23 Oct 2001
John Adamiak" @ENRON to Darrell Schoolcraft
Last Call for Houston Seminars
Invest in your future. One of the characteristics of successful people is that they take the time to increase their knowledge and enhance their value to the organization.…
-
23 Oct 2001
Joe Linhart to Lynn Blair, Gary Spraggins, Darrell Schoolcraft and 16 more
Oneok recap Oct.19th
Joe....................3-0518
-
22 Oct 2001
Mary Kay Miller to Toby Kuehl, TK Lohman, Perry Frazier and 10 more
RE: TW unsubscribed capacity report
Thanks for getting these mods complete and out there in such a short time. MK
-
22 Oct 2001
Jerry Graves to Gary E. Anderson, judy.beck@enron.com, controllers.dl-ets@enron.com and 36 more
Links Report Through May 2002
Please review the attached Links Report. Jerry Graves 713-345-8923
-
22 Oct 2001
Toby Kuehl to Mary Kay Miller, TK Lohman, Perry Frazier and 12 more
RE: TW unsubscribed capacity report
All, The updated TW Unsubscribed page was migrated to production today 10/22/01. Per our meeting 10/16/01, the extra line item groups have been added to the TW Unsubscrib…
-
22 Oct 2001
John Sturn to team.beaver-plant@enron.com, team.mullinville-maintenance@enron.com, team.mullinville-operations@enron.com and 53 more
Beaver to Bushton configuration without the Bushton turbine - REVISION
Well my plan lasted about 30 minutes. I had missed that Clifton unit 32 has been mothballed. It is in a preserved state, requiring an estimated 12 hours to place it back …
-
22 Oct 2001
Gary Spraggins to Tom Rice and 6 more
RE: Pierz Compressor
Gas Control looks at the 3 receipt/delivery points we have with Viking and net everything out at Pierze. Dependant on pressures on both sides at the Pierze point determin…
-
22 Oct 2001
John Sturn to team.beaver-plant@enron.com, team.mullinville-maintenance@enron.com, team.mullinville-operations@enron.com and 53 more
Beaver to Bushton configuration without the Bushton turbine
Below is a system configuration I was asked to put together to flow 1600 MM/D through Clifton without the Bushton turbine. A system weighted temperature of 29 F is foreca…
-
22 Oct 2001
Michele Winckowski to Lynn Blair, Dan Fancler, Sue Neville and 12 more
Draft - Procedures for Offsytem Transactions
Attached is the first draft of procedures for offsystem transactions. Please review and provide comments by Friday, Oct 26th . Thanks MW
-
22 Oct 2001
The following items were discussed in this week's ETS and Corporate Change Control Item
The following items were discussed in this week's ETS and Corporate Change Control Item... Oct. 21 From 10:00 a.m. - 2:00 p.m., the Unix team will perform maintenance and…
-
22 Oct 2001
Amy Mulligan to Darrell Schoolcraft, Laura Giambrone, Bert Hernandez and 5 more
Griffith Plant
The Griffith plant is currently down and will probably be down for the rest of the month. I have put a zero capacity in CAS for the deliveries through 10/31/01. If it sho…
-
22 Oct 2001
Sharon Brown to Steven January, Jerry Graves, Dale Ratliff and 2 more
FW: REMINDER! Morgan's Surprise Party! *PLEASE NOTE* NEW Location "EB 39C1"
Yes, it's still on. slb
-
22 Oct 2001
Peter Melera @ENRON to dschool@enron.com, wrtg@calpine.com, bwaters@calpine.com
southpoint
- Southpoint Gas Model.xls
-
22 Oct 2001
Jerry Graves to controllers.dl-ets@enron.com and 10 more
(Updates) Mullinville Unit 26 & Bushton Turbine
FYI, Here's the latest information on these two turbines. Bushton Turbine - Maximum Turbine should be on site Wednesday 10/24/01 to set unit 25 at Bushton. Unit 25 is the…
-
22 Oct 2001
Nancy Callans to controllers.dl-ets@enron.com, Jodie Floyd
FW: SUNFLOWER - NNG1.xls
-----Original Message----- From: "Rodenburg, Eric" <erodenbu@UtiliCorp.com>@ENRON Sent: Monday, October 22, 2001 8:14 AM To: Schoolcraft, Darrell; Spraggins, Gary; Carr, …
-
22 Oct 2001
Rodenburg, Eric" @ENRON to Darrell Schoolcraft, Gary Spraggins, James Carr and 7 more
SUNFLOWER - NNG1.xls
<<SUNFLOWER - NNG1.xls>> No change in nom for Sunflower. - SUNFLOWER - NNG1.xls
-
22 Oct 2001
All-Employee Meeting
The All-Employee Meeting will be held Tuesday, Oct. 23, at 10 a.m. Houston time at the Hyatt Regency Houston Imperial Ballroom. As one of the enhanced security measures w…
-
22 Oct 2001
All-Employee Meeting
I want to remind you about our All-Employee Meeting this Tuesday, Oct. 23, at 10 a.m. Houston time at the Hyatt Regency. We obviously have a lot to talk about. Last week …
-
22 Oct 2001
Chris A. Smith to Hottap HelpDesk, Toby Kuehl, Bradley Holmes and 17 more
All tests successfully executed
All testing was completed successfully, and we have confirmed with ENW Resolution Center that Exchange servers are up.
-
22 Oct 2001
Jeffrey Cochran to Janet Cones, controllers.dl-ets@enron.com
Market Affiliates Tape
Could a tape be made available for Gas Control shift workers at EB4225 like it was last year? Thanks.
-
22 Oct 2001
Enron in Action 10.22.01
Enron in Action can be accessed through the new Community Relations web site at http://cr.enron.com/eia.html . In this week's issue you will find out information regardin…
-
19 Oct 2001
Margaret Hall to controllers.dl-ets@enron.com
FW: STORAGE CALL
KEEP LINEPACKS 3350 - 3450 FOR THE WEEKEND
-
19 Oct 2001
Jodie Floyd to Frankie Adams, t..adams@enron.com, Jean Adams and 117 more
NNG Measurement Log thru 10/19/01
Attached is the NNG Measurement Log thru 10/19/01. I have created another sheet in the file named NNG Measlog sort by Region. Both sheet have the same information. Any qu…
-
19 Oct 2001
Margaret Hall to controllers.dl-ets@enron.com, Steve Thomas
STORAGE CALL
CUNN max w/d 600 max inj. 225-250 REDF max inj. 275 min. inj. 150 *Can shutin if necessary only last resort. LYONS max inj. 65 with 2 units at Bushton WRENSHALL max vapor…
-
19 Oct 2001
Jerry Graves to ken.anderson@enron.com, Ben Asante, scott.bade@enron.com and 36 more
Beatrice Region Outage Report Through May 2002
Please review the attached outage report. Jerry Graves 713-345-8923