to:deb@aelaw.com means Don Brookhyser (deb@aelaw.com).
-
30 May 2001
Don Brookhyser to Evelyn Kahl, mpa@a-klaw.com, michaelearly@earthlink.net and 57 more
Rehearing on RTO Agreement Limiting Liability
In the April 26 Order regarding the RTO West filing, FERC rejected the Agreement Limiting Liability, reiterating prior holdings that FERC would not approve a tariff limit…
-
26 Apr 2001
Don Brookhyser to Evelyn Kahl Elsesser, mpa@aelaw.com, michaelearly@earthlink.net and 56 more
RTO West order
Here is a copy in Wordperfect of the FERC Order on RTO West. - rt01-35.00b.wpd
-
26 Apr 2001
Kristi M. Wallis to Lincoln Wolverton, mpa@aelaw.com, Don Brookhyser and 223 more
FERC RTO West Order
To Members of the RTO West Stage 2 Market Monitoring, Planning, Provisions/Requirements and Scheduling Content Groups: Hello! In case you haven't already received it, I t…
-
22 Apr 2001
Don Brookhyser to Evelyn Kahl Elsesser, mpa@aelaw.com, michaelearly@earthlink.net and 57 more
RTO West
In case you hadn't heard, the RTO West and TransConnect filings are on the FERC agenda for Wednesday, April 25. Don
-
4 Apr 2001
Kristi M. Wallis to Freedman, Eric (SEA), ambarnes@bpa.gov, Stan Berman and 76 more
Re: RTO West/PRRQ -- RRG Meeting
Hello -- I just wanted to confirm that the work of the PRRQ has been suspended until further notice. (At a minimum the meetings in April will not take place.) In April, t…
-
26 Mar 2001
Kristi M. Wallis to Freedman, Eric (SEA), ambarnes@bpa.gov, Stan Berman and 76 more
RTO West/PRRQ -- RRG Meeting
To Members of the RTO West Provisions and Requirements Content Group: Hello! As you may already know, at last Friday's meeting, the RRG agreed that the RTO West process s…
-
21 Mar 2001
Christine Elliott to Freedman, Eric (SEA), ambarnes@bpa.gov, Stan Berman and 77 more
BRIDGE - RTO West/PRRQ -- 3/22 Provisions and Requirements Content Group Meeting
Hello everyone.? This is Judy on Chris' machine since I didn't get this email. ? Sorry this is so late - but in case any of you need the conference bridge for the meeting…
-
19 Mar 2001
Kristi M. Wallis to Freedman, Eric (SEA), ambarnes@bpa.gov, Stan Berman and 76 more
RTO West/PRRQ -- 3/22 Provisions and Requirements Content Group Meeting
To Members of the RTO West Stage 2 Provisions and Requirements Content Group: Hello! As you know, the next meeting of the Provisions and Requirements Content Group is Wed…
-
16 Mar 2001
Sarah Dennison-Leonard to mschaff@worldnet.att.net, barrie.michael@gov.ab.ca, vipin.prasad@powerpool.ab.ca and 120 more
TIGR - Meeting Reminder and Notice of Posted Materials
Greetings, members of the RTO West Stage 2 Tariff Integration Group. ? This e-mail is to remind you that we will meet on Wednesday, March 21 from 7:30 a.m. to 5:30 p.m. a…
-
15 Mar 2001
Kristi M. Wallis to Freedman, Eric (SEA), ambarnes@bpa.gov, Stan Berman and 75 more
RTO West/PRRQ -- 3/21 Provisions and Requirements Content Group Meeting
To Members of the RTO West Stage 2 Provisions and Requirements Content Group Meeting: Hello! Just a quick reminder that the next meeting of the Provisions and Requirement…
-
11 Mar 2001
Kristi M. Wallis to Freedman, Eric (SEA), ambarnes@bpa.gov, Stan Berman and 75 more
[Fwd: Fwd: CAISO Notice - New Facility Interconnection Policy]
To Members of the RTO West Provisions and Requirements Content Group: Hello! Attached is an e-mail regarding California's New Facility Interconnection Policy. My thanks t…
-
2 Mar 2001
Paul Mohler to Sarah Dennison-Leonard and 16 more
Revised ADR Provision Options
This incorporates what Mary and Don sent and should, subject to any revisions by Sarah, be close to the final product for posting and discussion next week. Please let Sar…
-
2 Mar 2001
Mary Hain to Sarah Dennison-Leonard, GARY A. DAHLKE, Mary Hain and 6 more
ADR Provision
See attached.
-
2 Mar 2001
Paul Mohler to Sarah Dennison-Leonard and 16 more
ADR Options
<<ADR Options Master.rtf>> Hi Sarah, Here is the compilation of ADR-related "options.". I haven't yet received anything from Mary or Don, so these sections are not includ…
-
26 Feb 2001
Paul Mohler to GARY A. DAHLKE, Mary Hain, Don Brookhyser and 10 more
ADR Provision for RTO West Tariff
As agreed at last week's tariff integration group meeting, I will be collecting and organizing the revisions/options we discussed for the RTO West Tariff ADR provision. I…
-
9 Feb 2001
Mary Hain to Don Brookhyser and 2 more
RTO West
I thought you might want to be the Tariff Integration group's liason to the Provisions/Requirements Content Group since that group is dealing with interconnection issues.…