from:center.ets@enron.com means ETS Solution Center, (center.ets@enron.com).
-
15 Mar 2002
ETS Solution Center to sue.rich@enron.com
Updates - ETS and Corporate Change Control
The following additions have been made to this weeks corporate changes.... Mar. 16 From 4:00 - 11:00 p.m., the Corporate Messaging team will take Nahou-msmbx01v Storage g…
-
1 Mar 2002
ETS Solution Center to Diane Becker, sue.rich@enron.com and 228 more
ETS and Corporate Change Control
An additional change control has been entered for this week.... Mar. 2 From 10:30 p.m. through 3/3 at 2:00 a.m., the Corporate Server team will perform maintenance on the…
-
27 Feb 2002
ETS Solution Center to sue.rich@enron.com, ETS Solution Center,
FW: ETS and Corporate Change Control
The following items were discussed in this weeks corporate change control... Feb 27 From 5:00 - 6:00 p.m., Enron Network Services will block all ICMP messages from all In…
-
21 Feb 2002
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Feb. 21 From 11:00 a.m. - 2:00 p.m., Enron Network Services will re-address the IP structur…
-
14 Feb 2002
ETS Solution Center to william.aldinger@enron.com, Dennis Alters, a..ayres@enron.com and 115 more
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Feb. 13 From 5:00 p.m. through 2/14 at 6:00 a.m., the Envision team will perform hardware m…
-
8 Feb 2002
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Feb. 11 From 5:00 p.m. - 6:00 a.m., the Envision team will perform hardware maintenance on …
-
1 Feb 2002
ETS Solution Center to sue.rich@enron.com, Diane Becker
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Feb. 2 From 6:00 - 9:00 a.m., the Envision team will re-index the databases. This outage wi…
-
1 Feb 2002
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Feb. 2 From 6:00 - 9:00 a.m., the Envision team will re-index the databases. This outage wi…
-
31 Jan 2002
ETS Solution Center to sue.rich@enron.com, Diane Becker
Envision System Outage
IMPORTANT MESSAGE! PLEASE READ! FILENET SYSTEM OUTAGE JANUARY 31, 2002 The FileNet Envision System will be down Thursday, January 31st beginning at 5:00 p.m. It is necess…
-
31 Jan 2002
Envision System Outage
IMPORTANT MESSAGE! PLEASE READ! FILENET SYSTEM OUTAGE JANUARY 31, 2002 The FileNet Envision System will be down Thursday, January 31st beginning at 5:00 p.m. It is necess…
-
30 Jan 2002
VoiceMail Issue
The Telephony Team performed maintenance over the weekend which impacted the user voicemail that moved from 3AC. Although the Telephony Group is working on restoring the …
-
25 Jan 2002
ETS Solution Center to sue.rich@enron.com, ETS Solution Center,
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Jan 28 Beginning at 6:00 p.m., the Telephony team will remove the telephone switch from 3AC…
-
25 Jan 2002
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Jan 28 Beginning at 6:00 p.m., the Telephony team will remove the telephone switch from 3AC…
-
24 Jan 2002
Outlook Tips
The following information and tips are provided to assist you as you're working with Outlook: The Outlook mail file size restriction has been removed. However, if you hav…
-
16 Jan 2002
ETS Solution Center to william.aldinger@enron.com, Dennis Alters, a..ayres@enron.com and 112 more
Remote Access Changes
There have been numerous changes over the last few months with regard to how we remotely access the Enron computing environment. As part of the ongoing consolidation of r…
-
10 Jan 2002
ETS and Corporate Change Control
The following items was presented in this week's corporate change control.... Jan 10 From 10:00 a.m. - 1:00 p.m., the Messaging team will upgrade mailsweeper servers NAHO…
-
4 Jan 2002
ETS Solution Center, to ETS Solution Center,, sue.rich@enron.com
ETS and Corporate Change Control
The following item was presented in this week's corporate change control.... Jan. 3 From 6:00 - 6:30 p.m., the Corporate server team will move cluster notes nahou-us06 an…
-
2 Jan 2002
ETS Solution Center, to ETS Solution Center,
EHR ONLINE IS UP!
EHR is back online. Thank you for your patience. Thank you, ETS Solution Center - Houston, at 713-345-4745 ETS Solution Center - Omaha, at 402-398-7454
-
2 Jan 2002
ETS Solution Center, to ETS Solution Center,
EHR ONLINE
We are currently experiencing issues with EHR online. We are aware of these issues and are working to get them resolved quickly. Thank you for your patience and we will n…
-
28 Dec 2001
ETS and Corporate Change Control
The following item was presented in this week's corporate change control.... Dec. 28 Beginning at 5:00 p.m., the Corporate server team will remove domain controllers CORP…
-
27 Dec 2001
ETS and Corporate Change Control
The following item was presented in this week's corporate change control.... Jan. 7 From 7:00 a.m. through 1/11 at 5:00 p.m., Facilities will perform the annual maintenan…
-
20 Dec 2001
ETS Solution Center, to sue.rich@enron.com, ETS Solution Center,
Risk Acceptance in eRequest!!
Announcing The New ETS Categories Of Risk Acceptance In eRequest!! All deviations from the Corp/ETS IT standards will require appropriate business justification and can n…
-
19 Dec 2001
Server Maintenance - today at 5:00PM
Please note! We have to perform emergency maintenance on the Quick Place server (nahou-lnww01) today at 5:00PM. This means that Change Control and other Quick Place sites…
-
14 Dec 2001
ETS Solution Center, to ETS Solution Center, and 2 more
ETS and Corporate Change Control
The following change has been put on hold. I will notify you when it is rescheduled. Dec. 14 From 10:30 p.m. through 12/15 at 2:00 a.m., Enron Network Services will remov…
-
13 Dec 2001
ETS and Corporate Change Control
The following items were presented in this week's corporate change control.... Dec. 14 From 8:00 a.m. - 5:00 p.m., the EDI team will install and upgrade Oracle to version…