Enron email

Algorithmic Indexing

70 messages for to:iain.greig@enron.com

Newest Oldest

Matching messages by month
Skilling resigns
Q3 loss announced
Bankruptcy filing

to:iain.greig@enron.com means Iain Greig (iain.greig@enron.com).

  1. 5 Feb 2002

    Tom Engel to Regan M. Smith, Thresa A. Allen, Susan Amador and 88 more

    RE: PLEASE REVIEW - PROGRESS REPORT from testing on Monday, Feb 4th & WEDNESDAY AND THURSDAY TESTING SCHEDULE

    ETX was supposed to be Electronic Transaction. An exchange is a regulated body - which we are not. We should be careful not to use the word "exchange". I know this sounds…

  2. 5 Feb 2002

    Regan M. Smith to Thresa A. Allen, Susan Amador, Sherry Anastas and 89 more

    FW: PLEASE REVIEW - PROGRESS REPORT from testing on Monday, Feb 4th & WEDNESDAY AND THURSDAY TESTING SCHEDULE

    Typo correction - ETX for Electronic Trading Exchange as the UBS name for EOL internal identifier, not EFX as my previous email. Thanks Tom. Regan Smith Energy Operations…

  3. 5 Feb 2002

    Regan M. Smith to Thresa A. Allen, Susan Amador, Sherry Anastas and 89 more

    PLEASE REVIEW - PROGRESS REPORT from testing on Monday, Feb 4th & WEDNESDAY AND THURSDAY TESTING SCHEDULE

    Please review the progress report from Monday's regression test below. It was a success, and the goals were accomplished! Thank you for your participation! All the issues…

  4. 4 Feb 2002

    Susan Elledge to Regan M. Smith, Thresa A. Allen, Susan Amador and 86 more

    RE: Updates... PLEASE READ - Netco testing schedule for Monday, Feb 4th & Tuesday, Feb 5th

    Regan, I know I provided the physical and financial contracts, but I did not tell you which ones were sut up to fail. Here they are: Counterparty Legal Name K # Contract …

  5. 4 Feb 2002

    Rhonda L. Denton to Regan M. Smith, Thresa A. Allen, Susan Amador and 86 more

    RE: Updates... PLEASE READ - Netco testing schedule for Monday, Feb 4th & Tuesday, Feb 5th

    The power contracts set up are as follows 20000543 - Williams Energy Marketing & Trading (Power Bilateral) 20000544 - Reliant Energy Services (Power Sale) Nothing set up …

  6. 4 Feb 2002

    Regan M. Smith to Thresa A. Allen, Susan Amador, Sherry Anastas and 86 more

    Updates... PLEASE READ - Netco testing schedule for Monday, Feb 4th & Tuesday, Feb 5th

    Updates for Today's NetCo regression test at 1:00pm: NT User Id's For testing, if you are NT user id that participated in the 'PILOT' group, please use your PILOT id. Oth…

  7. 31 Jan 2002

    Regan M. Smith to Thresa A. Allen, Susan Amador, Sherry Anastas and 80 more

    PLEASE READ - Netco testing schedule for Monday, Feb 4th & Tuesday, Feb 5th

    Everyone, The attached document outlines the Netco testing schedule for Monday, Feb 4th & Tuesday, Feb 5th. There have been many decisions/ setup changes from the last te…

  8. 30 Jan 2002

    Regan M. Smith to Thresa A. Allen, Bridgette Anderson, Diane Anderson and 112 more

    IMPORTANT - PLEASE READ. TEST TODAY (3PM) WITH DISABLING NETCO PRODUCTION

    As part of the quality assurance testing with the NetCo systems separation from Estate, a test will be performed (TODAY, 4pm) to ensure that the Estate systems are totall…

  9. 28 Jan 2002

    Regan M. Smith to Thresa A. Allen, Bridgette Anderson, Diane Anderson and 77 more

    Monday 01/28 - Status report of integration testing, remaining, outstanding issues, going forward

    Everyone - updates from testing last week, and communication of information/ going forward. Thanks to all involved in last weeks testing. Much has been accomplished. We d…

  10. 24 Jan 2002

    Regan M. Smith to Thresa A. Allen, Bridgette Anderson, Diane Anderson and 75 more

    Status report of integration testing from Wednesday, Jan. 23rd ; and Thursday's continuation..

    Status report of integration testing from Wednesday, Jan. 23rd - (16 gas/ power types of transactions to test) Overall, there were no infrastructure or major application …

  11. 23 Jan 2002

    Regan M. Smith to Thresa A. Allen, Bridgette Anderson, Diane Anderson and 74 more

    Today's integration test deferred to 2:00pm...

