from:eric.gillaspie@enron.com means Eric Gillaspie (eric.gillaspie@enron.com).
-
30 Jan 2001
Eric Gillaspie to Greg Brazaitis and 2 more
Rio Nogales
Greg, I have forwarded you via inter-office mail 2 execution originals of the Rio Nogales Interconnect Agreement for your further handling. Thanks, Eric Gillaspie 713-345…
-
29 Jan 2001
Eric Gillaspie to Greg Brazaitis, james.haden@enron.com and 2 more
Rio Nogales
Greg, The latest version as discussed. Thanks Eric Gillaspie 713-345-7667 Enron Building 3886
-
29 Jan 2001
Eric Gillaspie to Greg Brazaitis and 4 more
Re: Rio Nogales Schematic
Greg, Looks good. The updated ICA for your further handling. Eric Gillaspie 713-345-7667 Enron Building 3886 Greg Brazaitis 01/29/2001 12:38 PM To: Eric Gillaspie/HOU/ECT…
-
29 Jan 2001
Eric Gillaspie to Greg Brazaitis and 4 more
Rio Nogales ICA
Greg, Gerald and I went over the document once more this morning and he has approved it for your further handling. Thanks, Eric Gillaspie 713-345-7667 Enron Building 3886
-
26 Jan 2001
Eric Gillaspie to Greg Brazaitis and 4 more
Rio Nogales ICA
Greg, Attached for your review is the Interconnect Agreement with Rio Nogales incorporating the changes from the recent meeting. Gerald is out this afternoon and has not …
-
22 Jan 2001
Eric Gillaspie to Mark D Thorne and 2 more
Re: HPL INTRASTATE STORAGE CONTRACTS
Mark, Could you pull the contracts listed below and send them to me. Thanks, Eric Gillaspie 713-345-7667 Enron Building 3886
-
16 Jan 2001
Eric Gillaspie to william.e.nicas@exxon.com and 4 more
Oneida Field Amendment
Bill, Attached for your further handling, review, and comment is the Amendment to that certain Interruptible Gas Purchase Agreement between Houston Pipe Line Company and …
-
10 Jan 2001
Eric Gillaspie to Gerald Nemec
Bi-directional form
As requested, Eric Gillaspie 713-345-7667 Enron Building 3886
-
9 Jan 2001
Eric Gillaspie to Greg Brazaitis and 2 more
RNP Interconnect Agreement
Greg, Attached for your review and further handling is the Rio Nogales Power Project, L.P. Interconnect Agreement which incorporates the changes we discussed this morning…
-
9 Jan 2001
Eric Gillaspie to Greg Brazaitis and 2 more
BVP Interconnect Agreement
Greg, Attached for your review and further handling is the Brazos Valley Project, L.P. Interconnect Agreement which incorporates the changes we discussed this morning. Th…
-
5 Jan 2001
Eric Gillaspie to Greg Brazaitis and 2 more
ICA for RNP
Greg, Attached for your further handling is the revised Interconnect Agreement b/n HPL and RNP. Thanks, Eric Gillaspie 713-345-7667 Enron Building 3886
-
5 Jan 2001
Eric Gillaspie to Greg Brazaitis and 2 more
ICA for BVP
Greg, Attached for your further handling is the revised Interconnect Agreement b/n HPL and BVP. Thanks, Eric Gillaspie 713-345-7667 Enron Building 3886