  1. 21 Dec 2001

    John R. Keller to Mary Kay Miller, Dan Pribble, Phil Lowry and 14 more

    RE: Producer meeting

    Mary Kay: Please coordinate activities in this area with the Omaha Planning team through Bryan Reinecke - Planning Coordinator. Ken Anderson will be the primary person on…

  2. 21 Dec 2001

    Mary Kay Miller to Mary Kay Miller, Dan Pribble, paul.lowry@enron.com and 15 more

    RE: Producer meeting

    Phil/John/ Morgan, since Eric has left, can you let us know who to work with on the allocations alternatives??

  3. 20 Dec 2001
  4. 14 Dec 2001

    Jerry Graves to c..alexander@enron.com, Lynn Blair, mike.bonnstetter@enron.com and 72 more

    Outage Commercial Review Schedule (2002)

    FYI, Here is the 2002 schedule for the Outage Commercial Review Meeting. Note the new locations and the new conference code number. These dates have been set, but are sub…

  5. 13 Dec 2001

    Jerry Graves to team.ashland@enron.com, team.beaver-mach-shop@enron.com, team.beaver-plant@enron.com and 170 more

    Bushton Universe, Albuquerque, DesMoines, and Dakota Region Outage Reports Through December 2002

    FYI, In the interest of sending fewer emails, I have attached Bushton Universe, Albuquerque, DesMoines, and Dakota Region outage reports to the same email. Please review …

  6. 12 Dec 2001

    Ron Matthews to Michelle Lokay, Darrell Schoolcraft, Kimberly Watson and 4 more

    Burlington Study - El Paso WIndow Rock I/C

    This is a revised spreadsheet from the one yesterday. Changes made were a result of discussions with Darrell. Still need to stick to our guns and NOT give Burlington any …

  7. 6 Dec 2001

    Arnold L. Eisenstein to Larry F. Campbell, William Kendrick, Ruth Jensen and 7 more

    FW: EngineTest.xls

    This is the GG (jet) for Unit 2 on Red Rock also - look at the range and fuel rate at turndown