  1. 26 Sep 2001

    Larry Campbell to Scott Patti and 16 more

    RE: Review Draft - Sundevil Fatal Flaw Analysis/Briefing Report

    Scott, I shold probably clearify something. The existing right of way, which we intend on staying in, at least around Cordes Junction is located west of I-17, which will …

  2. 26 Sep 2001

    Larry Campbell to Scott Patti and 16 more

    Re: Additional Note

    Thanks Scott, I heard about the same thing, and was checking futrher to see if this was actually the case.... "Patti, Scott" <SPatti@ensr.com> on 09/25/2001 08:35:35 PM T…

  3. 26 Sep 2001

    Scott Patti to John Shafer, Doug Cebryk, Larry Campbell and 12 more

    Additional Note

    By the way, I got a call back from Greg Simmons in the BLM State Office in Arizona - my question to him was whether or not a proposed ROW across the Agua Fria National Mo…

  4. 26 Sep 2001

    Scott Patti to John Shafer, Doug Cebryk, Dave Hubbard and 10 more

    ENSR Cashflow Estimate Through Construction of Project Sundevil

    Lady and Gentlemen, As the Subject line would lead you to believe, I am attaching a further refinement of our cost estimate, spread out over the life of the project. I kn…

  5. 25 Sep 2001

    Scott Patti to John Shafer and 14 more

    RE: Review Draft - Sundevil Fatal Flaw Analysis/Briefing Report

    Gentlemen, Attached is our work to date (minus the telephone call summary sheets and permit requirement summary sheets [Appendix A] you've already received) on the Fatal …

  6. 25 Sep 2001

    Scott Patti to John Shafer and 14 more

    RE: Review Draft - Sundevil Fatal Flaw Analysis/Briefing Report

    Gentlemen, Attached is our work to date (minus the telephone call summary sheets and permit requirement summary sheets [Appendix A] you've already received) on the Fatal …

  7. 25 Sep 2001

    Rebecca W. Cantrell to Christi L. Nicolay and 216 more

    RE: Two proceeding changes

    Christi -- I don't think it changes the requirement to file by October 1 either, and we are proceeding under the same schedule. Several rehearing requests were submitted,…

  8. 25 Sep 2001

    Nelson, Kimberly (ETS) to Robert Hayes, Robert Kilmer III, Jack Boatman and 45 more

    ETS & Industry Mentions

    Wyoming.Fort Union Gas Gathering. 09/24/2001 Natural Gas Week EOTT'S RECAPITALIZATION WILL INCLUDE CONVERSION OF UNITS, NEW FINANCING 09/24/2001 Petroleum Finance Week St…

  9. 25 Sep 2001

    Van Wolf to arnold.l.eisenstein@enron.com, Dan Pribble, jerry.d.martin@enron.com and 7 more

    Red Rock/DEQ: pre-permit construct

    If the bottom line is being able to start critical construction activities as quickly as possible, rather than properly characterizing the type of permit revision, we hav…

  10. 25 Sep 2001

    Scott Patti to John Shafer, Larry Campbell and 12 more

    Fatal Flaw Analysis Status Report

    John and Larry, I have sent a copy of the Fatal Flaw Analysis to Jon Schmidt for review and input. It truly is a "living" document, and can be as complete as you would li…

  11. 24 Sep 2001

    Scott Patti to Doug Cebryk and 12 more

    Cursory Review of Faults and Seismicity Potential - Sundevil

    Doug, I got a call from Don Mohler this morning wanting to know if we had done a cursory check of faults and seismicity in the vicinity of the SunDevil route. He said to …

  12. 24 Sep 2001

    Scott Patti to scott.patti@enron.com, jon.schmidt@enron.com, John Shafer and 6 more

    Navajo ROW costs

    I got a call back from Ed Peck over the weekend. He said that he didn't know where the BLM guy got his numbers, but that $1MM/mile for ROW would be extremely steep. He sa…

