  1. 9 Jun 2000

    Darin Talley to Mark Frank, Thomas Myers, Georgeanne Hodges and 52 more

    Mgmt Summary

    Some of you had trouble opening the Mgmt Summary previously sent. You should be able to open this one. There were no changes to the numbers.

  2. 9 Jun 2000

    Darin Talley to Mark Frank, Thomas Myers, Georgeanne Hodges and 56 more

    Mgmt Summary & HotList

    Attached are the Mgmt Summary, Hot List and Metrics based on activity through 6/8/00.

  3. 7 Jun 2000

    Cynthia Morrow to Ken Choyce, dian.chu@enron.com, Frank Cernosek Jr. and 267 more

    Message from SAP Training Team

    In case there is any confusion all training classes that are scheduled to start at 8am will be starting at 8AM. If you are not in class by 8:10am your RC will be charged …

  4. 2 Jun 2000

    David W Delainey to Susan Helton, Max Yzaguirre and 2 more

    Vitro

    This is great - please update and forward weekly. Regards Delainey

  5. 19 May 2000

    Cynthia Morrow to Bryce Baxter, Rita Wynne, Lisa Csikos and 36 more

    SAP Training Statistics for 5/19 Attendance

    ENA had a good turn out on training this week, over 91% attendance. Thanks for encouraging everyone to attend this important training. Cindy

  6. 17 May 2000

    David W Delainey to Tammy R Shepperd and 8 more

    Development Budget

    Tammy, please ensure that budgets and cost tracking similar to the peakers/Doyle are set up ASAP for Austin and Vitro. These should be updated and circulated weely. Regar…

  7. 10 May 2000

    Fran L Mayes to jeffery.ader@enron.com, Scott Affelt, Mark Bernstein and 59 more

    PRC Memo

    In Case you did not receive the memo from the Office of the Chairman regarding the Midyear Performance Review Process, please read below. The mid-year Performance Managem…

  8. 9 Feb 2000

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 35 more

    2/8 Weekly Cost Summary & Draw Schedule - 99 Peakers

    Attached is the Final January 00 Weekly Cost Summary & Draw Schedule for the 99 Peakers with actuals through February 4, 2000. The next report will come out the beginning…

  9. 19 Jan 2000

    Kay Chapman to sandra.mcdonald@enron.com, Gil Muhl, Wendy King and 48 more

    CTG Presentation

    Please find attached the CTG Presentation that Billy Lemmons as asked me to forward to you. Thanks, and if you have any questions, please feel free to call. Kay 3-0643

  10. 11 Jan 2000

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    1/11/00 Weekly Cost Summary and Draw Schedule - 99 Peakers

    Attached are the Final 1999 Weekly Cost Summary and Draw Schedule for the 99 Peakers. Going forward, I will only be issuing these reports once a month since the Peakers a…

  11. 5 Jan 2000

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    Re: 99 Peakers Weekly Cost Summary & Draw Schedule

    I will not be sending out a cost summary or draw schedule this week for the 99 Peakers since there was no change from the prior week's reports. Next week I will be issuin…

  12. 4 Jan 2000

    Oscar Dalton to Wanda Curry, Tammy R Shepperd, Claire Broido and 6 more

    Alabama Electric

    Alabama Electric confirmed on Monday, 1/4/00, that they will not trigger their termination right under our recent Agreement. Pursuant to our executed transaction with AEC…

  13. 30 Dec 1999

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    99 Peakers 12/29 Weekly Cost Summary & Draw Schedule

    Attached is the 12/29 Weekly Cost Summary & Draw Schedule for the 99 Peakers updated with actual expenditures through 12/24. Please call me if you have any questions. Tha…

  14. 21 Dec 1999

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    12/21 Weekly Cost Summary & Draw Schedule - 99 Peakers

    Attached is the 99 Peakers' 12/21 Cost Summary and Draw Schedule for actual expenditures through 12/17/99. Due to the Christmas Holidays, next week's weekly summary will …

  15. 14 Dec 1999

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    12/14 Weekly Cost Summary & Draw Schedule - 99 Peakers.

    Attached is the 99 Peakers' Weekly TVA Cost Summary and Draw Schedule for actual expenditures through December 10, 1999. Please call me with any questions. Thanks, theres…