6 Sep 2001
Asem Atta to Cara Semperger, Corry Bentley and 8 more
RE: Testing PSW and Path confirmation for Target date 6/20
Cara, Thanks for stepping me through Deal Scheduling to see exactly what the problem was in regards to the Physical/Non-Physical issue. Addressed this issue and we have s…
-
6 Sep 2001
Asem Atta to Cara Semperger, Corry Bentley and 8 more
RE: Testing PSW and Path confirmation for Target date 6/20
Cara et all, Following list of bug fixes are moving out to stage to address the recently reported issues: New versions of both applications have been moved out to stage..…
-
5 Sep 2001
Cara Semperger to Asem Atta, Corry Bentley, David Poston and 8 more
Testing PSW and Path confirmation for Target date 6/20
Good Morning/Afternoon/Evening; I started working in June 22 to test path cut capabilities. I was able to save a cut path. Please make sure that Bill Williams III and Who…
-
5 Sep 2001
Asem Atta to Cara Semperger and 8 more
RE: Testing the PSW and Path Confirm Report
Cara, Could I get a copy of the psc file for the preschedworkspace tests you ran today? Id like to mimic your actions to see exactly how these errors were generated and p…
-
5 Sep 2001
Cara Semperger to Asem Atta, Corry Bentley, David Poston and 8 more
Testing the PSW and Path Confirm Report
Good Morning/Afternoon/Evening; I started working in June 22 to test path cut capabilities. I was able to save a cut path. Please make sure that Bill Williams III and Who…
-
29 Aug 2001
Will Smith to Cara Semperger and 6 more
PreSchedule and Path Confirmation
Cara, Here is a list of updates: Asem, Vish: Please look this over to verify that I haven't missed anything. Aug 14: Pre-Schedule Workspace: When double click a cell auto…
-
29 Aug 2001
Asem Atta to Cara Semperger and 10 more
RE: Testing PSW and Path Confirmation done on 8/23
Cara, Looking at the Stage and Production versions of the deal scheduling application it looks like the stage version has some issues/differences.. [e.g being that check …
-
29 Aug 2001
Asem Atta to Cara Semperger, Corry Bentley, David Poston and 2 more
RE: Testing PSW and Path Confirmation done on 8/23
Cara, You are correct, if run with the params you supplied there are no results.. I did go ahead and check the option to 'Include Cross Portfolio Deals' and deals did the…
-
24 Aug 2001
Asem Atta to Cara Semperger and 8 more
RE: Testing PSW and Path Confirmation done on 8/23
Cara, Trying to figure out why Im seeing a discrepancy.. could you please send me a snapshot of the deal criteria screeen from within scheduling so that I can see exactly…
-
23 Aug 2001
Asem Atta to Cara Semperger, Corry Bentley and 8 more
PreSchedule Workspace
Cara / Corry, Having released versions of Path Confirmation and PreSchedule Workspace, we definitely would like to hear as to how the applications do testing-wise before …
-
16 Aug 2001
Will Smith to Cara Semperger, Corry Bentley and 4 more
Pre-Schedule and Path Confirmation
Cara, Corry, I am trying to get data refreshed to pwrtestp from production, but there will be some delay due to some other testing against testp. Until then the "useful" …
-
14 Aug 2001
Asem Atta to Cara Semperger and 4 more
RE: Further Testing of PSW
Cara, Understood, and your plan sounds fine.. any chance of you copying that production sheet onto your local machine and using it as your own 'test' copy then? The plan …
-
14 Aug 2001
Will Smith to Cara Semperger, Corry Bentley, David Poston and 1 more
RE: More on the Region Choices for Path Cut
Cara, We store the region from the path cuts in the database as a single EnPower Region. That means that we can only map California to one of R10, R11, and R12. Are you i…
-
13 Aug 2001
Asem Atta to Cara Semperger and 4 more
RE: Further Testing of PSW
Cara, Reason for the error is that the file it was looking for was titled PhysicalAndBookoutSummary_v2_54_WESTTestP.xls . Ive gone ahead and made changes to the applicati…
-
3 Aug 2001
Asem Atta to Cara Semperger and 6 more
RE: California Regions
Cara, Looking into the Physical and Bookout summary reports, upon recreating the functionality there are certain sections to the report which we aren't clear on.. we are …
-
31 Jul 2001
Cara Semperger to Corry Bentley, David Poston, Will Smith and 1 more
RE: Outstanding Issues with Pre-Schedule and Path Confirmation
Please see my comments in blue What follows are known issues with the Pre-Schedule Workspace and Path Confirmation Report. Pre-Schedule Workspace: Generating Transmission…
-
31 Jul 2001
Will Smith to Cara Semperger, Corry Bentley and 4 more
Outstanding Issues with Pre-Schedule and Path Confirmation
What follows are known issues with the Pre-Schedule Workspace and Path Confirmation Report. Pre-Schedule Workspace: Generating Transmission confirmation records appears n…
-
27 Jul 2001
Cara Semperger to Corry Bentley, David Poston, Will Smith and 3 more
Path Confirmation Testing of latest Release
Good Afternoon: I am looking at version 1.0.0.47 the day I was checking was initally June 23, but switched over to June 20th (new data) TEXT WRAPPING: The text wraps in t…
-
25 Jul 2001
Will Smith to Cara Semperger, Corry Bentley, David Poston and 1 more
RE: Test Results for June 23rd
A new Path Confirm has been release that should fix your problem of not being able to see your path records. Regards, Will
-
25 Jul 2001
Will Smith to Cara Semperger, Corry Bentley, David Poston and 1 more
RE: Test Results for June 23rd
Cara, There is a bug in Path confirm that which will not allow you to select the Trading Region/Desk. Vish is working on a fix and there should be a new version available…
-
25 Jul 2001
Will Smith to Cara Semperger, Corry Bentley, David Poston and 1 more
RE: Resuming Testing Today
Routes deleted for these points: MidColumbia COB N/S Portland General System BPA Busbar Palo Verde Midway-PSC Mead-230KV Four Corners-345KV Four Corners-230KV West Wing C…
-
25 Jul 2001
Will Smith to Cara Semperger, Corry Bentley and 4 more
Pre-Schedule WS and Path Confirmation
Corry, Cara, There are new versions have been released to stage. What's new and what's fixed: Pre-Schedule Workspace: Now able to select a Trading Region/Desk (EAST or WE…
-
19 Jul 2001
Asem Atta to Cara Semperger, Corry Bentley and 4 more
RE: Preparing for Next Test Day
New version of PreSchedWS has been migrated to Stage.. Corry - TVA routing records have been deleted for 6/22/01 Cara - All specified delivery points records have been de…
-
18 Jul 2001
Cara Semperger to Corry Bentley, David Poston, Will Smith and 1 more
RE: Preschedule Workspace Testing-June 21 target date
Good Morning All, I will talk to Corry about how we need our transmission represented. The format is ok, I just need more information in the path or the ability to put th…
-
18 Jul 2001
Will Smith to Cara Semperger and 6 more
RE: Preschedule Workspace Testing-June 21 target date
Cara, PreSchedule: 1. Concerning the path with transmission data... The original format was based off of Corry's suggestion. Perhaps the two of you need to discuss your n…