2 more fall outside these years.
-
4 Apr 2001
(no subject)
Geoff, The vesting for restricted stock is 1/3 on first anniversary of signing, and 1/3 on the next two anniversaries of signing. Let me know if you have any other questi…
-
3 Apr 2001
Zhiyong Wei to Louise Kitchen and 10 more
GTV II weekly status update
Louise, Please see below for the GTV II project weekly status update and the attached file for the updated project timelines. GTV status meeting attendees: Zhiyong Wei, K…
-
2 Apr 2001
Geoff Storey to Colin Tonks, Dave Nommensen, Zhiyong Wei
GTV Meeting in EB3269
CALENDAR ENTRY: INVITATION Description: GTV Meeting in EB3269 Date: 4/3/2001 Time: 3:00 PM - 4:00 PM (Central Standard Time) Chairperson: Geoff Storey Detailed Descriptio…
-
2 Apr 2001
Enron Kid's Center Enrollment Acknowledgement
---------------------- Forwarded by Geoff Storey/HOU/ECT on 04/02/2001 09:28 AM --------------------------- "LeadTrack" <leadtrack@klcorp.com> on 03/30/2001 03:36:08 PM T…
-
2 Apr 2001
Enron Kid's Center Application Acknowledgement
---------------------- Forwarded by Geoff Storey/HOU/ECT on 04/02/2001 09:28 AM --------------------------- "Catherine Franklin-Rhem" <cfranklin-rhem@klcorp.com> on 03/30…
-
2 Apr 2001
Zhiyong Wei to Louise Kitchen and 10 more
GTV II weekly status update
Louise, Please see below for the GTV II project weekly status update and the attached file for the updated project timelines. GTV status meeting attendees: Zhiyong Wei, K…
-
31 Mar 2001
Catherine Franklin-Rhem to gstorey@enron.com
Enron Kid's Center Application Acknowledgement
Thank you for your Pre-Enrollment Application for our Enron Kid's Center. If you have questions related to the care of your child, lottery, room capacity, tuition, wait-l…
-
31 Mar 2001
LeadTrack to gstorey@enron.com
Enron Kid's Center Enrollment Acknowledgement
Victoria, Thank you for your Pre-Enrollment Application for our Enron Kid's Center. If you have questions related to the care of your child, lottery, room capacity, tuiti…
-
30 Mar 2001
Presentation for McKay
I have updated the forecast to reflect TCPL delays until Nov 1.
-
29 Mar 2001
FW: GTV weekly status meeting
INVITATION Chairperson: Zhiyong Wei Invitees: Geoff Storey Date: 3/26/2001 Time: 2:00 PM - 3:00 PM (Central Standard Time) Room: EB2601@ECT Description: GTV weekly status…
-
29 Mar 2001
FW: GTV weekly status meeting
Geof, Please join us to the GTV weekly status meeting on Mondays. The meeting is held in room 2601 from 2:00 pm to 3:00 pm. Thanks Zhiyong -----Original Appointment-----
-
29 Mar 2001
Geoff Storey to Parking & Transportation
Re: Enron Center Garage
sign me up please, thank you very very much geof
-
28 Mar 2001
Kevin Heal to Rob Milnthorp, Robert Hemstock, Eric LeDain and 11 more
S&P MOU Draft
Here is the latest version of the TCPL Mainline MOU. Significant changes (i.e. watered down) changes to turnback policy. More meetings next week as indicated below. I wil…
-
28 Mar 2001
Zhiyong Wei to Louise Kitchen and 10 more
GTV II weekly status update
Louise, The GTV II team has a weekly status meeting on Mondays. Yesterday, we had our first status meeting. Please see below for the current status of the project. Please…
-
27 Mar 2001
assignee.notification@us.pwcglobal.com to gstorey@enron.com
Important Information from PricewaterhouseCoopers IAS-Geoffrey Storey
Please respond to assignee.supportThis is the second of the two messages. Dear Geoffrey As noted in the previous message, the following password should be used for access…
-
27 Mar 2001
assignee.notification@us.pwcglobal.com to gstorey@enron.com
Important Information from PricewaterhouseCoopers IAS-Geoffrey Storey
Please respond to assignee.supportThis is the first of the two messages. Dear Geoffrey We are pleased to inform you that you are eligible for PricewaterhouseCoopers' 2000…
-
27 Mar 2001
Michelle Shabits to Michelle Shabits
Revised December Stats
Good Morning Please disregard my previous email. Attached is the December monthly report. Michelle Shabits National Energy Board - DEC00.xls
-
27 Mar 2001
Michelle Shabits to Michelle Shabits
December 2000 Natural Gas Export & Import Report
Good Morning! Attached is the December monthly report. Have a great day. Michelle Shabits National Energy Board - 0012.xls
-
27 Mar 2001
GTV version 3 requirement meeting notes: Please review
Geof, Please review the meeting notes for the requirements of GTV II phase 2 in the attached file. Please let me know any discrepancy and changes you want me to make. The…
-
27 Mar 2001
NG Curves up to 20224
Geoff, Attached is yesterdays NG curves that goes out more than 14 years. Is the curve that you talked to me about yesterday? If it is, this curve was entered by Dutch Qu…
-
27 Mar 2001
Louise Kitchen to Zhiyong Wei and 10 more
GTVII
Zhiyong Thanks for getting me the signed (so far) copy. (Beth and Philippe, please sign the document today ). When they have signed please recirculate the final signed co…
-
27 Mar 2001
Zhiyong Wei to Louise Kitchen and 10 more
GTV II weekly status update
Louise, The GTV II team has a weekly status meeting on Mondays. Yesterday, we had our first status meeting. Please see below for the current status of the project. Please…
-
27 Mar 2001
Kevin Heal to Rob Milnthorp, Robert Hemstock, Eric LeDain and 11 more
S&P MOU Draft
Here is the latest version of the TCPL Mainline MOU. Significant changes (i.e. watered down) changes to turnback policy. More meetings next week as indicated below. I wil…
-
27 Mar 2001
GTV version 3 requirement meeting notes: Please review
Geof, Please review the meeting notes for the requirements of GTV II phase 2 in the attached file. Please let me know any discrepancy and changes you want me to make. The…
-
27 Mar 2001
NG Curves up to 20224
Geoff, Attached is yesterdays NG curves that goes out more than 14 years. Is the curve that you talked to me about yesterday? If it is, this curve was entered by Dutch Qu…