from:preston.ochsner@enron.com means Preston Ochsner (preston.ochsner@enron.com).
-
26 Oct 2001
Preston Ochsner to Rogers Herndon and 18 more
RE: ERCOT physical delivery update
Rogers, Here's a summary of today's meeting and other discussions I've had with the parties involved. Does everyone have the information they need? Services Management - …
-
25 Oct 2001
Preston Ochsner to rogers.'612@enron.com, Joseph Wagner, Narsimha Misra and 14 more
ERCOT Physical Delivery Update Agenda
1. Does everyone have the information they need? ? Services Management - Scott ? Site Profile Desk - Mallik ? Load Profile Desk - Michael ? Power Desk - Preston ? Schedul…
-
24 Oct 2001
-
24 Oct 2001
Preston Ochsner to John M. Forney
ERCOT Swap
John, Your new daily swap seems to be generating a lot of interest. I've gotten calls from friends at both Reliant and Dynegy in the last 24 hours about it. Good job.
-
1 Aug 2001
Preston Ochsner to Murray P. O'Neil and 2 more
ERCOT settlements protocol
have you had a chance to outline the requirements?
-
1 Aug 2001
Preston Ochsner to George Phillips, Gary Nelson, Chris Stokley and 1 more
FW: Meeting Thurs. 8/2 on Texas retail issues
would like to have you there
-
31 Jul 2001
Preston Ochsner to Murray P. O'Neil, Jeff Merola, George Phillips and 13 more
ERCOT Physical Delivery Progress Report
I need your help to make September 1 physical delivery happen. Please talk amongst yourselves and set up meetings as necessary. Just keep me in the loop. Rogers Herndon a…
-
25 Jul 2001
Preston Ochsner to Murray P. O'Neil, Jeff Merola, George Phillips and 7 more
ERCOT Physical Delivery Progress Report
While cautious of the issues we face, I'm very encouraged by your experience and your willingness to help. I tried to summarize the issues discussed in the meeting this a…
-
24 Jul 2001
Preston Ochsner to Chris Stokley, Murray P. O'Neil and 2 more
ERCOT settlements protocol
as promised. once you've had time to digest, let me know what you think our IT requirements will be to set up the Access database
-
24 Jul 2001
Preston Ochsner to Chris Stokley, Murray P. O'Neil and 2 more
FW: Confirms for Final Review
as promised, below are drafts of the standard Texas confirms (2)
-
24 Jul 2001
-
24 Jul 2001
-
24 Jul 2001
-
24 Jul 2001
Preston Ochsner to Jeffrey Miller and 4 more
RE: ERCOT Physical delivery issues
can we meet Wednesday sometime between 10 and 12? there are a couple of people from the Portland office that I'd like to attend. we can probably benefit from their knowle…
-
2 Jul 2001
Preston Ochsner to Chris Stokley
intrazonal congestion
did you guys ever find your summary of intrazonal congestion charges?
-
21 May 2001
Preston Ochsner to patricia.collins@enron.com, Mark Courtney and 6 more
ERCOT Constraints
Thought you might find this helpful. I think the last slide is especially good. It shows the excess generation in the South, the South-North limit and the "tight" scenari…