  1. 9 Mar 2002

    Kevin Hyatt to Ron Matthews, Arnold L. Eisenstein, l..smith@enron.com and 2 more

    Sun Devil project costs

    When: Thursday, March 14, 2002 10:30 AM-11:30 AM (GMT-06:00) Central Time (US & Canada). Where: EB1334 *~*~*~*~*~*~*~*~*~*

  2. 28 Feb 2002

    Kevin Hyatt to Ron Matthews

    FW: Sun Devil

    -----Original Message----- From: Gadd, Eric Sent: Thursday, February 28, 2002 2:07 PM To: Hyatt, Kevin Subject: FW: Sun Devil . . . unless you can address with OBAs . . .…

  3. 20 Feb 2002
  4. 19 Feb 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Sarah Haden and 12 more

    Sun Devil meeting

    we will cancel these weekly meetings until we get some marketing contracts signed. Any updates will be taken care of via weekly reports or in Steve Harris' weekly staff m…

  5. 19 Feb 2002

    Kevin Hyatt to Darrell Schoolcraft, Ron Matthews

    MMBtu content

    Guys, is there a way you can tell me what the MMBtu content of the gas is coming into TW from NorthWest Pipeline, TransColorado, and then what it is at Gallup? I'm lookin…

  6. 5 Feb 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Sarah Haden and 8 more

    Sun Devil meeting today cancelled

    Due to conflict with Stan Horton's meeting this afternoon (2/5). We will reconvene at the regular time on 2/12.

  7. 31 Jan 2002

    Kevin Hyatt to Ron Matthews, Eric Gadd, James Centilli

    meet w/ E Gadd on new Sun Devil case economics

    When: Friday, February 01, 2002 8:30 AM-9:00 AM (GMT-06:00) Central Time (US & Canada). Where: Eric's ofc *~*~*~*~*~*~*~*~*~*

  8. 16 Jan 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 13 more

    weekly Sun Devil update meeting

    We've changed the weekly scheduled meeting to accommodate more people's calendars: When: every Tuesday When: 3pm Where: 15c1

  9. 14 Jan 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 9 more

    Sun Devil update moved to tues 1/15

    due to Conf room conflict (Ken Lay needed our room!). We'll do it on Tues at 3:30 in 15c1. We'll update you on the Phoenix meetings last week plus the Desert Crossing pro…

  10. 7 Jan 2002

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 11 more

    Sun Devil Update moved to Tues 3:30 pm 15c1

    this change is for today only as I have a meeting conflict on another project. Let me know please if you can't make it. We have some interesting developments to discuss i…

  11. 17 Dec 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 11 more

    sun devil weekly meeting update

    Due to the holidays and vacation schedules, we will hold off having any further weekly project meetings until Monday, January 7 at 3:30pm. Plan on meeting in ECN 15c1. th…

  12. 19 Nov 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 9 more

    Sun Devil Update no meeting 11/19 or 11/26

    No meeting today but here's the update. We had our meeting with AZ Public Service on Friday 11/16. Here's the highlights: 30 year term is not a deal killer Rates & fuel a…

  13. 8 Nov 2001

    Kevin Hyatt to Susan Wadle, Dennis Alters, Larry Campbell and 10 more

    Sun Devil update meeting Monday 11/12 cancelled

    I will be travelling on 11/12 so here's the update: Sonoran Pipeline - Received offer price from Kinder Morgan to purchase capacity on their project. Marketing - Panda En…

  14. 8 Nov 2001

    Kevin Hyatt to Ron Matthews

    RE: Sun Devil delivery pressure

    What would be the pressure if we don't install stations 1.5 and Kingman? My thinking is we might not have enough market at Cal Border to require those stations.

  15. 7 Nov 2001

    Kevin Hyatt to Ron Matthews, Ben Asante and 4 more

    Sun Devil delivery pressure

    Ron, can you please verify for me the delivery pressure in pounds for volume off the Sun Devil project at the juncture of Panda's lateral at the El Paso interconnect outs…

  16. 7 Nov 2001

    Kevin Hyatt to Ben Asante, Ron Matthews and 12 more

    Sun Devil Fuel

    Ben and Ron-- Following up on our meeting today, I need to know what my negotiation parameters are regarding the fuel charge for our Sun Devil Project. How much (if any) …

  17. 7 Nov 2001

    Kevin Hyatt to Ron Matthews, Ben Asante and 12 more

    Sun Devil Fuel

    Ben and Ron-- Following up on our meeting today, I need to know what my negotiation parameters are regarding the fuel charge for our Sun Devil Project. How much (if any) …

  18. 2 Nov 2001

    Kevin Hyatt to Ron Matthews

    FW: Maximum Hourly Flow

    -----Original Message----- From: Smith, Buzz Sent: Thursday, November 01, 2001 3:47 PM To: Hyatt, Kevin Cc: Alters, Dennis Subject: Maximum Hourly Flow To calculate maxim…

  19. 29 Oct 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 11 more

    postponed Sun Devil update for Monday 10/29

    We'll do the regularly scheduled update next week 11/5 when we will hopefully have more market feedback. Right now we are still working to secure market commitment and de…

  20. 26 Oct 2001

    Kevin Hyatt to Ron Matthews, Darrell Schoolcraft

    Sun Devil Talking Points for Albuquerque

    Attached are the notes for your meeting in Albuquerque. Please avoid discussing the cost figures (it tends to reach competitive ears). If anyone has any questions, or any…

  21. 15 Oct 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 7 more

    Revised meeting location for Sun Devil update (again)

    Due to a room schedule conflict-- We're back to our original location at 3pm in 42c1 today. thanks kh

  22. 15 Oct 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 7 more

    Location change - Sun Devil weekly meeting

    sorry, but some of you will get this twice.

  23. 8 Oct 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 7 more

    Sun Devil meeting

    Please plan on meeting for the weekly Sun Devil update today (Monday 10.8) at 3pm in 42c1. thx kh

  24. 28 Sep 2001

    Kevin Hyatt to Dennis Alters, Larry Campbell, Doug Cebryk and 9 more

    No Sun Devil update meeting Monday 10/1

    We expect the cost estimate to be completed 10/2 and will likely begin the weekly meeting Monday 10/8.