from:l..nicolay@enron.com means Christi L. Nicolay (l..nicolay@enron.com).
to:d..baughman@enron.com means Edward D. Baughman (d..baughman@enron.com).
-
27 Nov 2001
Christi L. Nicolay to Rogers Herndon, Kevin M. Presto, James D. Steffes and 20 more
Entergy joins SETRANS (southern, etal) RTO
Entergy has joined the SE Trans RTO (Southern, etal). I will review the FERC filing; however, an Entergy rep called me today to ask for Enron's support stating that the n…
-
7 Nov 2001
Christi L. Nicolay to Susan Lindberg, Michael Roan, Kerry Stroup and 24 more
Enron responses to MISO filings
On Monday, Enron filed these responses to MISO filings at FERC: -- Protested MISO's proposed $1000 penalty on accepted requests that are subsequently withdrawn by the cus…
-
2 Nov 2001
Christi L. Nicolay to Larry Valderrama, Don Baughman Jr., Edward D. Baughman and 2 more
MISO proposed $1000 penalty
Susan discussed with you this bad $1000 proposed penalty for one week or more in length transmission requests that are accepted by MISO, but not confirmed by the Customer…
-
29 Oct 2001
Christi L. Nicolay to Susan Lindberg, Harry Kingerski, James D. Steffes and 30 more
Enron response in Dynegy v. ComEd
Attached is Enron's response against Dynegy's argument that Firm LD contracts cannot be used as designated sources for network transmission pursuant to the FERC OATT. Com…
-
25 Oct 2001
Christi L. Nicolay to Guy Sharfman, Harry Kingerski, James D. Steffes and 20 more
RE: NEED COMMENTS-Dynegy v. ComEd response
Thanks, Guy. Your point is valid; however, you are right that we don't want to emphasize the intra-day hourly part in this pleading since a firm power contract is necessa…
-
25 Oct 2001
Christi L. Nicolay to Harry Kingerski, James D. Steffes, Rogers Herndon and 19 more
NEED COMMENTS-Dynegy v. ComEd response
Attached in very draft form is EPMI/EES's response against Dynegy's request that ComEd not allow Firm LD to be designated as a Network transmission resource. Please provi…
-
26 Sep 2001
Christi L. Nicolay to Susan Lindberg, Richard Shapiro, James D. Steffes and 40 more
EPMI's response to SE RTO mediation
Attached is EPMI's FERC-filed response to the SE RTO mediation report. The response discusses all characteristics/functions of our initial preferred RTO structure for the…
-
24 Sep 2001
Christi L. Nicolay to Sarah Novosel, Donna Fulton, Joe Connor and 18 more
draft EPMI response to SE RTO mediation report
Please provide any comments by COB Tues. 9/25. Thanks.
-
11 Sep 2001
Christi L. Nicolay to Kevin M. Presto, Louise Kitchen, John J Lavorato and 49 more
Judge's Final SE RTO Mediation Report + CN summary
The ALJ submits her report to FERC to obtain FERC review of the Southeast Power Grid platform that resulted from the mediation. ** JUDGE'S FINAL RECOMMENDATIONS: FERC sho…