from:arnold.eisenstein@enron.com means Arnold L Eisenstein (arnold.eisenstein@enron.com).
-
29 Oct 2001
Arnold L Eisenstein to Larry Campbell
FW: ENRON-TRANSWESTERN/PARTICULATES
resend in case the first one didn't come on friday
-
26 Oct 2001
Arnold L Eisenstein to Larry Campbell, William Kendrick and 2 more
FW: ENRON-TRANSWESTERN/PARTICULATES
this was not the letter I attached to Shudeish
-
30 Apr 2001
Arnold Eisenstein to Kevin Hyatt
Tranwestern/Your Letter Dated April 26
---------------------- Forwarded by Arnold L Eisenstein/ENRON_DEVELOPMENT on 04/30/2001 04:46 PM --------------------------- jose.dumenigo@ps.ge.com on 04/30/2001 01:32:0…
-
25 Apr 2001
Arnold L Eisenstein to Larry Campbell
FW: Updated Information Regarding EPA's Current Thinking on Draft MACT Content
in case you didn't receive
-
22 Apr 2001
Arnold Eisenstein to Jerry D. Martin and 32 more
Red Rock Weekly Report
1. ACTIVITIES: a. Video conference held with GE/NP to refine turbine SOW b. Marketing held a "bid" last week ending on Friday; results are encourging as multible bids wer…
-
6 Apr 2001
Arnold Eisenstein to d.martin@enron.com and 32 more
Red Rock Weekly Report
1. ACTIVITIES: a. FERC Certificate is filed. No questions have been received to date. b Turbine Compressor Letter of Intent was issued to GE/NP for 4 PGT25+ for the Red R…
-
15 Mar 2001
Arnold Eisenstein to Jerry D. Martin and 30 more
Red Rock Weekly Report
1. ACTIVITIES: A. Discussions with TW on critical items in order to finalize FERC application: Navajo Environmental has requested a Threatened & Endangered Species (T&E) …
-
10 Mar 2001
Arnold Eisenstein to Jerry D. Martin and 30 more
Red Rock Weekly Report
1. ACTIVITIES: a. Completed site visit to all stations and evaluation of existing facilities b. Discussions with TW on critical items in order to finalize FERC applicatio…
-
15 Feb 2001
Arnold L Eisenstein to Larry Campbell and 2 more
Re: loading range of the RB211
You will need this!! confirming our conversation......reserve emissions for a nom 350KW (gas if prime - diesel if standby) gen set at each site
-
14 Feb 2001
Arnold L Eisenstein to Larry Campbell
TRANSWESTERN RB211
---------------------- Forwarded by Arnold L Eisenstein/ENRON_DEVELOPMENT on 02/14/2001 07:37 AM --------------------------- "John J. Mcilvoy" <john.mcilvoy@rolls-roycees…
-
9 Feb 2001
Arnold L Eisenstein to Larry Campbell and 8 more
Re: TW Mainline Expansion