to:peter.nassab@enron.com means Peter Nassab (peter.nassab@enron.com).
-
29 Mar 2002
Esmeralda Hinojosa to adam.caldwell@enron.com, Susan Edison, fred.enochs@enron.com and 542 more
Tuesday - April 2: Wholesale/Retail Floor Meeting
Dan Leff will host a floor meeting on Tuesday. Please plan to join him as follows: Tuesday - April 2, 2002 at 11:00 A.M. Enron Center South 3rd Floor Mark your calendar! …
-
21 Mar 2002
Esmeralda Hinojosa to henry.starr@enron.com, willie.scott@enron.com, adam.caldwell@enron.com and 311 more
FW: Tomorrow: Floor Meeting with Dan Leff - ECS 4th Floor
The meeting will be on the 4th Floor of Enron Center South (new building). Thanks - Esmeralda
-
21 Mar 2002
Esmeralda Hinojosa to henry.starr@enron.com, willie.scott@enron.com, adam.caldwell@enron.com and 311 more
Tomorrow: Floor Meeting with Dan Leff - ECS 4th Floor
<Embedded Microsoft Word Document>
-
2 Mar 2001
Mike McConnell to Peter Nassab
Re: Resume
Peter, Thanks for your voicemail and email. Your resume is impressive and I have 2 thoughts. Most of our efforts in EGM are not asset related but I would suggest you cont…
-
6 Feb 2001
Kay Mann to Richard Leibert, Fred L Kelly, Peter Nassab and 5 more
Cost plus contract for Co Op City
As a follow up to my previous e-mail, here is the second request, which was in my opinion adequately addressed by John Schwartzenburg. I am frustrated with beginning the …
-
6 Feb 2001
Kay Mann to John G Rigby, Richard Leibert, Fred L Kelly and 7 more
Re: FW: Draft Coop City Term Sheet - priority.
Gentlemen, This was my first written request for a cost plus contract. The request was made to NEPCO because at that time NEPCO was supposedly still involved in the proje…
-
1 Feb 2001
Kay Mann to david.lund@enron.com, John Schwartzenburg, John G Rigby and 5 more
Cost plus contract for Co Op City
Gentlemen, As Dave and John know, I'm working on a deal for ENA (and with Jude) which has as one aspect a cost plus EPC contract for the construction of a power plant. We…
-
31 Jan 2001
John G Rigby to Ben Jacoby and 12 more
Siemens - Westinghouse 31 Jan AM Update.
1. Met with Ron Tapscott, Jim Studdert and Scott Laidlaw, primary subject insurance claim status. Scott Laidlaw gave Jim a letter from Siemens in which Siemens says the g…
-
14 Sep 2000
Brian D Barto to Darrell Stovall, Peter Nassab, Larry Bishop
Sample GE/WestLB/7FA Contract
Darrell: Per your request, for further requirements of ENA, attached is the most recent off balance sheet (West LB) turbine purchase contract executed between EECC and GE…
-
10 Jul 2000
Kay Mann to donald.solomon@enron.com and 4 more
Re: Calumet Project
My understanding is that the ABB equipment will most likely be used somewhere other than Calumet due to the noise issue. It is possible that LM 6000's will be used on Cal…
-
3 Jul 2000
Brian D Barto to Cheryl Costa, Kathleen Clark and 2 more
GE Standared Indemnification Language
Sheila: Per our last World Hunger meeting: Review GE Indemnity Language in theire Standard. Upon inspection of GE's standard selling terms, I must report that the only in…
-
30 Jun 2000
Brian D Barto to Cheryl Costa, stephen.swift@ps.ge.com, john.schroeder@ps.ge.com and 12 more
World Hunger Preliminary Discussion List
Distinguished Distributees: In the furtherance of our noble goal to reduce the number of required negotiation points on future contracts, Enron and General Electric have …
-
20 Jun 2000
Kay Mann to Brian D Barto, John Schwartzenburg, Scott Dieball and 4 more
Internal meeting re: GE issues
How about 10:00am on Thursday to discuss GE and how to end world hunger? Please let me know if this works for you, and I'll get us a conference room. Nominations for othe…