  1. 16 Aug 2000

    Kay Mann to Herman Manis, Lisa Bills and 6 more

    VEPCO

    Virginia Power has raised a question about wanting some type of guaranty or other form of performance security should an Enron LLC sign the contract. What can we propose …

  2. 16 Aug 2000

    Kay Mann to Jeffrey Keenan, Heather Kroll, swanita_99@yahoo.com and 6 more

    Public Staff Data Request

    In speaking with Allyson, she believes we need to have the responses the Public Staff's data request no later than sometime next week. The Staff wants to have a meeting o…

  3. 15 Aug 2000

    Kay Mann to dutch_bumgardner@dom.com, john_maple@dom.com, Heather Kroll and 6 more

    Aug 15 draft of CEC

    I am attaching a redline of a revised version of the document formerly known as the PPA. This is compared against the August 7 draft. I am sending it without anyone else …

  4. 15 Aug 2000

    Kay Mann to Heather Kroll, Ozzie Pagan, Jeffrey Keenan

    Another try...

    Here's the clean version (no redline) of the most recent draft of the PPA. I have no idea what happened with the redline, but I'll try to get a decent one done.

  5. 15 Aug 2000

    Kay Mann to Ozzie Pagan, Heather Kroll, Jeffrey Keenan

    Evolving VEPCO contract

    Here's the most recent version of the document formerly known as the PPA: Kay

  6. 10 Aug 2000

    Kay Mann to Allyson Duncan and 12 more

    RE: NCNG Delivery Points

    Allyson, Thank you for your prompt response. Can you describe the process and timing for filing a project update? Thanks, Kay "Duncan, Allyson" <aduncan@kilstock.com> on …

  7. 10 Aug 2000

    Kay Mann to Nancy Wodka and 2 more

    VEPCO PPA.DOC

    Hi Nancy, I am planning to make the changes which arose out of our meeting with VEPCO. When we met with them, we agreed that we would accept all the changes in this draft…

  8. 9 Aug 2000
  9. 9 Aug 2000

    Kay Mann to Allyson Duncan and 10 more

    Re: NCNG Delivery Points

    Allyson, Thank you for the email. It seems to stop in mid sentence, so I was wondering if maybe something got deleted? We have an interest in having the application for t…

  10. 9 Aug 2000

    Kay Mann to Heather Kroll, Ozzie Pagan, Jeffrey Keenan

    NCNG Delivery Points

    I don't think she finished her thought. I'll check with Allyson on this. Kay

  11. 8 Aug 2000

    Kay Mann to karen.carter@enron.com and 20 more

    Re: Austin turbines - transfer from West LB facility

    I agree that we need a "standard" way of moving the turbines (and transformers) into other structures. Both the GE contract for the LM 6000's and the ABB transformer cont…

  12. 7 Aug 2000
  13. 6 Aug 2000

    Kay Mann to Lisa Bills, Herman Manis, Roseann Engeldorf and 7 more

    VEPCO PPA.DOC

    The attached is the version of the contract which is under internal review and has therefore not been sent to VEPCO. Warning: the black lining may not be much help to you…

  14. 4 Aug 2000

    Kay Mann to Allyson Duncan and 8 more

    VEPCO/City of Rocky Mount

    Allyson, As you know, we have had discussions with the City of Rocky Mount regarding possibly buying gas from them for the new power plant in Edgecombe County. Evidently,…

  15. 4 Aug 2000

    Kay Mann to Nancy Wodka and 4 more

    VEPCO Tax Language

    Nancy, Please incorporate this language from Enron's Tax Guys. Thanks, Kay

  16. 2 Aug 2000

    Kay Mann to Heather Kroll

    (no subject)

    Here's something to work with: Virginia Power and ENA agree that Virginia Power will authorize and pay for the ________ so that the queue (que?) spot for necessary interc…

  17. 31 Jul 2000

    Kay Mann to Heather Kroll, Ozzie Pagan, Jeffrey Keenan and 1 more

    VEPCO capacity contract issues

    I've made a list of issues Heather and I have discussed based on VEPCO's suggested revisions. Some of the issues are commercial, some legal, some just reminders. Comments…

  18. 31 Jul 2000

    Kay Mann to Heather Kroll, Jeffrey Keenan

    501D5A/VEPCO

    I'm trying to locate a copy of the contract to purchase the 501D5A turbine to see if we need to be aware of any issues in the contract. Do you have a copy? If not, I can …

  19. 31 Jul 2000

    Kay Mann to Heather Kroll, Jeffrey Keenan, Christi L Nicolay

    VEPCO's form interconnection agreement

    Attached is the form interconnection agreement provided by Virgina Power, for your information, review, etc. It is a new form which is currently under review by VEPCO. Ka…

  20. 27 Jul 2000

    Kay Mann to mscolo@poynerspruill.com, kraber@electricities.org and 6 more

    Revised option agreement

    Gentlemen, I have made the revisions to paragraphs 16 and 22 as suggested. I have also changed the state designation of the Tarheel notary to Texas. If this version is ac…

  21. 27 Jul 2000

    Kay Mann to mscolo@poynerspruill.com and 8 more

    RE: Land Option

    I've just returned to the office, and will handle the changes as suggested. Thanks, Kay "Colo, Mike" <MSColo@POYNERSPRUILL.COM> on 07/25/2000 04:59:10 PM To: "'Kay.Mann@e…

  22. 27 Jul 2000

    Kay Mann to Heather Kroll, Ozzie Pagan, Jeffrey Keenan

    RE: Land Option

    ---------------------- Forwarded by Kay Mann/Corp/Enron on 07/27/2000 09:41 AM --------------------------- "Colo, Mike" <MSColo@POYNERSPRUILL.COM> on 07/25/2000 04:59:10 …

  23. 25 Jul 2000

    Kay Mann to Herman Manis and 2 more

    Re: IGNORE the last one - Vepco POWER PURCHASE

    Tomorrow is bad for me, but Thursday afternoon or anytime Friday is good. Kay

  24. 25 Jul 2000

    Kay Mann to Herman Manis, Lisa Bills, Matthew Berry and 8 more

    CLEAN VEPCO PPA.DOC

    Attached is the current draft of the PPA for the VEPCO deal for your information, review, etc. Kay

  25. 25 Jul 2000

    Kay Mann to Allyson Duncan and 12 more

    Re: CPCN Update

    Allyson, Thank you for the update. Is not having the CPCN an absolute bar to beginning construction? What are the risks? Thanks, Kay "Duncan, Allyson" <aduncan@kilstock.c…