from:mitch.robinson@enron.com means Mitch Robinson (mitch.robinson@enron.com).
to:stuart.zisman@enron.com means Stuart Zisman (stuart.zisman@enron.com).
-
20 Apr 2001
Mitch Robinson to Stuart Zisman and 6 more
Re: Westinghouse - State Group Claims
I concur legally and contractually. That was the intent of the agreement. All we gave up was our right to LD claims for construction schedule and initial performance, not…
-
20 Apr 2001
Mitch Robinson to Stuart Zisman and 6 more
Re: Westinghouse - State Group Claims
I concur contractually and legally. However, given that our total claim is on the order of $0.4 From: Stuart Zisman@ECT on 04/20/2001 09:34 AM To: Ross Newlin/HOU/EES@EES…
-
8 Dec 2000
Mitch Robinson to rogerrippy@akllp.com and 12 more
Re: Schedule Updates
See below. My comments are in quotation marks "". Mitch "Rippy, Roger" <rogerrippy@akllp.com> on 12/07/2000 09:29:26 PM To: <Mitch.Robinson@enron.com> cc: <stuart.zisman@…
-
7 Dec 2000
Mitch Robinson to Stuart Zisman and 6 more
Monroe Contract
It appears that we did not cancel the second station service contract with Monroe County. This second contract was for construction power supply, and is now used as an em…
-
5 Dec 2000
Mitch Robinson to Don Miller and 4 more
SWPC Transfer
Don - Please forward on to Allegheny. In order to facilitate the smooth transfer of the assets, to close out the turbine purchase contracts, and to provide Allegheny with…
-
27 Nov 2000
Mitch Robinson to Stuart Zisman, Don Miller and 4 more
Re: Westinghouse
Stuart - Attached are the chain of e-mails on the agreement. I recommend a direct red-line between the two agreements (what I sent them, and what they sent back) before w…
-
22 Nov 2000
Mitch Robinson to Kay Mann and 4 more
Enron Issues Letter
Some changes. Can you review and advise? Mitch
-
2 Nov 2000
Mitch Robinson to Don Miller, Stuart Zisman and 4 more
Gleason (Shelby) Transmission Upgrade
Larry Soderquist has forwarded to me a TVA schedule of the Shelby upgrade. If it's not already in Deal Bench, let me know and I'll forward it down. Scheduled completion i…
-
10 Oct 2000
Mitch Robinson to Stuart Zisman and 4 more
Revised Wheatland Proposal
Stuart - This is the finalized DRAFT agreement with Cinergy for the maintenance of the Wheatland switchyard. I recommend including it and the e-mail below in the due dili…
-
3 Oct 2000
Mitch Robinson to Don Miller, Mike J Miller, Stuart Zisman and 3 more
ENRON Lincoln 7 Generator Failure Status Report 10/03/00
Attached is the executive summary and recommendations from GE's Root Cause Analysis (RCA) for the Lincoln #7 generator failure. I recommend including it in the Due Dilige…
-
29 Sep 2000
Mitch Robinson to Don Miller and 8 more
Lincoln Center Improvements
Don - I recommend putting the attached e-mails and attachments in the DD room. We've also had verbal discussions with the IEPA to verify that the retest can be postponed.…