  1. 10 May 2001

    Marc De La Roche to Doug Leach, V Charles Weldon

    Re: Fuel Specification Requirements

    HHV is not the proper terminology, Gross Heat of Combustion is. The following is for Light diesel. First number is min, second is max. Jet fuel should be in the same ball…

  2. 10 May 2001

    John Kiani to V Charles Weldon

    RE: Stagecoach Pricing

    Charlie, We are waiting on TGP to hear how their discussions with management have played out. We,ll definitely update you when we get more information. Let me know if yo…

  3. 10 May 2001

    V Charles Weldon to John Kiani

    Re: Gas Pricing Update

    John, Based on yesterday's (5/9/01) curves, and applying spreads from our previous quotes, the new updated notionl bid is $4.51/MMBTU. Let me know if you need any more as…

  4. 10 May 2001

    John Kiani to V Charles Weldon

    Stagecoach Contract

    Charlie, Here is the Stagecoach contract that I promised you. Let me know if you have any questions. Regards, John

  5. 10 May 2001

    John Kiani to V Charles Weldon

    Gas Pricing Update

    Charlie, Can you please update the gas price for the National Fuel deal in New York? Our customer called and would like updated deal economics from us. This was the one t…

  6. 10 May 2001

    Marc De La Roche to Doug Leach, V Charles Weldon

    Re: Fuel Specification Requirements

    HHV is not the proper terminology, Gross Heat of Combustion is. The following is for Light diesel. First number is min, second is max. Jet fuel should be in the same ball…

  7. 10 May 2001

    V Charles Weldon to Doug Leach

    Re: Fuel Specification Requirements

    Doug, Thanks for the info. I have passed it along. I have one more question regarding heating values. Do you know what the LHV and HHV values are for #2 and jet fuel? I f…

  8. 10 May 2001

    V Charles Weldon to Mike Coleman

    Re: Fuel Specification Requirements

    Mike, I noticed that your name was not on the distribution list for these exchanges so I am forwarding them to you to catch you up. I have faxed the #2 Diesel Fuel specs …

  9. 10 May 2001

    Doug Leach to V Charles Weldon and 4 more

    Re: Fuel Specification Requirements

    Yesterday I faxed a copy of Colonial Pipeline's specifications for fungible low sulfur diesel fuel (74 grade) to Mark Breese. That spec sheet is indicative of the specs f…

  10. 10 May 2001

    V Charles Weldon to Matthew Tezyk and 10 more

    Re: Fuel Specification Requirements

    Matt, Thank you very much for the info. I have forwarded the specs on to Doug Leach who will be responsible for ordering the fuel oil. I asked him to identify any spec pa…

  11. 10 May 2001

    V Charles Weldon to Doug Leach and 4 more

    Re: Fuel Specification Requirements

    Doug, Attached is the (long-awaited) spec for the 200K gallons of low-sulphur #2 Fuel Oil to partially refill the tank at the Ft. Pierce facility in Florida. As the attac…

  12. 10 May 2001

    Rusty Stevens to Ruth Concannon and 4 more

    Pipeline Contractors

    I got this message for a contractor that might be interested in working with us on the lateral. Steve Thome had good luck with them on a water line and wanted to pass the…

  13. 9 May 2001

    Matthew Tezyk to V Charles Weldon and 10 more

    Re: Fuel Specification Requirements

    Charles, Attached below is the fuel oil specification. Our Engineering group has reviewed all Vendor and Air Permit requirements, and the sheet labeled "Fuel Oil Spec" is…

  14. 9 May 2001

    Nick Hiemstra to V Charles Weldon and 2 more

    Midway gas supply

    FYI. The email below changes things for years 4 & 5 because we would need to have gas for the summer months. Charlie - please proceed with getting the pricing as we talke…

  15. 9 May 2001

    Doug Leach to V Charles Weldon and 4 more

    Re: Fuel Specification Requirements

    Yesterday I faxed a copy of Colonial Pipeline's specifications for fungible low sulfur diesel fuel (74 grade) to Mark Breese. That spec sheet is indicative of the specs f…

  16. 9 May 2001

    Rusty Stevens to Ruth Concannon and 4 more

    Pipeline Contractors

    I got this message for a contractor that might be interested in working with us on the lateral. Steve Thome had good luck with them on a water line and wanted to pass the…

  17. 9 May 2001

    Matthew Tezyk to V Charles Weldon and 10 more

    Re: Fuel Specification Requirements

    Charles, Attached below is the fuel oil specification. Our Engineering group has reviewed all Vendor and Air Permit requirements, and the sheet labeled "Fuel Oil Spec" is…

  18. 9 May 2001

    Nick Hiemstra to V Charles Weldon and 2 more

    Midway gas supply

    FYI. The email below changes things for years 4 & 5 because we would need to have gas for the summer months. Charlie - please proceed with getting the pricing as we talke…

  19. 9 May 2001

    V Charles Weldon to Soma Ghosh

    Bammel Storage Pricing

    Soma, Per your request, I've calculated a Houston Area notional swap price for 6/01 through 12/04. I used the IF-Katy mid curve as of today's close and have not adjusted …

  20. 9 May 2001

    Santiago Garcia to Louis Dicarlo

    Historic prices

    Louis, Attached you will find the historic prices for TETCO M3, HSC, and NYMEX FOM. I doubled check the HSC prices and XMIM gives you a historic price for HSC and a diffe…

  21. 8 May 2001

    V Charles Weldon to Charlie Weldon" @ENRON

    ClickAtHome Portal is HERE!

    ---------------------- Forwarded by V Charles Weldon/HOU/ECT on 05/08/2001 12:17 PM --------------------------- Enron North America Corp. From: Click at Home @ ENRON 05/0…

  22. 8 May 2001

    V Charles Weldon to Charlie Weldon" @ENRON

    (no subject)

    http://www.cnn.com/SPECIALS/views/y/2001/01/feldman.power.jan3/

  23. 8 May 2001

    V Charles Weldon to Karen Buckley

    Re: ENA - Trading Track

    Karen, I just wanted to confirm that you received my resume OK. I just noticed that I replied to your EGM message you sent out yesterday instead of your ENA Trading Track…

  24. 8 May 2001
  25. 8 May 2001

    Mathew Gimble to Ruth Concannon, V Charles Weldon, Mark Breese and 6 more

    Information Request