipated. For that reason, the Kingsgate capacity will be further limited to 2220 MMcf/d begi…
-
25 Apr 2001
Shannon Seagondollar to Derek Aberle, abshirek@epenergy.com, jadams2@enron.com and 264 more
Updated May Maintenance Schedule
April 25, 2001 ***May Scheduled Maintenance Update*** PG&E Gas Transmission Northwest (GTN) will be performing a portion of the previously canceled maintenance at Station…
-
24 Apr 2001
Ben Ledene to avallow@lodielectric.com, angela@cook-inlet.com, Barry Brunelle @ENRON and 103 more
Wild Goose Storage and the Ruby Pipeline
The following news release comes from today's Gas Daily. Feel free to call us at Wild Goose Storage Inc. to discuss what opportunities are available to align your storage…
-
20 Apr 2001
Shannon Seagondollar to gascontroller@aec.ca, Derek Aberle, abshirek@epenergy.com and 266 more
Updated April Maintenance Schedule
April 20, 2001 ***April Scheduled Maintenance Update*** PG&E Gas Transmission Northwest (GTN) will perform scheduled maintenance at Station 3 and Station 13 C-unit from A…
-
20 Apr 2001
Miki Bode to abenton@utilicorp.com, anita.reubens@swgas.com, bblanar@coral-energy.com and 59 more
NWP System Notice - 01-236 Soliciting Electronic Bids
Post Date: April 20, 2001 Category: SHORT-TERM FIRM CAPACITY Subcategory: NWP OFFERS Subject: 01-236 Soliciting Electronic Bids Notice Text: All Shippers Notification: 01…
-
20 Apr 2001
-
20 Apr 2001
BusinessDvp WGPW to Calvin Miller, dsuter@sempratrading.com, 20355-5010@williams.com and 78 more
KERN RIVER MAY 2001 IT
- C.DTF
-
19 Apr 2001
Linda W Humphrey to abbyb@usgt.com, astant@sempratrading.com, ajangula@mtpower.com and 118 more
All Shippers Notification: 01-235 - NORTHWEST PIPELINE'S NOTICE OF AVAILABLE AND POTENTIALLY AVAILABLE FIRM TRANSPORTATION CAPACITY
- 01-235 04-19-2001 includes Remaining Mitigated Capacity_.doc
-
30 Oct 2000
Jim Schoene to acarter@westerngas.com, colliw@texaco.com, bblanar@coral-energy.com and 38 more
GTN Quaterly Meeting Reminder
Thursday, November 2 is our next, less than quarterly, meeting to up date you on events that willl affect your business in the Western U.S. The meeting is at the Hyatt do…