from:shona.wilson@enron.com means Shona Wilson (shona.wilson@enron.com).
-
2 May 2001
Shona Wilson to Beth Apollo, Sally Beck, Rick Buy and 7 more
4/30/01 UK Power DPR loss
The UK Power 5 day rolling loss of $29,475K noted in the April 30, 2001preliminary DPR is not considered a limit notification because that number includes $11 million of …
-
24 Apr 2001
Shona Wilson to Rick Buy, Ted Murphy, David Port and 7 more
4/20 Americas gas VAR limit violation
Attached is the Enron Americas gas VAR limit violation for April 20, 2001. The head trader for Enron Americas is responsible for printing out a hard copy of this memo, si…
-
12 Apr 2001
Shona Wilson to Sally Beck and 6 more
April 30 operational risk meeting
Dear Sally, Beth and I are planning to put on a Risk management/ MRM RAC meeting to go over: The BOD policy What MRM RAC is responsible for and Brainstorm on current and …
-
12 Apr 2001
Shona Wilson to Sally Beck and 6 more
April 30 operational risk meeting
Dear Sally, Beth and I are planning to put on a Risk management/ MRM RAC meeting to go over: The BOD policy What MRM RAC is responsible for and Brainstorm on current and …
-
6 Mar 2001
Shona Wilson to Stacey W White
FW: TECO
---------------------- Forwarded by Shona Wilson/NA/Enron on 03/06/2001 09:30 AM --------------------------- From: Frank Hayden/ENRON@enronXgate on 03/05/2001 06:38 PM To…
-
6 Mar 2001
Shona Wilson to John J Lavorato, John Sherriff, Jeffrey A Shankman and 26 more
merchant asset reclass in DPR
We have been asked to reclassify the Merchant Assets on the DPR. Currently, these assets are shown below the total trading line of the DPR, because, as per the risk polic…
-
27 Feb 2001
Shona Wilson to Louise Kitchen and 4 more
Review of DPR and related reports
Dear Louise, I am responsible for the Daily Position & Violation Reporting. With the change in your role, I would like to set up a half hour with you to go over this repo…
-
22 Feb 2001
Shona Wilson to Sally Beck, Patti Thompson
(no subject)
Sally may want to goto this as Rick Causey & Rick Buy are invited.
-
20 Feb 2001
Shona Wilson to Jeffrey C Gossett, Stacey W White, Michelle Bruce and 23 more
DPR - what it consists of, where it is going
I would like you to join me in discussing the DPR, this Thursday at 9:30am. Topics I would like to discuss are: what is currently reported in the DPR (accrual vs mtm) com…
-
14 Feb 2001
Shona Wilson to Heidi Mason and 2 more
Re: Your Input please
Thanks for your note. With the increased focus on our middle office products and the possible outsourcing of those, I am in very stong agreement that all groups need to s…
-
9 Feb 2001
Shona Wilson to Bob M Hall, Leslie Reeves, Jeffrey C Gossett and 23 more
Revised Risk Management Policy
Please find attached the Risk Management Policy expected to be approved by Enron Corp. Board of Directors on February 13, 2001. Take a moment to look through the policy a…
-
6 Feb 2001
Shona Wilson to Stephen Stock, Zhiyong Wei and 10 more
Executive report viewer
Dear Steve and Zhiyong, I have had a chance to review the elaboration document for the executive report viewer. I agree with the goals and objectives for this project. As…
-
5 Feb 2001
Shona Wilson to Jeffrey C Gossett and 2 more
ERMS DISCOUNTING Solution
As referenced below, we have this information. Let's meet tomorrow to go over an implementation approach.
-
5 Feb 2001
Shona Wilson to Mechelle Atwood and 12 more
models project
Dear Mechelle, Although I am still somewhat confused about goals and deliverables of the model project that we discussed last week, I thought I would share some informati…
-
31 Jan 2001
Shona Wilson to John J Lavorato, Jeffrey A Shankman, Gary Hickerson and 12 more
US Drift
There is a disagreement over where US Drift should be shown on the DPR. After discussions with all of you, it is apparent that Mark Frevert must make the decision about w…
-
31 Jan 2001
Shona Wilson to Thomas Myers and 16 more
Re: Inventory Accounting
I would be surprised if this is still not an issue as I believe much of the inventory is carried at forward values. From: Thomas Myers/ENRON@enronXgate on 01/31/2001 11:1…
-
31 Jan 2001
Shona Wilson to Chris Abel, Susie Ayala, Michael Benien and 18 more
updated org chart
As you know, there have been significant changes within the Global Risk Operations group. As such, I have prepared an updated organization chart to reflect the group's re…
-
31 Jan 2001
Shona Wilson to Cassandra Schultz and 14 more
Re: Sales Agency Arrangements
Further information - during the NY doorstep we noted that this issue as it relates to agents used by North America has been cleared, with the exception of one S. Korea a…
-
30 Jan 2001
Indian Contracts
---------------------- Forwarded by Shona Wilson/NA/Enron on 01/30/2001 12:39 PM --------------------------- Doug Imrie@ECT 01/24/2001 11:06 AM To: Shona Wilson/NA/Enron@…
-
18 Jan 2001
Shona Wilson to philip.bacon@enron.com, joe.robertson@enron.com, Marcelo Parra and 22 more
NY Doorstep
Dear Phil, Joe, & Marcelo, I wanted to drop you a line on behalf of your doorstep visitors to let you know we appreciate the time, effort, and cooperation the NY, St Loui…
-
16 Jan 2001
Shona Wilson to Ted Murphy, Sally Beck, Bjorn Hagelmann and 2 more
NY Doorstep with Word Stuff
Draft report for tomorrow. We have cleared the findings with Mike Jordan, Marcelo Parra, and Lou Colarusso, and will clear the report with them after we discuss it tomorr…
-
15 Dec 2000
Shona Wilson to Ted Murphy and 10 more
Re: Dec 13 DPR
Dear John, The following are the amounts that make up the $5.8 mil. I have looked into your query and noted that there was a late adjustment not exported to us (so not ca…
-
14 Dec 2000
Shona Wilson to john.powell@enron.com and 6 more
Re: Deals with P and F
Judging by the length of the spreadsheet, it looks like a pervasive problem. Nancy and I will work with debbie/some in credit to determine physical/financial guidelines a…
-
13 Dec 2000
Shona Wilson to Patti Thompson, Sally Beck
Draft Doorstep Presentation
---------------------- Forwarded by Shona Wilson/NA/Enron on 12/13/2000 06:09 PM --------------------------- From: Cassandra Schultz on 12/13/2000 05:38 PM To: Shona Wils…
-
13 Dec 2000
Shona Wilson to Bob M Hall, Leslie Reeves, Jeffrey C Gossett and 35 more
timing of submitting information to Risk Controls - update
Just to let you know, since sending this memo we have not seen a marked improvement in your reporting. We are starting to log each problem and who is late in reporting an…