from:david.owen@enron.com means David Owen (david.owen@enron.com).
-
27 Nov 2001
David Owen to Chris Hilgert and 2 more
RE: Construction Expedition Letter
Chris, Why are they removing language that let's us "..confer with Gulf's project management...and subcontractors..."? What's to hide? Remember, lack of such information …
-
21 Nov 2001
David Owen to Gerald Nemec, Chris Hilgert, c..alexander@enron.com
Dave Owen comments to Gulf letter
My comments attached... Jim, any comments / suggestions?? Dave
-
16 Nov 2001
David Owen to Scott Josey and 4 more
Summary of discussion with Gerald
Scott, I talked to Gerald after our telecon as you requested ----- here's the summary: I repeated to Gerald my reply when you asked my opinion regarding the best way to a…
-
7 Nov 2001
David Owen to Chris Hilgert, Gerald Nemec
New version of Station 13 Summary
Lads Latest version...found a minor typo. Dave
-
30 Oct 2001
David Owen to Brian Redmond, Garry D. Wilson, Gerald Nemec
FW: Napoleonville Storage No. 1
All, FYI Dave
-
20 Aug 2001
FW: BCCKOP Operating Agreement
Gerald, How should I handle this? Is this something normally done during the legal (risk mgmt., etc.) review by someone in your group, RAC....??? Gracias! Dave
-
7 Aug 2001
-
25 Jul 2001
-
19 Jul 2001
FW: Bridgeline Application Deficiencies
Gerald, This is the e-mail with Larry's comments regarding dewatering prior to issuance of the operating permit. Dave
-
19 Jul 2001
FW: Bridgeline's response to deficiency letter
Napoleonville permit response below.....
-
17 Jul 2001
David Owen to Gerald Nemec, Troy Denetsosie, Garry D. Wilson
Updated: Mtg RE: Enron Napoleonville Contract Committments
When: Thursday, July 19, 2001 2:30 PM-3:00 PM (GMT-06:00) Central Time (US & Canada). Where: EB3567 *~*~*~*~*~*~*~*~*~*
-
12 Jul 2001
David Owen to Gerald Nemec, Troy Denetsosie, Garry D. Wilson
Mtg RE: Enron Napoleonville Contract Committments
When: Tuesday, July 17, 2001 2:30 PM-3:00 PM (GMT-06:00) Central Time (US & Canada). Where: EB3567 *~*~*~*~*~*~*~*~*~*
-
2 Jul 2001
David Owen to Patrick Johnson and 2 more
RE: LRCI tract
Pat, I suggest asking Gerald Nemec for some guidance. Gerald, any recommendations as to who we should contact for help with ROW matters? Gracias, Dave
-
21 May 2001
Northwest Pipeline Facilities Agreement
Gerald- Attached is NWPL's proposed facilities agreement. We're still working on final scope/costs, but I thought you might want to take a look at the idemnification, gov…
-
11 Apr 2001
M & H Enterprises
Gerald, We intend to use M & H for general engineering and technical services. Payment will be made consistent with rate sheets or at a day rate of $725. Please let me kn…