  1. 6 Jun 2001

    Ruth Concannon to Eric LeDain, Todd Busby, Louis Dicarlo and 3 more

    Sithe Independence Restructuring Update

    At Eric's request, I have set up a meeting to update him on the possible restructuring scenarios for the Sithe/Independence deal. Please attend the meeting, if you can. D…

  2. 5 Jun 2001

    Ruth Concannon to Eric LeDain, Geoff Storey, Ed McMichael Jr. and 1 more

    RE: Sithe TCPL transport

    I am free in the morning until 11:00 am. I think that Todd Busby should sit in on the meeting, since he is been so involved in the discussions with Sithe. Ruth

  3. 16 May 2001

    Ruth Concannon to Jeff Donahue, Timothy J. Detmering, Charles Ward and 17 more

    TransCanada's 2001/2002 Tolls and Tariff Application -- Sithe/Independence Capacity

    At the request of the NEB, TransCanada has sent out a notice to shippers and interested parties for comments on TCPL's application addressing the proposed Mainline Servic…

  4. 21 Dec 2000

    Ruth Concannon to Dan J Hyvl and 6 more

    Transaction Document --- Sithe/Independence 400 MW Off-Peak Turndown --- January 2001

    Dan, Here is the final agreement for your initials. Hopefully, you are back from your meeting. Jeff is leaving at 3:00 pm today and my hope is that he can sign the docume…

  5. 29 Nov 2000

    Ruth Concannon to bfernandez@sithe.com, bscherfling@sithe.com, mgrady@sithe.com and 10 more

    This Is A Procedure Test For Future MW Turndown Deals --- Case I

    I made a few other changes after I had time to think about our discussion yesterday. Let's get another conference call to discuss why these points are important to Enron.…

  6. 1 Nov 2000

    Ruth Concannon to joliver@sithe.com, mrosenberg@sithe.com and 4 more

    Revised Transaction Documents

    We found a couple of typo's and ommissions under the November delivery points. Here is a new set of documents. Ruth

  7. 1 Nov 2000

    Ruth Concannon to joliver@sithe.com, mrosenberg@sithe.com and 6 more

    Sithe/Independence On & Off Peak MW Turndown Transaction Agreements

    Jason -- Attached are draft transaction agreements for the on and off peak periods for the months of November and December. Regarding the side letter agreement which addr…

  8. 23 Oct 2000

    Ruth Concannon to joliver@sithe.com and 6 more

    Sithe/Independence On & Off Peak MW Turndown Transaction Agreements

    Jason -- Attached are the documents with the changes incorporated. As we discussed on Friday, the plant maintenance will run into November. Since we sold gas to the plant…

  9. 6 Oct 2000

    Ruth Concannon to mrosenberg@sithe.com, joliver@sithe.com and 6 more

    Sithe / Independence MW Turndown for Off-Peak & On-Peak Periods

    Attached are draft documents that address entering into separate transactions for the off-peak and on-peak periods. As you can see, these documents are similar to the dra…

  10. 28 Sep 2000

    Ruth Concannon to Dan J Hyvl and 2 more

    Sithe Gas Resale Prices

    Dan, These are what we need for the filling in of the blanks for the gas resale agreements: September ---- We are down to one day now (September 30). Price will be posted…

  11. 27 Sep 2000

    Ruth Concannon to mrosenberg@sithe.com, joliver@sithe.com, bhughes@sithe.com and 14 more

    Sithe Independence --- 570 MW Turndown Transaction Documents

    Attached are the project documents that incorporate your changes from last night. The following is a brief list of the changes, so that these documents can be reviewed mo…

  12. 26 Sep 2000

    Ruth Concannon to mrosenberg@sithe.com, joliver@sithe.com, bhughes@sithe.com and 12 more

    Re: Sithe Independence -- Sept and Oct transaction agreements attached.

    Here are revised draft transaction agreements for September and October. I believe that we have revised all the small volume changes that are indicated on the schedule th…

  13. 26 Sep 2000

    Ruth Concannon to mrosenberg@sithe.com, joliver@sithe.com, bhughes@sithe.com and 14 more

    Sithe Independence -- 570 MW Turndown Transaction

    Attached is the Second Revised Draft of the bullet point procedures and an updated schedule of the volumes that will be transacted for during the October outage. The chan…

  14. 22 Sep 2000

    Ruth Concannon to mrosenberg@sithe.com, joliver@sithe.com, bhughes@sithe.com and 12 more

    Draft Sithe Independence MW Turndown Transaction Agreement --- October 2000

    Attached is a draft transaction agreement for October 2000, the assumed maintenance month during the MW Turndown time period. The boiler-plate language is identical to th…