  13. 24 Sep 2001

    Scott Patti to Larry Campbell and 8 more

    Discussion with Roger Kohn of Region IX EPA

    Larry, I called Roger this morning to make sure he had received the BA. He said that he had not yet gotten it, but that it should be there around noon. I asked him to be …

  14. 24 Sep 2001
  15. 23 Sep 2001

    Darrell Schoolcraft to Randy Rice, Dan Pribble, John Shafer and 23 more

    Gallup Compressor Station

    Gas Day September 23, 2001 Gallup Compressor Station will be doing run testing. Capacity for San Juan will stay at 800,000 mmbtu/d. Gas Day September 24, 2001 Gallup Comp…

  16. 21 Sep 2001

    Scott Patti to John Shafer, Kevin Hyatt, Eric Gadd and 8 more

    Land Use Categories and Constraints along the proposed Sun Devil Route

    Attached is the land use category and constraint table that Jon Alstad has put together for the currently proposed route. He and I both have been working on the briefing …

  17. 21 Sep 2001

    Doug Cebryk to scott'.'patti@enron.com, John Shafer, Kevin Hyatt and 11 more

    RE: Agencies and NGOs already contacted for Sun Devil

    To All I have done a cursory review of the requirements of the agencies contacted, and 2 significant itmes leap out. #1 New Mexico BLM Permitting - Cultural Resources Dav…

  18. 21 Sep 2001

    Scott Patti to John Shafer, Kevin Hyatt, Eric Gadd and 8 more

    RE: Additional Agency Correspondence

    Attached are some additional pieces of the puzzle; a supplement to the large set of correspondence/permitting requirements sent earlier. Scott J. Patti Senior Project Man…

  19. 21 Sep 2001

    Scott Patti to John Shafer, Kevin Hyatt, Eric Gadd and 8 more

    Agencies and NGOs already contacted for Sun Devil

    US EPA, Regions VI and IX US Forest Service - Coconino, Kaibab, and Prescott Forests BLM - NM State Office, Farmington Field Office, AZ State Office, Phoenix Field Office…

  20. 21 Sep 2001

    Louis Soldano to Steven J. Kean, Michael Terraso and 4 more

    Transwestern Red Rock Permitting Status

    FYI gents - the meeting yesterday with the Arizona DEQ did not result in significant progress. Basically the agency folks at that level are simply not motivated to engage…

  21. 21 Sep 2001

    George Robinson to Larry Campbell, William Kendrick, Louis Soldano and 2 more

    TW Roswell Station - Waste Characterization of Pit Areas

    Soil sampling for waste characterization was completed on September 6th. Bill Olson with the NMOCD was on-site to observe the sampling activities. Twenty-two soil samples…

  22. 20 Sep 2001

    Scott Patti to John Shafer, armando.diaz@enron.com, Doug Cebryk and 6 more

    RE: REVISED Preliminary Cost Estimate for Environmental through Construction Phase - Sun Devil

    Gentlemen, this is the cost estimate I was trying to send you previously. Scott Scott J. Patti Senior Project Manager ENSR International 1601 Prospect Parkway Fort Collin…

  23. 19 Sep 2001

    Scott Patti to Larry Campbell and 16 more

    T&E species update - Red Rock Mainline Expansion

    As an update to many of you, I have been on the phone with Roger Kohn of EPA Region 9 a couple of different times today. It turns out that what they really were expecting…

  24. 19 Sep 2001

    Jan Cobden to Van Wolf, shead@ensr.com, John Shafer and 8 more

    Contacts List - final version

    Attached is the final version of the Contacts List on the Red Rock Project. ; Jan Cobden Enron Transportation Services Company 1400 Smith Street, Suite EB4780 Houston, T…

  25. 19 Sep 2001

    Nancy Bagot to Janet Butler, Ray Alvarez, Martha Benner and 101 more

    Wood announces Staff

    This release came out at FERC late last night. NEWS MEDIA CONTACT: FOR IMMEDIATE RELEASE Hedley Burrell September 18, 2001 (202) 208-0680 FERC CHAIRMAN WOOD NAMES PERSONA…