Skilling resigns
Q3 loss announced
Bankruptcy filing

to:ccobb@akllp.com means ccobb@akllp.com.

  1. 17 Jan 2001

    Kay Mann to Peter J. Thompson, ccobb@akllp.com and 4 more

    Re: Fountain Valley/GE Facility Agreement

    Pete, I intended for you to call me about Rigby's comments to discuss. I don't know that ENA is willing to accept all of what he wants. Please call to discuss implication…

  2. 17 Jan 2001
  3. 5 Jan 2001

    Kay Mann to Peter J. Thompson, ccobb@akllp.com and 2 more

    ABB/GE

    The ABB and GE agreements for CAED were signed by ABB and GE. There was a revision to the ABB agreement (deleting irrelevant data sheets) that Kathleen Carnahan will send…

  4. 5 Jan 2001

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    ABB Agreement - Revised Exhibit A

    ---------------------- Forwarded by Kay Mann/Corp/Enron on 01/05/2001 11:06 AM --------------------------- Fred Mitro@ECT 01/05/2001 09:50 AM To: Kay Mann/Corp/Enron@Enro…

  5. 22 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    Wednesday, Dec 27 11AM CST Conference Call

    ---------------------- Forwarded by Kay Mann/Corp/Enron on 12/22/2000 04:27 PM --------------------------- From: Ben F Jacoby @ ECT 12/22/2000 04:22 PM Sent by: Ben Jacob…

  6. 21 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    Re: Sweetgum/ENA

    otherwise known as CA Development I and CA Development II

  7. 20 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    E-Next Generation CASO1 and CASO2 Comparison of Section 10.8.4

    Gentlemen, This is now back to being the CA Development I and II deal. Please change the name. Please send it to me and Lee Johnson tomorrow, if possible. Kay

  8. 19 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    Re: City of Austin Agreement and Exhibits

    ---------------------- Forwarded by Kay Mann/Corp/Enron on 12/19/2000 07:56 AM --------------------------- Jody Pierce@ECT 12/18/2000 12:31 PM To: Eric Boyt/Corp/Enron@EN…

  9. 13 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com, Dale Rasmussen and 5 more

    LM 6000 breakout contracts

    The end is in sight! The break out contracts for the TurboPark LM's need to be finished up (not news to anyone). Each of these agreements will be between GE and E-Next Ge…

  10. 12 Dec 2000

    Kay Mann to Peter J. Thompson and 6 more

    RE: Performance guarantees

    I like that idea. Do we know what the guarantee is supposed to look like? I don't have the agreement with me (see below). At last word the Coral deal was sidelined. More …

  11. 11 Dec 2000

    lee.johnson@ss.ps.ge.com to Rebecca Walker, lee.johnson@ss.ps.ge.com and 8 more

    RE: LM 6000 Breakout Contract Amounts

    Rebecca, John Ayres and I met today. He wishes to add the interconnect piping between the chiller and cooling tower options in Exhibit N-2 for the ESA Electrobolt Project…

  12. 11 Dec 2000

    Kay Mann to david.onuscheck@us.abb.com and 4 more

    Attached Files

    Here's a good place to start. I'm including a memo from Andrews & Kurth, our outside counsel who drafted the form. Thanks, Kay

  13. 8 Dec 2000

    Kay Mann to Shoemaker, Kent (GEAE), Peter J. Thompson, ccobb@akllp.com and 1 more

    Break out contract form

    There may be a possible bust in 17.4.. Specifically please look at how the math works on the refund due to termination. I think that the baseline should be the maximum li…

  14. 8 Dec 2000

    Rebecca Walker to lee.johnson@ss.ps.ge.com and 8 more

    LM 6000 Breakout Contract Amounts

    Attatched please find a contract payment summary for the LM 6000 turbines. Feel free to contact me with any questions. Rebecca Walker 713-345-7968

  15. 7 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com, lee.johnson@ss.ps.ge.com and 11 more

    ESA facility agreement - close to execution version

    The first facility agreement which needs to be finished is the ESA Facility Agreement. Peter and/or Chris, could you please send/re-send the most recent version with a em…

  16. 7 Dec 2000

    Kay Mann to Dale Rasmussen and 8 more

    Re: Payment schedule for Las Vegas Turbines

    I believe the payment schedule on the spread sheet previously given to AK is correct. If there is a conflict, change order 4 takes precedence as to the timing of the paym…

  17. 7 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    RE: Attached Files

    ---------------------- Forwarded by Kay Mann/Corp/Enron on 12/07/2000 11:19 AM --------------------------- lee.johnson@ss.ps.ge.com on 12/07/2000 11:04:30 AM To: Kay.Mann…

  18. 7 Dec 2000
  19. 6 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    Master contract in Word

    Hi there. Could you send me the Word final of the master GE contract which was the basis for the subsequent facility agreements? I don't have it in Word- just WordPerfect…

  20. 5 Dec 2000
  21. 5 Dec 2000

    Kay Mann to Lisa Bills, Roseann Engeldorf, Rob Taylor and 2 more

    Attached Files

    Just so we are all on the same page, this is the most recent draft of the ESA breakout contract in my files. Thanks, Kay

  22. 4 Dec 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com

    ESA

    Hi Guys, In a conversation with GE today, they indicated that they thought it would be appropriate to insert the performance values in the text of the document, and do aw…

  23. 30 Nov 2000

    Kay Mann to Peter J. Thompson, ccobb@akllp.com and 2 more

    Next to tee up

    Gentlemen, The ESA docs are being reviewed internally for financing and accounting issues. Thanks for turning the docs in such a timely manner. COA is on stand by, due to…

  24. 30 Nov 2000
  25. 28 Nov 2000