to:tammy.barta@enron.com means Tammy Barta (tammy.barta@enron.com).
-
28 Jun 2000
Cindy Stokes to Thomas Myers, Hope Vargas, angeles.beltri@enron.com and 20 more
Timesheets
Unless you have exception time (vacation/sick/Fwp) you will not have to fill out a timesheet - this is for exempt personnel only. For those of you who do, I will be comin…
-
28 Jun 2000
Pam Becton to stacy.hardy@enron.com, lisa.king@enron.com, lisa.best@enron.com and 17 more
Transaction Types in SAP
FYI - Here is the list of the transaction types we will be using in SAP with the numbers assigned to them in production. A transaction type will be required anytime we bo…
-
23 Jun 2000
Cynthia Morrow to Ken Choyce, dian.chu@enron.com, Frank Cernosek Jr. and 264 more
Support Tips Emails
A helpful hint of the day.
-
23 Jun 2000
Cindy Stokes to Thomas Myers, Hope Vargas, angeles.beltri@enron.com and 20 more
GL CO and Cost Center Numbers
FYI, Our SAP company number is 413 and the cost center is 105668.
-
22 Jun 2000
Cynthia Morrow to Ken Choyce, dian.chu@enron.com, Frank Cernosek Jr. and 264 more
CATS Time Entry Training Material Development
If you have access to LEAP there is now a class available to learn to enter your time via the eHRonline. See details below.
-
7 Jun 2000
Cynthia Morrow to Ken Choyce, dian.chu@enron.com, Frank Cernosek Jr. and 267 more
Message from SAP Training Team
In case there is any confusion all training classes that are scheduled to start at 8am will be starting at 8AM. If you are not in class by 8:10am your RC will be charged …
-
2 Jun 2000
Cindy Stokes to Hope Vargas, angeles.beltri@enron.com, michael.galvan@enron.com and 18 more
Re: NEW EMPLOYEES
We are pleased to announce the following new additions to our team; Brian Schwertner will report to Hope as a Sr. Specialist responsible for CLO Coordination & Special As…
-
9 Feb 2000
Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 35 more
2/8 Weekly Cost Summary & Draw Schedule - 99 Peakers
Attached is the Final January 00 Weekly Cost Summary & Draw Schedule for the 99 Peakers with actuals through February 4, 2000. The next report will come out the beginning…
-
11 Jan 2000
Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more
1/11/00 Weekly Cost Summary and Draw Schedule - 99 Peakers
Attached are the Final 1999 Weekly Cost Summary and Draw Schedule for the 99 Peakers. Going forward, I will only be issuing these reports once a month since the Peakers a…
-
5 Jan 2000
Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more
Re: 99 Peakers Weekly Cost Summary & Draw Schedule
I will not be sending out a cost summary or draw schedule this week for the 99 Peakers since there was no change from the prior week's reports. Next week I will be issuin…
-
30 Dec 1999
Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more
99 Peakers 12/29 Weekly Cost Summary & Draw Schedule
Attached is the 12/29 Weekly Cost Summary & Draw Schedule for the 99 Peakers updated with actual expenditures through 12/24. Please call me if you have any questions. Tha…
-
21 Dec 1999
Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more
12/21 Weekly Cost Summary & Draw Schedule - 99 Peakers
Attached is the 99 Peakers' 12/21 Cost Summary and Draw Schedule for actual expenditures through 12/17/99. Due to the Christmas Holidays, next week's weekly summary will …
-
14 Dec 1999
Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more
12/14 Weekly Cost Summary & Draw Schedule - 99 Peakers.
Attached is the 99 Peakers' Weekly TVA Cost Summary and Draw Schedule for actual expenditures through December 10, 1999. Please call me with any questions. Thanks, theres…