to:chris.germany@enron.com means Chris Germany (chris.germany@enron.com).
-
29 Feb 2000
dkinney@columbiaenergygroup.com to Scott Goodell and 6 more
Re: Updated Mar'00 Requirements Received at 11:25am from CES
Scott--My March '00 first-of-the-month numbers for AGL assumed that the total daily firm load across all 9 pools would average 36,774 dth/day. This would be met by a comb…
-
29 Feb 2000
Chris Germany to Scott Goodell and 2 more
AGL Sonat capacity
We need to add Sonat to our CES retail demand charge sheet. Let's chat.
-
29 Feb 2000
dscott1@columbiaenergygroup.com to Chris Germany, Scott Goodell, christina_sanchez@enron.com
March volumes
Based on the Atlanta requirements for 3/1/00, I have summarized below the volumes I anticipate flowing on the 1st, assuming Enron elects to continue basing ETNG, then Tra…
-
29 Feb 2000
dscott1@columbiaenergygroup.com to Chris Germany, christina_sanchez@enron.com, Scott Goodell and 1 more
Final volumes
Please see the Mar-00 spreadsheet which shows my IBSS withdrawals and what I'm estimating to be the total capacity numbers from ETNG and Transco. David - CES-AGL-Feb00.xl…
-
29 Feb 2000
dscott1@columbiaenergygroup.com to Chris Germany, christina_sanchez@enron.com, Scott Goodell and 1 more
Preliminary volumes
- CES-AGL-Feb00.xls
-
29 Feb 2000
Joan Veselack to John M Singer and 16 more
Re: March Deals - Help!!!! - PLEASE READ
John, I'm sorry my question was not clear. Please advise which Sitara deal tickets you want changed to match the spreadsheet volumes. This will be your decision as a trad…
-
28 Feb 2000
Judy Townsend to Chris Germany
Cove Point LNG Open Season
---------------------- Forwarded by Judy Townsend/HOU/ECT on 02/28/2000 05:24 PM --------------------------- Enron North America Corp. From: Rebecca W Cantrell 02/16/2000…
-
28 Feb 2000
Joe A Casas to Steve Gillespie, Chris Germany, Tricia Bowen
DP&L
Kim, just called and said Dayton has issued an ofo and her new number for the 29th is 963 dth from the 1309. thanx
-
28 Feb 2000
-
28 Feb 2000
bperron@columbiaenergygroup.com to Chris Germany
Re: Beldon & Blake
They worked it out. I'll check on specifics when she gets in. Chris.Germany@enron.com on 02/25/2000 08:55:54 PM Please respond to Chris.Germany@enron.com To: Brian Perron…
-
25 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany
March requirements update
Chris--Attached is an updated version of our March Needs estimates. I know that changes have been made to Nipsco Choice and to CGV requirements. There may be some other c…
-
25 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany
Updated Mar'00 Requirements
Chris--The attached file contains updated needs requirements for March'00. There are a couple of changes as compared to the update that I sent you yesterday. Please note …
-
25 Feb 2000
knovsek@columbiaenergygroup.com to Chris Germany and 6 more
Re: February 2000 Deliveries to CGE
that is correct until monday morning. tuesday may change. Chris.Germany@enron.com on 02/25/2000 11:53:14 AM Please respond to Chris.Germany@enron.com To: Steve.Gillespie@…
-
25 Feb 2000
Joe A Casas to Chris Germany, Steve Gillespie, Tricia Bowen
February 2000 Deliveries to CGE
---------------------- Forwarded by Joe A Casas/HOU/ECT on 02/25/2000 08:35 AM --------------------------- knovsek@columbiaenergygroup.com on 02/25/2000 08:35:04 AM To: "…
-
24 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany
Updated March '00 Needs
Chris--The attached file is an update of our March 2000 needs. There are 3 changes versus the prior version sent earlier today. These are listed below. Please call if you…
-
24 Feb 2000
Sandra Dial to Mechelle Stevens, Jeff W Westover and 2 more
CES Invoicing
I talked with Chris G a little while ago---Two important items to note: * He will be working on the rest of the CES business on Saturday and should be ready for us to bil…
-
24 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany
March '00 Needs update
Chris--Attached is an updated version of our March '00 Needs spreadsheet from the one that I sent you last night. The only changes relative to the previous version are as…
-
24 Feb 2000
Joe A Casas to Chris Germany, Steve Gillespie
MARCH 2000 NEEDS
---------------------- Forwarded by Joe A Casas/HOU/ECT on 02/24/2000 03:55 PM --------------------------- knovsek@columbiaenergygroup.com on 02/24/2000 08:23:19 AM To: "…
-
24 Feb 2000
Joan Veselack to dkinney@columbiaenergygroup.com and 18 more
Re: TCO storage withdawals
I need Joann to pull total 25,000 out of storage for 2/25. Joann already has 15,000 scheduled. I'll schedule 20,000 for choice. We'll be short about 3000, but I was over …
-
24 Feb 2000
Colleen Sullivan to Robin Barbe, Dick Jenkins, Scott Neal and 6 more
GELP, additional information
Attached is additional information from CES regarding administration of the GELP deal. They have given us the contact at CGV to discuss the meter reading process--Joan, c…
-
24 Feb 2000
Clarissa Garcia to Chris Germany
O&R Parcel #'s Released for Columbia Energy March 00
---------------------- Forwarded by Clarissa Garcia/HOU/ECT on 02/24/2000 08:59 AM --------------------------- hboyd@columbiaenergygroup.com on 02/23/2000 04:29:18 PM To:…
-
23 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany and 2 more
March Requirements Spreadsheet
Chris--Sheet2 of the attached file is the latest version of our gas needs for March '00. I have input the daily dth requirements for AGL that I sent you via an earlier e-…
-
23 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany and 6 more
AGL March'00 Requirements Revised
Chris--I apologize for having to revise the numbers I sent a few minutes ago, but I had made an erroneous assumption about the volume of SONAT storage gas that we could w…
-
23 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany and 6 more
AGL March '00 Requirements
Chris--So as not to delay things more than I already have, the table below shows our March '00 Requirements on AGL by pipeline. I will put these values into the spreadshe…
-
23 Feb 2000
dkinney@columbiaenergygroup.com to Chris Germany and 2 more
Upadated March '00 Needs Table
Chris--The attached table is an updated version of the one I sent you last night. The only thing missing is the AGL numbers which I am finalizing now, since we understand…