    In light of the offsite UBS meeting this morning, today's test will be moved from 12:00 to 2:00pm. We will use the same global data already setup from Friday/ Tuesday. He…

  12. 23 Jan 2002

    Regan M. Smith to Thresa A. Allen, Bridgette Anderson, Diane Anderson and 75 more

    Status report of integration testing from Tuesday, Jan. 22nd

    Status report of integration testing from Tuesday, Jan. 22nd (completion of subset of Gas/ Power scenarios to test that all platform components are setup) We've completed…

  13. 22 Jan 2002

    Aftab Saleem to Regan M. Smith, Thresa A. Allen, Diane Anderson and 71 more

    RE: Status report of NETCO integration testing from Friday, Jan. 18th and next weeks testing...

    Hi, The attached document outlines the Netco testing schedule for today and tomorrow. The focus for today is to complete the scenarios which were not completed last Frida…

  14. 20 Jan 2002

    Regan M. Smith to Thresa A. Allen, Diane Anderson, Evelyn Aucoin and 72 more

    Status report of NETCO integration testing from Friday, Jan. 18th and next weeks testing...

    Status report of integration testing from Friday, Jan. 18th (executed subset of Gas/ Power scenarios to test that all platform components are setup) Thanks to all those i…

  15. 18 Jan 2002

    Bill D. Hare to Bill D. Hare, Terry Sanvido, Debbie R. Brackett and 55 more

    NETCO Testing

    NOTE 1) New SAP Company Number from 0364 to 7001 NOTE 2) SAP will notify Sundar when they are ready to accept data, no SAP customer or Vendor numbers are available at thi…

  16. 17 Jan 2002

    Aftab Saleem to Aftab Saleem, Bill D. Hare, Bernice Rodriguez and 33 more

    Updated: NETCO Testing

    Hi, Please see the attached document with the correct date that corresponds with the meeting request. In addition, the Canadian and Portland users are also included. The …

  17. 17 Jan 2002

    Aftab Saleem to Bill D. Hare, Bernice Rodriguez, Stacey Richardson and 32 more

    Updated: NETCO Testing

    When: Friday, January 18, 2002 1:00 PM-5:00 PM (GMT-06:00) Central Time (US & Canada). Where: 2521, 2525 *~*~*~*~*~*~*~*~*~* Hi, Please see the attached document with the…

  18. 17 Jan 2002

    Aftab Saleem to Bill D. Hare, Bernice Rodriguez, Stacey Richardson and 22 more

    NETCO Testing

    When: Friday, January 18, 2002 1:00 PM-5:00 PM (GMT-06:00) Central Time (US & Canada). Where: 2521, 2525 *~*~*~*~*~*~*~*~*~* Hi, Attached is schedule for NETCO testing fo…

  19. 17 Jan 2002

    Bill D. Hare to Terry Sanvido, Debbie R. Brackett, Frank Hayden and 62 more

    NETCO Book Port Folios Testing

    I have attached the Books and Portfolios setup in Global Counterparty todate. We are still making modifications as requested. Bill

  20. 17 Jan 2002

    Aftab Saleem to Aftab Saleem, Dawn C. Kenne, Melissa Ann Murphy and 10 more

    Front Office NETCO Testing

    Hi, Let us plan to meet to perform preliminary integration testing for the Front Office for NETCO. We are working on completing the front office application migration by …

  21. 17 Jan 2002

    Aftab Saleem to Dawn C. Kenne, Melissa Ann Murphy, Corry Bentley and 9 more

    Front Office NETCO Testing

    When: Thursday, January 17, 2002 2:00 PM-5:00 PM (GMT-06:00) Central Time (US & Canada). Where: 2521 *~*~*~*~*~*~*~*~*~* Hi, Let us plan to meet to perform preliminary in…

  22. 15 Jan 2002

    Regan M. Smith to Debbie R. Brackett, Bill D. Hare, Frank Hayden and 53 more

    Update on Netco integration test for this week/ global data setup.

    Everyone - Below is a update on the testing schedule for NetCo The integration test plan for NetCo is scheduled for Thursday and/ or Friday. However, there are numerous d…

  23. 14 Jan 2002

    Jeff Johnson to Terry Sanvido, Debbie R. Brackett, Bill D. Hare and 253 more

    RE: Congratulations - Estate Integration Test Milestone !

    Thanks to everyone for all the hard work in making this a successful test. Thanks also to everyone involved in continuing to support Estate as well as the Net Co due dili…

  24. 14 Jan 2002

    Jay Webb to Steve Stock, office.dl-it@enron.com, charles.ballmer@enron.com and 37 more

    RE: Estate Migration

    The planning and execution of this migration and testing effort has been flawless. It is a testament to the tremendous talent and professionalism of Enron's IT department…

  25. 14 Jan 2002

    Steve Stock to office.dl-it@enron.com, charles.ballmer@enron.com, Michael Barber and 38 more

    Estate Migration

    The Estate version of the systems were commissioned successfuly onto Estate hardware this weekend with the users completing their testing on sunday, and it looks as thoug…