to:john.shafer@enron.com means John Shafer (john.shafer@enron.com).
-
22 Feb 2001
Jeffery Fawcett to Shelley Corman, Mary Kay Miller, Drew Fossum and 10 more
California Data Requested
Shelley, Since Steve and Kevin are out, I'll wade in here. The TW Red Rock expansion is for 150,000 Dth/d. It is a mainline expansion, allowing Transwestern to flow west …
-
21 Feb 2001
Larry Campbell to John Shafer, William Kendrick, Louis Soldano and 4 more
SoCal Meeting with Southwest Gas
I wanted to let everyone know that the meeting between Southwest Gas and SoCal concerning presence of PCBs on the Southwest Gas system will be this tuesday. I had an oppo…
-
21 Feb 2001
Kenny_Maltby@eott.com to Larry Campbell and 18 more
Re: Rogas Line -- USFW Approval
I will get a name from Randy and see if we can set something up for next week. I believe the contact is Dr. Jeffrey Single, with all the changes it's a good idea for us a…
-
21 Feb 2001
Larry Campbell to Richard McCurdy and 10 more
Line 300 Liquid Sample SummaryFeb01TW.xls
Rich, thanx for the sampling update. Ill pass it along to the apropriate parties. A cursory look at the data shows it to be inconsistently up and down, as expected, with …
-
21 Feb 2001
Larry Campbell to George Robinson and 4 more
Re: Meeting with the Laguna's over the PCB remediation at C/S 6
Thanx, George. Please let us know what their initial reaction and evaluation is of the conditions at Sta. 6. Im interested in what their thoughts are with respect to the …
-
21 Feb 2001
Kenny_Maltby@eott.com to John Shafer and 18 more
Re: Rogas Line -- USFW Approval
I obtained a copy of a letter sent to Gary Fuller from the Department of Fish and Game on November 3, 2000. In the letter the Fish and Game agreed EOTT has 41 Acres of co…
-
21 Feb 2001
Larry Campbell to Arnold L Eisenstein, Earl Chanley, Donna Martens and 10 more
Arizona Mainline Expansion
This is a gentle reminder, and Im sure that most are aware, but under no circumstances is there to be any construction activiy initiated for the turbine installation at t…
-
21 Feb 2001
Larry.Campbell@enron.com to John Shafer, scott.jones@enron.com and 20 more
Re: Rogas Line -- USFW Approval
John, Scott Jones, I believe is still on vacation in Hawaii of all places. And I believe you are correct that we have around 15 acres of existing credit. Kenny, let me kn…
-
21 Feb 2001
Larry Campbell to William Kendrick and 8 more
RE: TW Expansion Project
Bill, the baseline noise surveys, which have been completed, were performed by Hoover and Keith out of Houston, Tx. I have a meeting scheduled with the permit engineers f…
-
16 Feb 2001
Larry Campbell to John Shafer, Louis Soldano, Cutty Cunningham and 3 more
Meeting with the Laguna's over the PCB remediation at C/S 6
John, Lou, Cutty, Bill, I want to bring this issue back up for your attention, as I know that everyone is very busy. During the EPA Title V inspection at the Laguna C/S t…
-
15 Feb 2001
Team Kingman-Needles to Rich Jolly, team.kingman-sta1@enron.com, team.kingman@enron.com and 14 more
PG&E Report
The topock Lat. is still dry as a bone at the Measurement station and at the SLX plant. See attached on liquids gathered for this months sample run. Results will follow a…
-
12 Feb 2001
Larry Campbell to John Shafer and 8 more
Permitting Status, Rogas Construction Project
John, this is a short note to let you know where we stand on the 7 mile pipeline construction Rogas Project with respect to environmental permitting and approvals. The fo…
-
9 Feb 2001
Arnold L Eisenstein to Larry Campbell and 8 more
Re: TW Mainline Expansion
Larry, your ears are good! I just heard the same news. I sent some data on emissions on the RB211on 1/31 resending the e-mails attchments. In orfer to capture the emissio…
-
5 Feb 2001
Re: Annual Report
John, I had asked Randi to complete an annual report for the F&G 2081 permit, as I did not want to have this hang over our head when EOTT's 2081 application was reviewed.…
-
1 Feb 2001
Larry Campbell to Edward Attanasio and 14 more
Re: No. Coles Levee to Rogas Interconnect - Permit & Property Owner R equirements
Ed the 6" project you are talking about is a small project independant of Rogas where a 6"line will be constructed from North Coles and run above ground, if possible, to …