14 Aug 2001
RE: More on the Region Choices for Path Cut
As represented in the database Northwest would be MID-COLUMBIA. Is this acceptable? Thanks, Will
-
14 Aug 2001
Will Smith to Cara Semperger, Corry Bentley, David Poston and 1 more
RE: More on the Region Choices for Path Cut
Cara, We store the region from the path cuts in the database as a single EnPower Region. That means that we can only map California to one of R10, R11, and R12. Are you i…
-
14 Aug 2001
Will Smith to Cara Semperger, Karen Y Martin
RE: Deal Scheduling Is Ready for Testing
Cara, Do you have a couple of specific deal numbers we can research? Thanks, Will
-
13 Aug 2001
-
13 Aug 2001
RE: Testing PSW and Path confirmation
Cara, It appears that some clarification on the Regions is necessary. Vish has implemented the cuts to show regions as defined by the Regions table in EnPower. This is th…
-
13 Aug 2001
RE: Further Testing of PSW
Cara, Not a prob, the application wont look at the prod summary file unless you log in against PWRPRODN, so if you are logging against the test db's yer safe.. and for th…
-
13 Aug 2001
Asem Atta to Cara Semperger and 4 more
RE: Further Testing of PSW
Cara, Reason for the error is that the file it was looking for was titled PhysicalAndBookoutSummary_v2_54_WESTTestP.xls . Ive gone ahead and made changes to the applicati…
-
13 Aug 2001
Will Smith to Cara Semperger, Corry Bentley
RE: PreSchedule Workspace Testing
Cara, I apologize for not sending out an email last week; I have been busy with the Consolidated Position Manager. I did release new versions of both Pre-Schedule and Pat…
-
13 Aug 2001
-
11 Aug 2001
Lester Rawson to Cara Semperger
Lotus Notes
Cara, I can't get into Lotus Notes. However, looking at the scheduling file we quit entering Services schedules in the Lotus notes files early Jan. 2001 when the CALPX we…
-
10 Aug 2001
Karen Y Martin to Corry Bentley, Cara Semperger
Deal Scheduling Is Ready for Testing
All, Deal Scheduling has been moved to stage and is available for testing. Thanks, Karen 713.345.7810
-
8 Aug 2001
RE: EPE scheduling fee on the invoice
I shouldn't have any problems - just let me know when the annuity is entered - then I will check it out with Kathy at El Paso each month and included it in our total sale…
-
8 Aug 2001
Amy Clemons to Kate Symes, Cara Semperger
RE: July EPE Scheduling Service Fees
I'm confused - Cara had already entered an annuity, deal #709630.1, for $43,708.25 for the scheduling fee. Kate, is the deal #723265.1 in addition? What is it for? - Amy
-
7 Aug 2001
Heather Dunton to Virginia Thompson, Holden Salisbury and 2 more
RE: DPR on your PMA's
The CARP IT people : hmmmm I don't know if they exist - I got a kick out of that one! Yes I do have a call into IT - they are working on a solution for CARP. In the meant…
-
6 Aug 2001
Kate Symes to Amy Clemons and 6 more
RE: Kathy from EPE's answer
Amy - That's the best news I've heard all day! Looks like we're getting this checkout process down to a science. As far as the new scheduling fee, I'm being told that we'…
-
6 Aug 2001
Amy Clemons to Cara Semperger and 2 more
RE: Kathy from EPE's answer
Cara - will you be adding this annuity into EnPower so that I can include it in my invoice to El Paso for June? Thanks - A
-
6 Aug 2001
pserrano@epelectric.com to Greg Wolfe
Billing Procedure Question
Greg: This is to confirm our agreement to use the billing methodology as discussed by Kathy with Cara. Thanks.
-
6 Aug 2001
Stacy Runswick to Cara Semperger
More vacation time
Hey Cara, I was hoping I could take Friday Sept. 7th off. Just another 3 day weekend to go down to Sacramento. After that day I will only have 1 vacation day left just FY…
-
4 Aug 2001
RE: California Regions
Cara, How goes it? ;> thanks for the mapping rules [got it all ironed out].. I do have one more question.. what do we map records with a 'SCHED_TERM' of 'WEEK' to? All th…
-
3 Aug 2001
Heather Dunton to Cara Semperger
RE: Transmission Demand Charge
I have not been notified there was a programming change. We were concerned due to the April Time change how it created 3 strips to not include HE3; the 3 strips had the d…
-
3 Aug 2001
Heather Dunton to Holden Salisbury, Mark Fischer, Tom Alonso and 4 more
FW: Transmission Demand Charge
Below confirms that the transmission deals in April did calculate the correct Demand Charge even though it created 3 strips. -Heather
-
3 Aug 2001
Asem Atta to Cara Semperger and 6 more
RE: California Regions
Cara, Looking into the Physical and Bookout summary reports, upon recreating the functionality there are certain sections to the report which we aren't clear on.. we are …
-
3 Aug 2001
Vishwanatha Venkataswami to Corry Bentley, Cara Semperger
RE: Outstanding Issues with Pre-Schedule and Path Confirmation
Corry, I will include regions "R1" to "R6's " in EAST desk, and WSCC-S, WSCC-N, Rockies, Northwest, California regions in West desk. Cara : What is the region code for Ca…
-
3 Aug 2001
Vishwanatha Venkataswami to Corry Bentley and 6 more
RE: Outstanding Issues with Pre-Schedule and Path Confirmation
Corry, Please give me the list of Region choices you want to see in Path Cut Detail View. Cara is looking for WSCC-S, WSCC-N, Rockies, Northwest, California regions in We…
-
2 Aug 2001