to:benjamin.bell@enron.com means Benjamin Bell (benjamin.bell@enron.com).
-
29 May 2002
Kurt Anderson to Benjamin Bell and 16 more
Re: FW: GEWE reporting and follow-up
Ben, Rick Winsor's note below has prompted me to provide a timeline with regards to the issue of Zilka's concerns with our Availability calculations. 5/2/02 Rick Winsor s…
-
20 May 2002
Hollis Kimbrough to Ilan Caplan and 6 more
"Vestas Availability"
Ilan, Per your request here is the VA with the leaning towers removed and the 90 day ramp up also removed. Discounting the leaning towers, there is a slight variation (ge…
-
17 May 2002
Hollis Kimbrough to ruth.meyer@enron.com and 4 more
Summarized Counter Values
Ruth, We have had a request from our commercial group for turbine availability numbers with the availability as defined by Vestas. The purpose of this is to present a cha…
-
17 May 2002
Hollis Kimbrough to Ilan Caplan and 6 more
Re: April Availability
Ilan, In order to calculate the VA we need the actual VisuPro counter data since we are using an assumed formula for the Vestas Availability. (See attached for this year …
-
15 May 2002
Hollis Kimbrough to Ilan Caplan, Benjamin Bell and 8 more
Vestas Availability 2002
Ilan, Here is our first attempt at a "Vestas Availability" calculation. We did this for the US 1.5 fleet for each month in the year 2002. There are some things you should…
-
14 May 2002
Jeff Maurer to mike.westbeld@enron.com, craig.christenson@enron.com, Kevin Cousineau and 51 more
Lessons Learned Matrix for 2001 Projects
All, Attached is the Lessons Learned matrix developed from our meeting last week. I want to thank everyone who participated. There were some who wanted to attend but coul…
-
25 Apr 2002
Hollis Kimbrough to Jeff Maurer and 4 more
Capabilities Memo
Jeff, This e-mail is intended to describe our existing and potential capabilities with respect to turbine performance analysis. Using existing SCADA data we presently hav…
-
16 Apr 2002
Joe Chapman to john.admire@enron.com, stan.ballard@enron.com, Benjamin Bell and 13 more
Storm Lake 1 & 2 SCADA password changed
The new password for Storm Lake 1 is: office The new password for Storm Lake 2 is: window Joe
-
10 Apr 2002
Ronald Brzezinski to dan.lindquist@enron.com and 12 more
Mill Run WTG 8 and 9 Counter Discrepancies
Dan, I've supplemented Mark's status with additional detail of the issue. I've included recommendations, including how we avoid this in the future. Please contact me if a…
-
9 Apr 2002
Hollis Kimbrough to dan.lindquist@enron.com and 12 more
WR585 Mill Run Production Data
Dan, This includes some additional comments and explanation of the lost data around the time of the manual counter re-sets. Regards, Hollis