from:mark.walker@enron.com means Mark V Walker (mark.walker@enron.com).
-
22 Apr 2002
Mark V Walker to Jeff Duff, Mark Fisher, Hollis Kimbrough
Repair/Maintenance counter behavior
---------------------- Forwarded by Mark V Walker/EWC/Enron on 04/22/2002 05:16 PM --------------------------- Garth Ripton 04/22/2002 07:09 AM To: Paul Landers/EWC/Enron…
-
19 Apr 2002
Mark V Walker to Garth Ripton, Kevin Cousineau, Paul Landers and 6 more
Availability Impact of Faults / Errors in 1.5 MW Turbine Projects
Executive Summary AvailDocument is the deliverable given to Erik Ellis to support Business Development turbine sales efforts. I send it you to expedite coordination betwe…
-
18 Apr 2002
Mark V Walker to Kurt Anderson, danielle.lewis@enron.com and 4 more
Clear Sky/Indian Mesa Production and availability for Mar 2002. Work Request complete.
Executive Summary The attached file, Clearskypavout0302, contains the production and availability data based on Visupro recorded data. The turbine production in March and…
-
17 Apr 2002
Mark V Walker to Ilan Caplan and 4 more
Re: Clipper Availability Edits
One other comment. It is still not clear how MT values in excess of the 100 hours will be handled. Is EWC to be penalized for these "excess hours"? Hopefully this will be…
-
17 Apr 2002
Mark V Walker to Ilan Caplan and 4 more
Re: Clipper Availability Edits
You asked if it was really true that the counters other than ST are stored in Visupro. The answer is yes. DT, RT, MT, EOT, LOT, and WOT are incrementing counters recorded…
-
17 Apr 2002
Mark V Walker to Ilan Caplan, Olivia Martinez and 4 more
Re: Proposed Clipper Availability
There are several ambiguities and operational issues with this definition. SOT: First, the phrase "available to operate without a status condition or fault that would oth…
-
16 Apr 2002
Re: downtime allocation document and parameter list
Please skim through the attachment below to see if you have any concerns about how the faults should trigger in the future.
-
16 Apr 2002
Mark V Walker to Kurt Anderson, george.griese@enron.com and 4 more
Availability and kWh Data From March 2002 that will go into Owner Report
Kurt, You asked for the availability of Clear Sky by 11 am. The attached file provides this and will form the final Onwer Report when the Manual Logs are fully integrated…
-
15 Apr 2002
Mark V Walker to Patricia Hunter, Rabi Sahoo and 2 more
Re: Visupro Upload Status Spreadsheet
Additional information: For the next week the 1.5 project priorities for the System Performance Group are: 1) Load up most recent Mon files for April at site indicated in…
-
15 Apr 2002
Mark V Walker to Patricia Hunter, Rabi Sahoo and 4 more
Visupro Upload Status Spreadsheet
To expedite the use of this spreadsheet I onlyl show the most recent (April) files. Late March files will be added in future releases of this spreadsheet.
-
11 Apr 2002
Mark V Walker to Leonard Mason and 6 more
Re: OH Reference on February Monthly Report
The 3.8 hours was added to the January and not Febuary OH term for WTG 11. The 3.8 hours was added back because the Emergency Oil Loss was interpreted by me to be a failu…
-
8 Apr 2002
Mark V Walker to Hollis Kimbrough and 4 more
Manual Log Data Recieved For March 2002
The attached file shows the Manual Log Data (in red) that is overdue and required to complete Owner Reports. The SCADA data is still under review. It will be added to thi…
-
3 Apr 2002
Mark V Walker to Hollis Kimbrough, marion.horna@enron.com, Kurt Anderson and 5 more
Detailed Guidance On 1.5 Availability Computation. Do not send Procedure to owners until Field Ops approves it for release to the Owners
Executive Summary Marion Horna and Kurt Anderson requested an explanation of how the EW 1.5 Availability was computed. In addition, Barry Riffe and Jeff Duff have express…