21 Mar 2001
Joseph McKechnie to Dan Masters, barbo@enron.com and 4 more
LNGC GOLAR FREEZE Into Penuelas 26 April, 2001
Dan/Paul: In regards to the cargo into the Eco terminal on 26 April we have chartered the LNGC Golar Freeze Lloyds Number 7361922, for this delivery. The Golar Freeze is …
-
21 Mar 2001
Dan Masters to gall@hoegh.no and 12 more
Voyage Orders
Please see the attached voyage orders including arrival vapor pressure orders and confirm receipt. Regards, Dan Masters
-
21 Mar 2001
Dan Masters to Victor Vega, Jaime Sanabria, Rick Sierra and 1 more
Re: Invoice for April delivery of "Methane Arctic"
Invoice for this shipment to be due on April 17 per below agreement. Dan
-
20 Mar 2001
Joseph McKechnie to pdelgado@gasnaturalsdg.es and 14 more
Re: Instructions for "Methane Arctic"
Good Morning Puri: We have been diligently working on your below request, and can now offer the following instructions. Next Loading date for Pt Fortin currently schedule…
-
19 Mar 2001
LNG/C Hoegh Galleon - Master to Dan Masters and 10 more
LNG/C"HOEGH GALLEON" - Bunkering
Dear Dan. Due to the time schedule and uncertainty regarding the eta Fujairah, we desided to not nominating bunkers for topping up this time. The vessel's rob on arrival …
-
19 Mar 2001
Wayne Perry to LNG/C Hoegh Galleon - Master, rln@hoegh.no and 12 more
Re: LNG/C"HOEGH GALLEON" - Bunkering
Where/when does the vessel have to take bunkers if it skips the topping at Fujairah ? What's the price differential ? "LNG/C Hoegh Galleon - Master" <master.amar@hoegh.no…
-
19 Mar 2001
-
19 Mar 2001
Dan Masters to LNG/C Hoegh Galleon - Master and 12 more
Re: LNG/C"HOEGH GALLEON" - Bunkering
OK- Thank you for the info. We will advise on bunkering in conjunction with the decision on whether or not to heel out. Dan Masters "LNG/C Hoegh Galleon - Master" <master…
-
19 Mar 2001
Sunita Katyal to Doug Arnell, Rick Bergsieker, Nancy Corbet and 50 more
Weekly Report for LNG Conf. Call on Monday, March 19 at 7:00 a.m. (Houston time), 5:00 p.m. (Dubai time)
Attached please find the Weekly Report for the LNG Conference Call on Monday, March 19 at 7:00 a.m. (Houston time), 5:00 p.m. (Dubai time). The dial-in numbers remain the…
-
18 Mar 2001
LNG/C Hoegh Galleon - Master to Tony Galt and 8 more
Departing Bahrain
Dear Tony, You have may already left Houston for Oman. But, please be adviced that we left Bahrain today, 18th, at 1800lt for Oman. We have now tested the steering gear a…
-
16 Mar 2001
Dan Masters to Wayne Perry and 6 more
Re: Voyage Orders
Wayne- The charter party max is 1,080 mb absolute which is in our standing orders, the tariff max at CMS is 1112 mb absolute, and according to Ron Tanner the average they…
-
15 Mar 2001
Paul Y'Barbo to harib.h.alkitani@olng.simis.com and 8 more
DPC Update - February 2001
Harib, Attached is the latest update for the DPC project. A printed copy of project photos is being forwarded to you seperately. If you have any questions, please feel fr…
-
15 Mar 2001
Paul Y'Barbo to jasultan@adgas.co.ae and 8 more
DPC Update - February 2001
Jassem, Attached is the latest update for the DPC project. A printed copy of project photos is being forwarded to you seperately. If you have any questions, please feel f…
-
15 Mar 2001
Wayne Perry to Dan Masters and 12 more
Re: Voyage Orders
Do we need to include in the orders that the arrival cargo saturation pressure not to exceed 1100mb ? ( whatever is TLNG's max. ). I believe the heel decision should wait…
-
14 Mar 2001
Remote PO - BULKPC - BULKPC to enron@enron.com, Tony Galt and 10 more
LNG/C"HOEGH GALLEON" - COOLDOWN AND GAS TRIAL
Dear Tony, Please be advised that all cargo tanks have been cooled down and all cargo pumps and spray pumps have been run and worked satisfactory. Have just arrived Bahra…
-
14 Mar 2001
(no subject)
Rudy- In the contract it says that nominations for the following month are firm while the 60 and 90 day ranges are just estimates. Since taking delivery of the smaller sh…
-
14 Mar 2001
Tony Galt to Remote PO - BULKPC - BULKPC" @ENRON and 12 more
Re: LNG/C"HOEGH GALLEON" - COOLDOWN AND GAS TRIAL
Capt. Kvammen, Thank you for the update. It looks as if all is now going according to plan. I have made arrangements through your agents Barwil to arrive in Sur during th…
-
13 Mar 2001
Dan Masters to cskinner@cabotlng.com, Jane Michalek, radamiak@cabotlng.com and 5 more
90 Day Schedule
Chris, As per clause 7.2 (a) (i) of the LNG sales contract we are providing you EcoElctrica's Ninety Day Schedule given the two assumptions listed. Assuming next ship is …
-
13 Mar 2001
Dan Masters to Jaime Sanabria and 10 more
Re: Lng Invoice
Jaime- I am just going by the contract which shows two banking days after receipt of invoice. There is no way to get a payment out today, as it takes a day or two to work…
-
13 Mar 2001
Deborah L. Keller to Dan Masters and 10 more
Re: Lng Invoice
Dan, I'm not sure how the contract reads, but we need to be in receipt of these funds first thing Thrusday morning at the very latest. Deborah L. Keller Manager, Loan Adm…
-
13 Mar 2001
Rick Sierra to pherrington@edisonmission.com and 14 more
Cash Flow
Phil, Yesterday we had our call to nominate the April LNG ship delivery. We decided to nominate our five day window between April 4 thru 8. PREPA is forecasting a 75% dis…
-
13 Mar 2001
Dan Masters to Brad Hitch, Eric Groves, Russell Dyk and 4 more
"Matthew" at Lake Charles
The "Matthew" discharged 2,702,390 MMBtu at Lake Charles. After taking out the 1.75% terminal fuel expense, we will have 2,655,098 available for our sale to ENA. We have …
-
12 Mar 2001
LNG/C Hoegh Galleon - Master to Tony Galt and 10 more
LNG/C"HOEGH GALLEON" - COOLING DOWN OPERATION
Dear Tony, Please be advised that the cooldown operation itself is going well. We lost abt 12 hrs during our purge operation of tks 2 and 3 due to the requirement of the …
-
12 Mar 2001
Sunita Katyal to Doug Arnell, Rick Bergsieker, Nancy Corbet and 49 more
UPDATED Weekly Report for LNG Conf. Call on Monday, March 12 at 7:00 a.m. (Houston time), 5:00 p.m. (Dubai time)
Attached please find the UPDATED Weekly Report for the LNG Conference Call on Monday, March 12 at 7:00 a.m. (Houston time), 5:00 p.m. (Dubai time). The dial-in numbers re…
-
9 Mar 2001