from:larry.campbell@enron.com means Larry Campbell (larry.campbell@enron.com).
to:rich.jolly@enron.com means Rich Jolly (rich.jolly@enron.com).
-
14 Dec 2001
Larry Campbell to steve.sanmiguel@enron.com, Team Mountainair, Rich Jolly and 4 more
RE: Station 7: Unit 703
Steve, what I have on my board is that when cubix did the test for 703 the engine load was 89%. If Cubix is willing to provide us a report that shows the load on 703 to b…
-
4 Dec 2001
RE: Duke's Tie In Into the Pipeline Liquids Tank at Wt-1
10-4. I saw a picture of Dustin's deer, pretty nice. someone from BLM told me a deer came in from the sandhills east of town that was 29" and non typical. I also heard of…
-
4 Dec 2001
Larry Campbell to John Shafer, Rich Jolly, Earl Chanley and 3 more
FW: Summary of Progress
FYI from Penn State on the progress of the model to remove PCB's from Transwetern's pipeline.
-
4 Dec 2001
Larry Campbell to Rich Jolly, team.carlsbad@enron.com and 2 more
Duke's Tie In Into the Pipeline Liquids Tank at Wt-1
Rich, concerning the environmental liabilities which may impact Transwestern if Duke should direct the liquids from their 8" line into the pipeline liquids tank at Wt-1, …
-
29 Nov 2001
Larry Campbell to Rich Jolly, Rick Loveless, roger.osborn@enron.com and 1 more
FW: True Story
-----Original Message----- From: Jolly, Rich Sent: Thursday, November 29, 2001 1:53 PM To: Campbell, Larry; Bailey, Arnie; Roensch, David; Smith, Rick Subject: FW: True S…
-
21 Sep 2001
Larry Campbell to William Kendrick, scott.clark@enron.com, Rich Jolly and 35 more
(no subject)
NORTHERN NATURAL GAS COMPANY Submitted Title V Permit Renewal for Mullinville Compressor to the KDHE. Submittal of standard exemption documention for the NNG Kermit, Plai…
-
7 Sep 2001
Larry Campbell to William Kendrick, John Shafer, Sarita Garza and 37 more
Albuquerque Environmental Roundtable, Oct. 16-17
The 2001 environmental roundtable has been confirmed for the above location and dates. Make your reservations at the Holiday Inn Crowne Plaza (505) 821-3333. The hotel is…
-
7 Sep 2001
Larry Campbell to Arnold L Eisenstein, John Shafer, William Kendrick and 10 more
Air Permit Delay, Red Rock Expansion
Yesterday evening I phoned both the state of Arizona ( agency for stations 1 and 2) and Region 9 EPA ( agency for stations 3 and 4) concerning the status of when the air …
-
7 Sep 2001
Larry Campbell to Arnold L Eisenstein, John Shafer, William Kendrick and 10 more
Air Permit Delay, Red Rock Expansion
Yesterday evening I phoned both the state of Arizona ( agency for stations 1 and 2) and Region 9 EPA ( agency for stations 3 and 4) concerning the status of when the air …
-
6 Sep 2001
Larry Campbell to William Kendrick, scott.clark@enron.com, Rich Jolly and 29 more
(no subject)
NORTHERN NATURAL GAS Reviewed Title V Operating Permit renewal applications with field teams for Finney Co. 1, Finney Co. 3 and Fowler. Contractor has made revisions and …
-
27 Aug 2001
Larry Campbell to Leon O'Bryan and 4 more
Re: Common Parts request
Leon, thanks for the list. If this is a complete list of the parts which are replaced, what parts are "common" between the 3505 and the 4700? Bill Scott is the attorney o…
-
14 Aug 2001
Larry Campbell to team.artesia@enron.com, team.big-lake@enron.com, team.carlsbad@enron.com and 54 more
Southwest Region Environmental Roundtable Oct. 16-18
The Southwest Region will be hosting its 2001 environmental roundtable in Albuquerque, NM on October 16-17 at the Holiday Inn Crowne Plaza (505) 821-3333. Room rates are …
-
14 Aug 2001
Larry Campbell to John Shafer, William Kendrick, Louis Soldano and 4 more
