to:rich.jolly@enron.com means Rich Jolly (rich.jolly@enron.com).
-
22 Jun 2001
Team Kingman-Needles to Rich Jolly, team.kingman-sta1@enron.com, team.kingman@enron.com and 13 more
PGE sample results
See attached for this months sample run.
-
21 Jun 2001
Darrell Schoolcraft to Gallup-Sta4, Team, Jerry Graves, Rich Jolly and 1 more
RE: station4 outage req.
1. On your first request for down time next week. You may have an opportunity this weekend 23, or 24 depending on the volumes. We can communicate this to your Team Friday…
-
21 Jun 2001
Louis Soldano to David Nutt, Larry Campbell, John Shafer and 6 more
NMED Compliance Order
Privileged & Confidential Attorney - Client Communication I just spoke with Mr. Charles de Saillan, Asst. General Counsel for the NMED, concerning the referenced Complian…
-
19 Jun 2001
Max Brown to laura.kunkel@enron.com and 10 more
FW: Transwestern 50479-30A and 30B
Laura, Can you shed any light on this?
-
19 Jun 2001
Larry Campbell to John Shafer, William Kendrick and 10 more
Compliance Order, P-1 C/S
Transwestern received a Compliance Order from the State of New Mexico, Air Quality Bureau, for an outstanding turbine replacement activity at the P-1 C/S which occurred i…
-
15 Jun 2001
-
13 Jun 2001
Darrell Schoolcraft to Gary Spraggins and 6 more
Re: Pigging from P-2 to P-3
I spoke to the guys in the field last week when our deliveries went up and we made the decision to run the pigs. It was passed on to us that the fluids in the line were h…
-
12 Jun 2001
Team Kingman-Needles to Rich Jolly, team.kingman-sta1@enron.com, team.kingman@enron.com and 13 more
PGE sample run
We had to change labs so i don't know when the results will be back. Here are the liquids gathered for this months sample run. See attached. Thanks, Randy
-
6 Jun 2001
Michael Adewumi to Larry Campbell and 14 more
RE: status, PCB pipeline modeling study
Dear Larry: We are currently completing the improved modeling to include the effect of flow regimes, which I am sure that you recall that in our meeting the last time, we…