from:stanley.cocke@enron.com means Stanley Cocke Jr. (stanley.cocke@enron.com).
-
29 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
West Services Short on 7/1 and 7/2
Gentlemen, West Services is short 19mw around-the-clock on Sunday and light-load Monday (7/1-7/2), as well as 23mw on-peak Monday (7/2). We are short in SP15, at $80 on-p…
-
28 Jun 2001
Stanley Cocke Jr. to Phillip Platter and 6 more
New Counterparty
Gentlemen, Looks like we are going to add a new generator to our program very soon. We will be the SC for Bay Environmental Management, hopefully starting on the July 3rd…
-
18 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Real-Time Generation for 6/19
Group, Here's what's available to sell real-time for Tuesday, 6/19. Sierra Forest Products: VESTAL_6_WDFIRE 2mw available during off-peak hours, 5mw prescheduled, total o…
-
13 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com and 2 more
Revised Real-Time Generation for 6/14
The additional 20mw that Harbor needs to sell is actually for HE11-13, not HE10-12 as previously indicated. --------------------------------------------------------------…
-
13 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com and 2 more
Real-Time Generation for 6/14
Group, Here's what's available to sell real-time for Wednesday, 6/14. Harbor: HARBGN_7_UNITS and HARBGN_7_PL2X3 15mw must be sold from the steam turbine (HARBGN_7_PL2X3),…
-
12 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Real-Time Generation for 6/13
Group, Here's what's available to sell real-time for Wednesday, 6/13. Harbor: HARBGN_7_UNITS 80mw available, 0 prescheduled, HE1-24, SP15, costs are roughly $110. Wheelab…
-
8 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Real-Time Generation for Sunday/Monday, 6/10-6/11
Group, Here's the plan for Sunday/Monday: Only submit supplemental bids for the generators if a Stage 1 emergency is called. This is due to the ISO's ability to ramp the …
-
8 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Revised Real-Time Generation for Saturday 6/9
There are a few changes to Saturday's schedule, so please disregard my previous email. ------------------------------------------------------ Group, The plan has slightly…
-
8 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Real-Time Generation for Saturday 6/9
Group, The plan has slightly changed for submitting supplemental bids for our generators for Saturday, 6/9. The plan is as follows: Only submit supplemental bids for the …
-
7 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Supplementals for 6/8-6/9
Group, Due to the recent drop in day-ahead prices, we have a few counterparties who scheduled less than their P-max generation. Therefore, we need to submit supplemental …
-
1 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Harbor Pmax
Group, This evening, Friday, 6/1, you will need to call the ISO real-time desk to have them change Harbor Cogen's Pmax. This morning, we had them change it from 80mw to 8…
-
1 Jun 2001
Stanley Cocke Jr. to shift.portland@enron.com
Delano Length for Saturday
Group, Please take note that Delano is long on Saturday, 6/2. Please sell 7mw for HE5, and 27mw for HE6-24. Also, please check in with the control room to make sure they …