to:rms@ercot.com means rms@ercot.com.
-
16 Nov 2001
jeanette-harris@reliantenergy.com@ENRON to rms@ercot.com, set@ercot.com
Outage Notification Proof of Concept Open Meeting 11/26
All interested Market Participants are encouraged to attend an Outage Notification Proof of Concept Open Meeting at the ERCOT Met Center, Room 206 A, on Monday, 11/26/01,…
-
29 Oct 2001
Hetrick, Nancy" @ENRON to rms@ercot.com, set@ercot.com, testplan@ercot.com and 4 more
PUCT Staff Questions/Concerns
I have taken the email that Connie and Trish forwarded to us and broken it down into direct questions. Dave Odle will be preparing the hig level comparison of Version 1.3…
-
29 Oct 2001
Hetrick, Nancy" @ENRON to rms@ercot.com, set@ercot.com, testplan@ercot.com and 4 more
Responses for RMS Workshop
I have attached a template for each Market Participant (one per company) to respond to the pros, risks, risk mitigation, and contingency plans for each option that was pr…
-
29 Oct 2001
Hetrick, Nancy" @ENRON to Odle, David" @ENRON, set@ercot.com, testplan@ercot.com and 6 more
RE: Functionality Differences 1.3 & 1.4
Thanks, Dave. Many of you that are literate in EDI will be able to fully understand what this document tells you, but there are many reading this document that will not h…
-
29 Oct 2001
Shirley Whyte" @ENRON to rms@ercot.com, set@ercot.com, testplan@ercot.com
Re: PUC Concerns with V. 1.4 Cutover
Per Nancy Hetrick's request, attached is a spreadsheet that details Flight 1001, Frame 6 Functionality. Regards, ________________________________ Shirley Whyte 713.906.52…
-
27 Oct 2001
Hetrick, Nancy" @ENRON to rms@ercot.com, set@ercot.com, testplan@ercot.com
FW: Thanks - Protocol 15.2
Does this clarification from John cause any issues that we were not aware of? Can this still be accomplished? Nancy A. Hetrick Enron Corp. Director, Government Affairs Ph…
-
27 Oct 2001
Hetrick, Nancy" @ENRON to elbarrow@cps-satx.com, dorothea.stockstill@mirant.com, kevin-gresham@reliantenergy.com and 9 more
ERCOT Budget Items
It has come to the attention of RMS that many items that had been identified as requested/required ERCOT system changes were inadvertently not included in the ERCOT 2002 …
-
27 Oct 2001
Hetrick, Nancy" @ENRON to rms@ercot.com, set@ercot.com, testplan@ercot.com
FW: PUC Concerns with V. 1.4 Cutover
These are the questions and concerns provided by Connie and Trish. To Dos: * For consistency, Dave Odle will you please address the first four items and provide the funct…
-
27 Oct 2001
Hetrick, Nancy" @ENRON to rms@ercot.com, set@ercot.com, testplan@ercot.com
Conversion 1.4 Options
The attached files (provided by Don Bender) contains key points from three options for the conversion to 1.4 that was discussed at the October 25th RMS meeting. Please re…
-
18 Oct 2001
Don_Bender/AEPIN@aep.com to rms@ercot.com, testplan@ercot.com, set@ercot.com
1.4 Strawman Migration Plan
At RMS' October 11, 2001 meeting, Nancy Hetrick, RMS Chair, announced that an effort was underway to create an integrated planning calendar for the 1.4 Migration Plan and…