to:controllers.dl-ets@enron.com means controllers.dl-ets@enron.com.
-
21 Mar 2002
Jerry Graves to Lynn Blair, scott.clark@enron.com, Shelley Corman and 32 more
NNG Outage Weekly
The Outages attached below have some potential flow impact, or are points of interest. (NNG) Jerry Graves 713-345-8923
-
21 Mar 2002
Gary Spraggins to controllers.dl-ets@enron.com
FW: NBPL gas 3-22
FYI- Plan to get additional 30,000 from NBPL Friday. This will not be reflected in the schedule. Gary
-
21 Mar 2002
Randy Janzen to Lynn Blair, controllers.dl-ets@enron.com, Cara Vaughan and 10 more
GPM/Duke Dumas Plant - POI 18058 Derhime
The Dumas plant is going to Derhime starting at 9:00 am tomorrow, Friday March 22nd. They will continue to flow approximately 35,000 dth of raw gas. They DO NOT have a pr…
-
21 Mar 2002
Gary Spraggins to Randy LeBeau, team.sunray-compressor@enron.com, controllers.dl-ets@enron.com and 2 more
FW: GPM/Duke Dumas Plant Update
FYI Well it looks like they have change their mind again. As of now we don't know when they will be shuting their plant down. Gary
-
21 Mar 2002
Randy Janzen to controllers.dl-ets@enron.com, Cara Vaughan, Chris Greaney and 17 more
GPM/Duke Dumas Plant Update
I talked to Lavila Lawrence and Duke has postponed the "permanent" shut down of this plant. The last date she gave me was April 1st but this has been extended to an undet…
-
20 Mar 2002
Jerry Graves to controllers.dl-ets@enron.com, Steve January
Chatfield
FYI, The Chatfield unit is back available as of today at 1530. Jerry
-
20 Mar 2002
Richard Barry to controllers.dl-ets@enron.com
Lonestar
Marketing has informed gas control that there is now a common OBA between the Pecos and Ward points. This means that we can now sum the two schedules together and make th…
-
20 Mar 2002
Jerry Graves to controllers.dl-ets@enron.com, Steve January
FW: Set points
Please read the comments below, and then let Darrell or I know if this sounds acceptable you. Please note the MAOP set points and the shut down timing scenario. I have th…
-
20 Mar 2002
Nancy Callans to controllers.dl-ets@enron.com
FW: SUNFLOWER - NNG - HOURLY - 2002.xls
-----Original Message----- From: "Rodenburg, Eric" <Eric.Rodenburg@aquila.com>@ENRON Sent: Wednesday, March 20, 2002 8:01 AM To: Schoolcraft, Darrell; Spraggins, Gary; Ca…
-
19 Mar 2002
Jerry Graves to Jesse Alvarado, ken.anderson@enron.com, Roy Armitage and 136 more
Amarillo, Beatrice, Midland, and Minneapolis Region Outage Reports Through December 2002
Please review the attached outage report that pertains to your region. If you have any questions, please give me a call. Jerry Graves 713-345-8923
-
19 Mar 2002
Jerry Graves to Gary E. Anderson, ken.anderson@enron.com, judy.beck@enron.com and 36 more
Links Report Through December 2002
Please review the attached Links Report. (Please note that the Hugoton team is still working on the final scope of work that will take place during their ESD (5/7/02). Th…
-
19 Mar 2002
Darrell Schoolcraft to David Roensch, Kimberly Watson, Michelle Lokay and 16 more
Postings
Please see the attached. ds
-
19 Mar 2002
Jerry Graves to Jerry Graves, Gary Spraggins, Team Cunningham and 4 more
Cunningham (Power Outage)
FYI, The Cunningham Electrical Substation outage will be on Wednesday (3/20). We moved it up a day, so can maintain max withdrawals on Thursday (3/21) when the temps look…
-
19 Mar 2002
Nancy Callans to controllers.dl-ets@enron.com
FW: SUNFLOWER - NNG - HOURLY - 20021.xls
-----Original Message----- From: "Rodenburg, Eric" <Eric.Rodenburg@aquila.com>@ENRON Sent: Tuesday, March 19, 2002 7:48 AM To: Schoolcraft, Darrell; Spraggins, Gary; Carr…
-
19 Mar 2002
-
18 Mar 2002
Gary Spraggins to controllers.dl-ets@enron.com
Jal Compressor
Jal will be unavailble 8 hours to check relief valves and change out a 12" valve. Gary
-
18 Mar 2002
Dale Ratliff to controllers.dl-ets@enron.com
OQ (Operator Qualification)
All gas controllers must complete the Skills Qualification Manual (SQM) by June 1,2002. For those who have not completed SMQ please contact you assigned verifier when you…
-
18 Mar 2002
Darrell Schoolcraft to John Buchanan, Laura Giambrone, Bert Hernandez and 8 more
Outages for April
Please see the attached.
-
17 Mar 2002
Jesse Alvarado to controllers.dl-ets@enron.com
GALLUP SUC. SETPT.
The suc set has been rasied back up to 687 which is about as low as we can go on this unit. We were real close to tripping the unit on low suc press. The reason is that t…
-
14 Mar 2002
Gary Spraggins to controllers.dl-ets@enron.com
FW: Amarillo Region Weekly Report
-----Original Message----- From: Lebeau, Randy Sent: Thursday, March 14, 2002 9:52 AM To: Adamson, Alvin; Barbee, Roger; Beaver-Mach-Shop, Team; Beaver-Plant, Team; Blair…
-
13 Mar 2002
Steve January to controllers.dl-ets@enron.com
FLOW & ORDERS
It is very important that we check our order sheets after each nom cycle against what is actually flowing at our receipt and delivery points. If there are points flowing …
-
13 Mar 2002
Gary Spraggins to Gary Spraggins, controllers.dl-ets@enron.com and 4 more
RE: Trailblazer Outage April
Update from NGPL : April 8th through the 11th compressor station 602 will down to rewheel compressor. NGPL will be able to free flow 520,000 mmbtu/d on their line while s…
-
8 Mar 2002
Jerry Graves to Lynn Blair, scott.clark@enron.com, Shelley Corman and 32 more
NNG Outage Weekly
The Outages attached below have some potential flow impact, or are points of interest. (NNG) Jerry Graves 713-345-8923
-
4 Mar 2002
Angela Sayegh to controllers.dl-ets@enron.com and 8 more
Station 5
Two new flow direction controls have been added to the system for Station 5. Flow East Control and Flow West Control. There is also a new Flow direction discrete. Thanks,…
-
3 Mar 2002
Bart Monden to controllers.dl-ets@enron.com
TW - Monument Junction
24" and the 30" are split out from Monument junction to WT - 2. Thanks Bart