16 Jan 2002
Darrell Schoolcraft to Team Laguna, Jerry Graves, Rick Smith and 1 more
RE: Station 6/602 request
I called Steve Richards at the station and this unit is in plant held for future use. I told him to get started. This is for unit 602 down from 1/16 to 5/31. We will stil…
-
3 Oct 2001
Darrell Schoolcraft to Rich Jolly and 22 more
RE: FW: FW: Gallup Peak Power Avoidance Data Points
I certainly agree. This should be fine. Let me know. DS
-
23 Sep 2001
Darrell Schoolcraft to Randy Rice, Dan Pribble, John Shafer and 23 more
Gallup Compressor Station
Gas Day September 23, 2001 Gallup Compressor Station will be doing run testing. Capacity for San Juan will stay at 800,000 mmbtu/d. Gas Day September 24, 2001 Gallup Comp…
-
21 Sep 2001
Darrell Schoolcraft to Arnie Bailey, Rich Jolly, roger.osborn@enron.com and 23 more
RE: Smart Pig Runs In Sections 7 & 8
Gas controllers on duty were Gayle Henley and Bart Mondon. They both did a great job. Thanks DS
-
10 Aug 2001
Darrell Schoolcraft to controllers.dl-ets@enron.com, Rich Jolly, Arnie Bailey and 8 more
FW: UPDATE - TW Smartpigging Project L-187 & 176
This is for smart pig runs. I have already let PNM know that Rio Puerco will not be able to flow to TW for the 18th -- 20th. Thanks DS
-
9 Aug 2001
Darrell Schoolcraft to Arnie Bailey, Team Gallup, Gallup-Sta4, Team and 23 more
RE: Caliper Tool Run on Section 5
At this time I see no problems. DS
-
30 Jul 2001
Darrell Schoolcraft to David Roensch, Jerry Graves and 14 more
RE: TW Outages 2002
I will be here Tuesday only this week. Tuesday works for me. ds
-
3 Jul 2001
Darrell Schoolcraft to Rick Smith, controllers.arnold@enron.com
RE: Gallup transformer
I will keep gas control informed on this outage. ds
-
21 Jun 2001
Darrell Schoolcraft to Gallup-Sta4, Team, Jerry Graves, Rich Jolly and 1 more
RE: station4 outage req.
1. On your first request for down time next week. You may have an opportunity this weekend 23, or 24 depending on the volumes. We can communicate this to your Team Friday…
-
31 May 2001
Darrell Schoolcraft to Kenneth Young and 38 more
Re: TW 1090 Project Schedule - Stations 1-4
We need know everyday units need to be taken down and for how long. Depending on system conditions we may have to allocate. DS From: Kenneth Young 05/31/2001 09:36 AM To:…
-
31 May 2001
Darrell Schoolcraft to Kenneth Young and 38 more
Re: TW 1090 Project Schedule - Stations 1-4
Ken, We currently have a unit down at Station 4. If you need to work on something now is the time to do it and not wait until June. DS From: Kenneth Young 05/30/2001 11:5…
-
31 May 2001
Darrell Schoolcraft to Kenneth Young and 38 more
Re: TW 1090 Project - Stations 1-4
What is the time frame these units need to be down. There are no postings for volume deductions. Please someone give me some ideas. Thanks Ds From: Kenneth Young 05/30/20…
-
24 May 2001
Darrell Schoolcraft to james.moore@enron.com and 26 more
Re: Concern - Possible Change In Smartpigging Dates
Right now it looks like we can run station 9, station 7, station 6 or station 5. We will just have to see what we have scheduled for the day. This will allow us to set ou…
-
24 May 2001
Darrell Schoolcraft to Arnie Bailey and 22 more
Re: Concern - Possible Change In Smartpigging Dates
You are correct looking at the models Ken Chow ran before he left was between 175 to 225 this will allow the pig to move approx. between 5 to 6 miles an hour. DS From: Ar…
-
24 May 2001
Darrell Schoolcraft to Max Brown and 22 more
Re: Concern - Possible Change In Smartpigging Dates
Is there a reason we think we will need to run station 8. I think with the volumes we will have to move to insure 6 miles and hour for the smart pig will be approx. 100 t…