P-1 NOV Issue
The State of New Mexico has issued the settlement penalty for the turbine replacement issue at the P-1 C/S. You may remember that the original amount levied against Trans…
-
19 Jul 2001
Larry Campbell to Arnie Bailey, Bob Bandel, David Roensch and 10 more
TNC Membership
Advisors, presented below is a memo from GPG Houston requesting that we provide to them the number of ETS employees in each team who have taken advantage of the one year …
-
18 Jul 2001
Larry Campbell to team.flagstaff-sta3@enron.com, Gallup-Sta4, Team, Gallup-Sta5, Team and 6 more
Public Water System Sampling Time Again
Sta.3, 4 and 5 As you may know, we are at the end of our grace period for not being required to do monthly sampling for the public water systems at sta. 3,4 and 5. Jeff L…
-
18 Jul 2001
Larry Campbell to Donna Martens, Arnold L Eisenstein, Mike McCracken and 8 more
RE: TWPL Station 2 Timber
I just spoke to the state of Arizona concerning the tree removal at Station 2. Their response to our request to remove the trees has been APPROVED, provided that this is …
-
6 Jul 2001
Larry Campbell to John Shafer and 10 more
RE: Flagstaff Trip Rescheduled for July 24 - 26th
John, I was just thinking that if this deconning becomes a routene activity for us and PG&E, we might want to consider breaking in a company that is less expensive, can m…
-
19 Jun 2001
Larry Campbell to John Shafer, William Kendrick and 10 more
Compliance Order, P-1 C/S
Transwestern received a Compliance Order from the State of New Mexico, Air Quality Bureau, for an outstanding turbine replacement activity at the P-1 C/S which occurred i…
-
24 May 2001
Larry Campbell to Michael Adewumi and 14 more
RE: status, PCB pipeline modeling study
Michael, I will be discussing with John and others in the near future about the status of the study. When will your progress report be ready for review? It might be a goo…
-
24 May 2001
Larry Campbell to Byron Rance and 10 more
Re: Building Colors
Byron/Tiny, I spoke to Ken Jacobs with the Forest Service and have attached his e mail below concerning the Forest Sevice's choice for the building. I have informed him t…
-
21 May 2001
Larry Campbell to team.flagstaff-sta2@enron.com, Team Flagstaff and 8 more
Tree Removal, Sta. 2
I spoke with Ken Jacobs, with the Forest Service in Flagstaff, concerning his agencies approval for the turbine construction at Station 2. As a condition of the approval …
-
18 May 2001
Larry Campbell to Lorraine Lindberg, Team Laguna, Team Mountainair and 4 more
RE: PCB sampling at Rio Puerco
Laguna and or Moutainair team, because I dont know which team is responsible for the Belen delivery point, would someone check on liquids at this location and if present,…
-
14 May 2001
Larry Campbell to Louis Soldano, John Shafer, William Kendrick and 3 more
RE: status, PCB pipeline modeling study
Louie, after the presentation MIchael gave, there were some issues about the data and predictions ie., like how much solvent do we really need to clean the pipeline and t…
-
11 May 2001
Larry Campbell to team.flagstaff-sta2@enron.com, Team Flagstaff, team.kingman-sta1@enron.com and 6 more
pollution Prevention Training
Under the regulations of the state of Arizona, facilities which have a pollution prevention plan (sta.1, sta. 2 and Needles) are required to have an annual training to ev…
-
11 May 2001
Larry Campbell to Edward Attanasio and 8 more
Re: Bakersfield Environmental Action Items
Ed, I would appreciate it very much if you would review the action item list from Scott Jones and choose which items are Koch's responsibility and which items belong to E…