from:earl.chanley@enron.com means Earl Chanley (earl.chanley@enron.com).
-
18 Mar 2002
Earl Chanley to Kimberly Watson and 2 more
Agave IC
Kim Received an as-built package for the interconnect on West Texas Lateral. Material matches up but there is not a hydro test and test log for the installation. This is …
-
14 Feb 2002
-
7 Nov 2001
Earl Chanley to Rene Bickerstaff, Kimberly Watson, ryan.woods@enron.com and 4 more
RE: Need Reimbursable Agreements
I do not have a copy of the agreement for either project. Marketing should have as they made the deals. Kim, can you furnish Rene with a copy of the agreements? Thanks Ea…
-
1 Nov 2001
Earl Chanley to Kimberly Watson, Rene Bickerstaff, ryan.woods@enron.com
RE: Need Reimbursable Agreements
Kim Can Marketing furnish the agreement for this project. I'm not in the possession of one. Thanks Earl C.
-
4 Oct 2001
Earl Chanley to Mark McConnell
FW: Atoka Interconnect
Mark Engineer reviewed Agaves list and this is the comments. Earl
-
1 Oct 2001
Earl Chanley to David Lanning, dragsdal@ypcnm.com and 4 more
Engineering Standards for Measurement
David or Paul Finally able to get to site. Would you print out a copy for Jim Williams. Theses are the Latest Standards for measurement, give me a call if Questions. Than…
-
26 Sep 2001
Earl Chanley to robert.geheb@enron.com and 4 more
P.A. Agave I/c
Robert Attached is a marketing project for an I/C for TW. Please route for approvals. The Marketing rep is Kim Watson. Thanks Earl
-
19 Sep 2001
Earl Chanley to dlanning@ytcnm.com and 4 more
FW: Atoka Cost
David This is the equipment for the proposed interconnect. The Enron "e"nternet is down at this time and I will e-mail your the Engineering Standards when it is running. …
-
16 Aug 2001
Earl Chanley to Michelle Lokay
(no subject)
Here is the estimate that I came up with for work still to be done by Enron when EOG is done. Please take a look at this and forward it on to Michelle Lokay if you are sa…
-
3 Aug 2001
Earl Chanley to Michelle Lokay and 2 more
FW: EOG Pronghorn I/C bldg.
Michelle The material for the I/C is ready to ship to EOG. Do we go ahead and send the material or hold till they pay? The material is in the Roswell CDC and will remain …
-
31 Jul 2001
Earl Chanley to Michelle Lokay
EOG Pronghorn Material cost
Michelle The cost for material ordered for this work order is $94,126.27. the attached spread sheet is from the SAP accounting system and invoices will be routed to Marke…
-
17 Jul 2001
Earl Chanley to Rich Jolly and 8 more
RE: EOG Pronghorn Meter Station
George Kneisley and possibly Ben Tanner will also attend this meeting for back up with any measurement issues. Earl Chanley
-
16 Jul 2001
Earl Chanley to Bob Burleson and 16 more
RE: FOG Pronghorn
Bob Met with the Team on Friday (713-01) to review the location and possible options for the Duke I/C at WT-1. The concern with the 4" restriction and the 30 mm they want…
-
31 Jan 2001
Earl Chanley to Michelle Lokay, Bob Burleson and 8 more
Re: Pogo Interconnect
There must be something I have missed. The work order was submitted to Marketing for approvals and is in SAP but has not been released to date. The middle of February in-…
-
31 Jan 2001
Earl Chanley to Michelle Lokay, Bob Burleson and 8 more
Re: Pogo Interconnect
There must be something I have missed. The work order was submitted to Marketing for approvals and is in SAP but has not been released to date. The middle of February in-…
-
13 Nov 2000
Earl Chanley to Bob Burleson and 16 more
Re: EOG Pronghorn Location
To aggressive. Will get to I/C when people are avib. Wil try but only can do so much Earl Chanley
-
8 Nov 2000
Earl Chanley to Bob Burleson and 10 more
Re: EOG Pronghorn Location
Bob EFM with Radio (not sure if power is at site). and model of EFM woul effect cost. Estimated cost for a package installed is in the $35,000 range. Earl Chanley