to:fred.mitro@enron.com means Fred Mitro (fred.mitro@enron.com).
-
23 Jan 2001
Anita DuPont to Robin Kittel, Bill Rust, Steve Walton and 21 more
Agenda for Transmission Roundtable on Wednesday, January 24, 2001
Sorry everyone, I guess I am having my Monday morning today. Here are the attachments.
-
22 Jan 2001
Christi L Nicolay to Tom Chapman, Ben Jacoby, Ozzie Pagan and 25 more
Duke files Interconnection Procedures at FERC
On 12/17/00, Duke filed interconnection procedures at FERC. It did not file a pro forma Interconnection Agreement. The procedures are generally fine and include: Posting …
-
22 Jan 2001
Kay Mann to Rebecca Walker, Fred Mitro
E-Next Generation Docs
I didn't go back and check, but I believe the bills of sale or the assignment/assumption agreement may help, as one of these should have the serial number. I think you ma…
-
22 Jan 2001
Ben Jacoby to Chris Booth, Fred Mitro and 2 more
Blue Dog Change Order
Chris: Are we already paying GE for the change order? Is GE pushing to have this resolved? Pending input from Kay, I would like to hold off documenting it until we deal w…
-
18 Jan 2001
Kay Mann to Kathleen Carnahan, Ben Jacoby, Fred Mitro
Escrow instruction letters
---------------------- Forwarded by Kay Mann/Corp/Enron on 01/18/2001 07:38 AM --------------------------- "Paradee, Lari" <Lparade@INTERGEN.com> on 01/17/2001 08:58:01 P…
-
17 Jan 2001
Kay Mann to Carolyn Campbell, John Keffer, Ben Jacoby and 9 more
CAED I and II closing (Intergen)
Just wanted to confirm that we are moving ahead for the Intergen closings. Lisa, I spoke with Karl, and he has promised to let me know if there any hitches on their end. …
-
16 Jan 2001
Kay Mann to Rebecca Walker and 6 more
Re: Letter of Credit from GE for LM6000s
The Intergen LOC should be in CAED I and CAED II's names, issued after closing on the 18th. The PSCO deal team should handle the PSCO LOC, which should be in the name of …
-
15 Jan 2001
Ben Jacoby to Kay Mann and 6 more
Re: Revised 7EA Turbine Letter Agreement
Kay: My only comment is in Section 5(e). The specific reference to Article 19.2 of the Facility Agreement should be deleted, and the paragraph should read "...as may be r…
-
11 Jan 2001
Carolyn Campbell to Kay Mann and 4 more
Revised 7EA Turbine Letter Agreement
<<2RZ504!.DOC>> <<2RZ5RED.DOC>> Kay: We have enclosed clean and marked copies of a revised draft of the 7EA turbine letter agreement reflecting revisions from the draft p…
-
11 Jan 2001
-
11 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Ben Jacoby and 2 more
CA Development
Attached are electronic versions of the final docs for the CA Development transactions. If there are no other comments we will get the Enron signatures. How many original…
-
10 Jan 2001
Carolyn Campbell to Kay Mann and 10 more
Closing Checklist
<<2RR404!.DOC>> Kay: An updated closing checklist for the ENA / SEL transaction is attached. Carolyn M. Campbell King & Spalding 713-276-7307 (phone) 713-751-3280 (fax) c…
-
10 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Catherine Clark and 6 more
Notice of Approval of Facility Agreements / Escrow Status
It looks like things are moving forward on the Intergen/CA deal. If we can verify the status of the wires we will want to give notice today. Fred Mitro is working on this…
-
10 Jan 2001
Kay Mann to f_mitro@hotmail.com, Fred Mitro, Ben Jacoby
Location of turbines
Fred, As we discussed, we need the physical addresses where the equipment in TurboPark is being stored. As I understand it the equipment is in at least a couple of places…
-
10 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Catherine Clark and 4 more
CA I and CA II assignment agreements
Attached are assignment and assumption agreements for CA I and CA II. The only changes to the GE form were those changes suggested by Lisa, and a little clean up. Kay
-
10 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Catherine Clark and 2 more
Revised notices for CA I and CAII
I'm attaching the notices for CA I and CA II. Please pay particular attention to CA II, since it is the first time it has been circulated. Obviously, we will need to inse…
-
10 Jan 2001
Kay Mann to Lisa Bills and 10 more
RE: CA Development - revised documents
Hi Lisa, I'm back, and will finish up these docs this am. The notice provision does not require that all the closing documents be completed as of the date of the notice, …
-
8 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Roger Ondreko and 3 more
CA Development - revised documents
Here's a set of CA I revised docs. If these are ok, we will get CA II lined up as well. I'm on the road tomorrow, but should be back in the office on Wednesday am. Kay
-
8 Jan 2001
Kay Mann to Ben Jacoby and 2 more
Re: Ltr to SEL enclosing Facility Agreements
I had Ozzie sign it, and it has been sent to Carolyn. Kay
-
8 Jan 2001
Kay Mann to Ben Jacoby and 2 more
Ltr to SEL enclosing Facility Agreements
Do you want to print, sign and fax, or shall I take to Janet or someone else to sign? Kay
-
8 Jan 2001
Kay Mann to Carolyn Campbell and 4 more
CA Development Agreements
Carolyn, These should be the correct blacklines to include in the transmittal with the GE facility agreements. Ben/Fred, Carolyn and I are coordinating the delivery of th…
-
8 Jan 2001
Kay Mann to Ben Jacoby, Fred Mitro
RE: CA Development
---------------------- Forwarded by Kay Mann/Corp/Enron on 01/08/2001 12:58 PM --------------------------- KWiemer@milbank.com on 01/08/2001 12:13:24 PM To: Kay.Mann@enro…
-
8 Jan 2001
Kay Mann to John Keffer, Carolyn Campbell, Fred Mitro and 1 more
Override letter related to the Blue Dog turbines
I believe this letter is applicable to the Blue Dog turbines:
-
8 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Catherine Clark and 5 more
RE: CA Development
The DCMA states in 6.01 that notice can be given by the designee. Karl thinks the notice must come from the DCM (ENA). Does it matter? I don't mind ENA giving the notice …
-
5 Jan 2001
ABB transformer/CAED
Fred, Is the ABB transformer currently in existence (already delivered)? Thanks, Kay