from:kay.mann@enron.com means Kay Mann (kay.mann@enron.com).
to:dale.rasmussen@enron.com means Dale Rasmussen (dale.rasmussen@enron.com).
-
4 Jan 2001
Kay Mann to Lisa Bills, Roseann Engeldorf, Catherine Clark and 5 more
Fountain Valley/GE Facility Agreement and Exhibits
The GE facility agreements are nearing completion. There will be facility agreements for Fountain Valley (aka PSCO) and for LV Co Gen. The form is attached for your revie…
-
3 Jan 2001
Kay Mann to Ben Jacoby, Dale Rasmussen, Alan Larsen
RE: invoice information/TurboPark
I've been told by Global Finance that this is how TurboPark stuff gets invoiced. I'm thinking it might help if copies are sent to project people. What do you think? Kay
-
3 Jan 2001
Kay Mann to Sheila Tweed, Barton Clark, Dale Rasmussen and 6 more
TURBOPARK STUFF/CA Development I and II notice of exercise of purchase option
I am working on a deal to move TurboPark equipment into Enron owned LLC's, with a simultaneous sale of 80% of the equity to a third party. This deal is supposed to close …
-
22 Dec 2000
Re: Attached Files- ABB facility agreement for conference call
I don't have any language like that on hand. I suspect it will be in great demand! Have a great holiday, Kay
-
22 Dec 2000
Kay Mann to Ben Jacoby, Sheila Tweed, Dale Rasmussen
Attached Files- ABB facility agreement for conference call
Here's the draft of the facility agreement that ABB has had to review, along with a memo for AK about certain questions. Kay
-
22 Dec 2000
Kay Mann to Dale Rasmussen, Sheila Tweed and 2 more
ABB contract
Ben is trying to set up a conference call with ABB for next Wednesday. Dale, are you available? Pete Thompson is on vacation next week, but I suspect he would be glad to …
-
22 Dec 2000
Kay Mann to Dale Rasmussen and 2 more
RE: Exhibit B-1 to Electrobolt Exhibits
EECC may have this. Can you check with whoever your team is working with, or do you want a copy job of what was in the master agreement? Kay
-
21 Dec 2000
Kay Mann to Jim Gilbert and 8 more
Re: Status of Equipment Sale
Jim, We are meeting with them at 230 cst to see if we can reach final agreement. Kay
-
20 Dec 2000
-
20 Dec 2000
Kay Mann to Barton Clark, Karen E Jones, Sheila Tweed and 9 more
TurboPark Requirement - override letter
Attached is the override letter which was used in connection with the LM6000 turbine contract as it was moved into TurboPark. This letter highlights the 97-10 and lender …
-
19 Dec 2000
Kay Mann to Jim Gilbert and 10 more
Re: NRG Confidentiality Agreement
We are waiting to hear. We have received documents from them, but no definitive word. Kay
-
18 Dec 2000
Kay Mann to david.onuscheck@us.abb.com and 2 more
Facility agreements/change orders
Hi Dave, I was wondering if you have had a chance to look over the draft facility agreement? We would like to make some progress on the form this week. In fact, you may h…
-
18 Dec 2000
-
18 Dec 2000
ABB
It won't hurt my feelings if you want to contact ABB's lawyer directly. His name is Dave Onuscheck, and his email is david.onuscheck@us.abb.com. I'm home with a sick kid,…
-
15 Dec 2000
Re: NRG
You'll be delighted to know that the call has moved to 1000 your time, noon central. Kay
-
15 Dec 2000
Kay Mann to Jim Gilbert, Dale Rasmussen, Ben Jacoby and 4 more
NRG
How about a conference call at 1100 (Central) time? Kay
-
14 Dec 2000
Kay Mann to Sheila Tweed, Jeffrey T Hodge, Barbara N Gray and 8 more
TurboPark
FYI: The champagne is flowing in New York, as TurboPark closed moments after GE agreed to revise their consent to meet WestLB's last request. Kay
-
13 Dec 2000
Kay Mann to Peter J. Thompson, ccobb@akllp.com, Dale Rasmussen and 5 more
LM 6000 breakout contracts
The end is in sight! The break out contracts for the TurboPark LM's need to be finished up (not news to anyone). Each of these agreements will be between GE and E-Next Ge…
-
12 Dec 2000
Kay Mann to Peter J. Thompson and 4 more
RE: LV Cogen Agreement and Exhibits
In fairness to Pete, we have him working on ALL the GE and ABB break out agreements at once. I'm going to be reviewing the ESA agreement, which is priority one because of…
-
7 Dec 2000
Kay Mann to Dale Rasmussen and 8 more
Re: Payment schedule for Las Vegas Turbines
I believe the payment schedule on the spread sheet previously given to AK is correct. If there is a conflict, change order 4 takes precedence as to the timing of the paym…
-
6 Dec 2000
Re: Las Vegas Cogen--LM 6000 Breakout Contract
Doesn't it feel good to delegate?
-
6 Dec 2000
Exhibits for Austin and LV Cogen Facility Agreements
---------------------- Forwarded by Kay Mann/Corp/Enron on 12/06/2000 08:42 AM --------------------------- lee.johnson@ss.ps.ge.com on 12/05/2000 03:54:02 PM To: kay.mann…
-
6 Dec 2000
GE Mtg.
---------------------- Forwarded by Kay Mann/Corp/Enron on 12/06/2000 08:35 AM --------------------------- 12/06/2000 08:06 AM Shelby Malkemes Shelby Malkemes Shelby Malk…
-
21 Nov 2000
Kay Mann to Dale Rasmussen and 4 more
Re: ABB / West LB Change Order #1
Hi Dale, There is another change order #1 which has been signed by ABB but not Enron, relating to the cancellation of a couple of transformers. I don't think it will be s…
-
18 Nov 2000
Re: LV Cogen--GE Breakout Contract
Dale, Do you have the missing info? If not, I can send it to you. Kay