30 Mar 2001
John Lavorato to Rob Milnthorp
RE: PML
Rob You simply can't negotiate on a choice market. Are your owed past fees for management? Let me know. I don't run industrial markets and Greg would have to settle this …
-
30 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 28 more
California Update 3/29/01
? Socal and PG&E have both made payments to the state of California (DWR) for power purchases per the PUC order on Tuesday. Socal made a payment on Wednesday of $43.5M fo…
-
29 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 28 more
California Update 3/29/01
? Socal and PG&E have both made payments to the state of California (DWR) for power purchases per the PUC order on Tuesday. Socal made a payment on Wednesday of $43.5M fo…
-
29 Mar 2001
David W Delainey to Tim Belden, Michael R Brown, Rick Buy and 85 more
PRC Committee Meeting April 3, 2001
You have been selected to serve on the 2001 VP Performance Review committee. This selection is based on your performance and recognizing that you possess the behaviors we…
-
28 Mar 2001
Mark Powell to Rob Milnthorp, Derek Davies, Kate Joslyn and 6 more
Retail Electricity Agreement & My Availability Tomorrow
Please find attached a copy of the 250MWh/year or less and the more than 250MWh/year forms of retail electricity contract. I will be out of the office at a course for mos…
-
28 Mar 2001
John J Lavorato to Kenneth Lay, Jeff Skilling, David W Delainey and 15 more
FW: Extension of Petro-Canada Wholesale Gas Services Arrangement for 5 more years
After a great deal of work the Canadian team has renewed our outsourcing arrangement with PetroCanada for another 5 years. This was a great accomplishment for Enron Canad…
-
28 Mar 2001
John Lavorato to Kenneth Lay, Jeff Skilling, David W Delainey and 15 more
FW: Extension of Petro-Canada Wholesale Gas Services Arrangement for 5 more years
After a great deal of work the Canadian team has renewed our outsourcing arrangement with PetroCanada for another 5 years. This was a great accomplishment for Enron Canad…
-
28 Mar 2001
Kay Chapman to Tim Belden, Michael R Brown, Rick Buy and 85 more
PRC Committee Meeting April 3, 2001
You have been selected to serve on the 2001 VP Performance Review committee. This selection is based on your performance and recognizing that you possess the behaviors we…
-
28 Mar 2001
Kevin Heal to Rob Milnthorp, Robert Hemstock, Eric LeDain and 11 more
S&P MOU Draft
Here is the latest version of the TCPL Mainline MOU. Significant changes (i.e. watered down) changes to turnback policy. More meetings next week as indicated below. I wil…
-
28 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 28 more
California Update #2; 3/27/01
? Item 5b of the PUC draft decision, which implements the 3 cent/kwh rate increase, has just passed unanimously. Commissioner Lynch stressed again that this rate increase…
-
27 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 28 more
California Update 3/27/01
Executive Summary: ? Undercollet Remains Sticking Point for Utility Creditors (especially QFs), involuntary bankruptcy likely if issue is not addressed in today's CAPUC h…
-
27 Mar 2001
Aleck Dadson to John J Lavorato, Rob Milnthorp, Eric Thode and 6 more
Ken Lay Speech - April 4
Attached is a draft of Ken Lay's speech for the Power Breakfast in Toronto on April 4. Any comments would be appreciated. I will be forwarding fresh briefing materials to…
-
27 Mar 2001
Kevin Heal to Rob Milnthorp, Robert Hemstock, Eric LeDain and 11 more
S&P MOU Draft
Here is the latest version of the TCPL Mainline MOU. Significant changes (i.e. watered down) changes to turnback policy. More meetings next week as indicated below. I wil…
-
27 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 28 more
California Update #2; 3/27/01
? Item 5b of the PUC draft decision, which implements the 3 cent/kwh rate increase, has just passed unanimously. Commissioner Lynch stressed again that this rate increase…
-
27 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 28 more
California Update 3/27/01
Executive Summary: ? Undercollet Remains Sticking Point for Utility Creditors (especially QFs), involuntary bankruptcy likely if issue is not addressed in today's CAPUC h…
-
26 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 26 more
California Update 3/26/01
Executive Summary: -CPUC likely to pass rate hikes tomorrow, politicians bowing to the inevitable -Many questions still unanswered, most notably size/structure of rate in…
-
24 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 26 more
California Update#2; 3/23/01
? Davis's transmission deal essentially dead As reported early, the primary sticking point in Davis's deal with PG&E was over PG&E's legal obligation to supply California…
-
23 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 26 more
California Update 3/22/01
Executive Summary: ? The as yet unnumbered rescue bill by Davis made it to the Senate floor ? An exemption of the gas-fired QFs from this bill (as proposed by Sen. Keeley…
-
22 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 26 more
California Update 3/22/01
? The legislature will meet and vote to repeal Section 390 of AB 1890. This will reverse what the QFs get paid from natural gas costs and replace it with the formula in t…
-
22 Mar 2001
Aleck Dadson to Kimberly Hillis and 6 more
RE: Toronto Trip
Kimberley, this is the material that is going to come in hard copies tomorrow. I received a draft of Mr. Lay's speech today and I am now engaged in a substantial rewritin…
-
22 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen and 26 more
California Update 3/21/01
Executive Summary: ? Situation "confused" but filing probably postponed until Monday ? Could be sooner if negotiations completely collapse, or if commercial paper holders…
-
21 Mar 2001
Ruth Concannon to Kevin Heal and 12 more
TransCanada Shipper Settlement -- Impact to Sithe/Independence Restructuring
As we discussed yesterday, the TCPL Mainline Service and Pricing Settlement language on the proposed Capacity Turnback Policy may be very important feature of the Settlem…
-
21 Mar 2001
John Lavorato to Rob Milnthorp
RE: Greg Shea
I met with Shea in Houston. Didn't broach the issue on working in Canada for us. He always puts on a good face about TC but I'm not sure he loves it. Until recently I was…
-
21 Mar 2001
Ruth Concannon to Kevin Heal and 12 more
TransCanada Shipper Settlement -- Impact to Sithe/Independence Restructuring
As we discussed yesterday, the TCPL Mainline Service and Pricing Settlement language on the proposed Capacity Turnback Policy may be very important feature of the Settlem…
-
16 Mar 2001
Kristin Walsh to John J Lavorato, Louise Kitchen, John L Nowlan and 28 more
California Update 3/16/01
? A source within the generator community confirms press reporting that Coram Energy plans to file an involuntary bankruptcy early next week. Through an intermediary, we …