from:theresa.hess@enron.com means Theresa Hess (theresa.hess@enron.com).
to:bradley.holmes@enron.com means Bradley Holmes (bradley.holmes@enron.com).
-
12 Mar 2002
Theresa Hess to Gerry Medeles, James Studebaker, Rick Dietz and 13 more
RRS - Proposed Accounting Timeline
During the March 7 meeting we reviewed the 'Proposed Accounting Timeline', which is part of the Project Update dated March 7, 2002. The proposed timeline at the bottom of…
-
8 Mar 2002
Theresa Hess to Shelley Corman, Bradley Holmes
Updates
ADDITIONAL NAESB BOARD NOTES During the Board meeting, a Provisional Activity was moved to the active section of the annual plan. The intent was to only move the partial …
-
6 Mar 2002
-
20 Feb 2002
Theresa Hess to Shelley Corman, Bradley Holmes
NAESB EC Meeting
The February EC meeting (wholesale gas quadrant) will be held Thursday, Feb 21. The agenda is light; I'll attend via conference call. I want to mention a couple of items.…
-
31 Jan 2002
Theresa Hess to Larry Berger, Ramona Betancourt, Rita Bianchi and 27 more
Log of GISB Requests
Attached is the log of requests submitted to GISB (now NAESB) by the Enron interstate pipelines. All of these requests are open and will be addressed by NAESB some time i…
-
25 Jan 2002
Theresa Hess to Shelley Corman, Bradley Holmes
NOPR Comments
FYI -- My comments and notes on the first draft of our comments are red-lined in the attachment. Thanks, Theresa
-
25 Jan 2002
Theresa Hess to Larry Berger, Ramona Betancourt, Lynn Blair and 25 more
GISB Update Meeting
A GISB Update meeting has been scheduled for Tuesday, January 29, 3:00 - 4:00 in conference room 47C1. The agenda is attached. Thanks, Theresa
-
17 Jan 2002
Theresa Hess to Shelley Corman, Bradley Holmes
GISB Board & EC Meeting Attendance
I know money is tight and I'd like to address our attendance at upcoming GISB Board and Executive Committee meetings. Per the new NAESB Bylaws, our seats, and therefore v…
-
9 Jan 2002
Theresa Hess to Shelley Corman, Bradley Holmes and 2 more
Updates
GISB IS NOW NAESB GISB is now officially NAESB. (The actual pronunciation is still undetermined!!!) I may unintentionally go back and forth between the names -- my apolog…
-
5 Jan 2002
Theresa Hess to Shelley Corman, Bradley Holmes
FW: GISB Membership Renewal
FYI -- Below is Scott's response to my question of whether Northern Border will renew their GISB membership. They have renewed their membership for 2002. I'll continue to…
-
4 Jan 2002
Theresa Hess to Shelley Corman, Bradley Holmes and 2 more
NOPR on GISB Standards
The FERC issued a NOPR on December 20, proposing to adopt version 1.5 of the GISB standards (RM96-1-020). In addition to the usual comments, the FERC is requesting commen…
-
14 Dec 2001
Theresa Hess to Larry Berger, Ramona Betancourt, Rita Bianchi and 33 more
GISB Update
Due to the additional activity within ETS and the holidays, we will not hold a GISB Update meeting during the remainder of this year. Hopefully we'll get back on a schedu…
-
19 Oct 2001
Theresa Hess to Shelley Corman, Bradley Holmes
NOPR (RM96-1-019)
CMS Energy (Bill Grygar and Kim Van Pelt) are asking whether the pipelines want to meet to discuss the NOPR and its affect on pipelines. And, whether the pipelines want t…