4 Mar 2002
market_relations@nyiso.com to Benjamin Rogers
NYISO Back-Up Disptach Testing - Tuesday, March 5, 2002
The NYISO Back-Up Dispatch System is scheduled to be tested on Tuesday, March 5,2002_. The test will begin at about 10:30 a.m. and last for approximately one hour. Securi…
-
1 Mar 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - Problems with SCD
Dear Market Participants, The NYISO encountered problems with SCD last night as a result of the code changes to transfer the Rockland Electric load to PJM. The NYISO ente…
-
28 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - NERC Implementation of E-Tag Version 1.7
Dear Market Participants, NERC announced a delay in the implementation of E-Tag Version 1.7 from March 6, 2002 to April 10, 2002. This delay is necessitated by vendor int…
-
27 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - Comprehensive Mitigation filing date delayed to allow time for review
Dear Market Participants, To allow sufficient time for review and incorporation of comments, the NYISO has delayed the expected filing date of the Comprehensive Mitigatio…
-
27 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - New External Bid Caps for Economic Priority of Pre-Scheduled Transactions - Update
Dear Market Participants, In an order issued yesterday, the FERC approved NYISO's initial implementation of Pre-Scheduled Transactions, including new bid caps for externa…
-
27 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - New External Bid Caps for Economic priority of Pre-Scheduled Transactions - Clarification
Dear Market Participants, Please note that the message below was sent to provide advance notice of expected changes to NYISO bid caps for external transactions. These cha…
-
26 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - New External Bid Caps for Economic priority of Pre-Scheduled Transactions
Dear Market Participants, In order to provide economic priority for Pre-Scheduled Day Ahead External Transactions, the NYISO will be implementing new Bid Caps for Day-Ahe…
-
19 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - TCC Market
Dear Market Participants, The ISO is reviewing its financial assurance policy with regard to collateral requirements for participation in the T.C.C. market. The ISO will …
-
15 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO Offices Closed
The NYISO offices will be closed for normal business on Monday, February 18 in observance of Presidents Day. We will re-open on Tuesday, February 19. Regards, Customer Re…
-
15 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - Software Release - February 26, 2002
Dear Market Participants, The following changes to the NYISO OASIS/MIS/CSS systems will be released on February 26, 2002. Preliminary changes to the MIS database will be …
-
14 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - Delay in Round 1 Sale of One-Year TCCs in the Spring 2002 Auction
Dear Market Participants: The NYISO has decided to delay the Round 1 Sale of One-Year TCCs in the Spring 2002 TCC Auction by one day due to the Presidents Day holiday on …
-
12 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - Initial Spring 2002 TCC Auction Bid and Offer Forms
Dear Market Participants: The NYISO has encountered delays in the posting of the Initial Spring 2002, TCC Auction Bid and Offer Forms. The NYISO will post the forms as so…
-
11 Feb 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO Back-Up Dispatch System Testing
The NYISO Back-Up Dispatch System is scheduled to be tested on Tuesday, February 12 ,2002. The test will begin at about 10:30 a.m. and last for approximately one hour. Se…
-
30 Jan 2002
market_relations@nyiso.com@ENRON to Paul D. Thomas
NYISO - E-Tag Changeover
Dear Market Participants, NERC recently announced the plan for changing the E-Tag System from Version 1.67 to Version 1.7. That changeover is currently scheduled for Marc…
-
29 Jan 2002
market_relations@nyiso.com@ENRON to Paul D. Thomas
NYISO - Common Market Announcement
Dear Market Participants, Attached are a press release announcing an agreement between NYISO and ISO-NE to form a common market and a copy of the signed agreement. If you…
-
18 Jan 2002
market_relations@nyiso.com to rring@ees.enron.com
Martin Luther King Day - January 21, 2002
Dear Market Participants: Please be advised that the NYISO will be observing Martin Luther King Day, on Monday, January 21, 2002. As this holiday is not observed by all c…
-
18 Jan 2002
market_relations@nyiso.com to Paul D. Thomas
Martin Luther King Day - January 21, 2002
Dear Market Participants: Please be advised that the NYISO will be observing Martin Luther King Day, on Monday, January 21, 2002. As this holiday is not observed by all c…
-
18 Jan 2002
market_relations@nyiso.com to Benjamin Rogers
Martin Luther King Day - January 21, 2002
Dear Market Participants: Please be advised that the NYISO will be observing Martin Luther King Day, on Monday, January 21, 2002. As this holiday is not observed by all c…
-
15 Jan 2002
market_relations@nyiso.com@EES to rring@ees.enron.com
NYISO - ICAP Meeting January 17th - Conference Call Information and link to meeting material
Dear ICAP Working Group Members, Regarding the January 17th ICAP WG, please click on the attached link to view the NYISO Calendar where you will see the the meeting's Con…
-
15 Jan 2002
market_relations@nyiso.com@ENRON to Paul D. Thomas
NYISO - ICAP Meeting January 17th - Conference Call Information and link to meeting material
Dear ICAP Working Group Members, Regarding the January 17th ICAP WG, please click on the attached link to view the NYISO Calendar where you will see the the meeting's Con…
-
15 Jan 2002
market_relations@nyiso.com@ENRON to Benjamin Rogers
NYISO - ICAP Meeting January 17th - Conference Call Information and link to meeting material
Dear ICAP Working Group Members, Regarding the January 17th ICAP WG, please click on the attached link to view the NYISO Calendar where you will see the the meeting's Con…
-
7 Jan 2002
market_relations@nyiso.com to rring@ees.enron.com
NYISO Back-Up Dispatch System Testing
The NYISO Back-Up Dispatch System is scheduled to be tested on Tuesday, January 8 ,2002. The test will begin at about 10:30 a.m. and last for approximately one hour. Secu…
-
7 Jan 2002
market_relations@nyiso.com to Paul D. Thomas
NYISO Back-Up Dispatch System Testing
The NYISO Back-Up Dispatch System is scheduled to be tested on Tuesday, January 8 ,2002. The test will begin at about 10:30 a.m. and last for approximately one hour. Secu…
-
7 Jan 2002
market_relations@nyiso.com to Benjamin Rogers
NYISO Back-Up Dispatch System Testing
The NYISO Back-Up Dispatch System is scheduled to be tested on Tuesday, January 8 ,2002. The test will begin at about 10:30 a.m. and last for approximately one hour. Secu…
-
2 Jan 2002
market_relations@nyiso.com@EES to rring@ees.enron.com
NYISO - New TIE list software update
Dear Market Participants, The transition to the new TIE list software is complete. The 'OLD' TIE list will be disabled and the NYISO will post exclusively to the new list…