16 Mar 2001
Kay Mann to Peter J. Thompson and 6 more
Lv Co Gen Plan B
Hi Pete, There's been a Plan B developed on the LV Co Gen project. We are seriously exploring the possibility of selling the current LV Co Gen turbines to a third party, …
-
13 Mar 2001
Kay Mann to Carlos Sole, Stephen Thome, Jake Thomas and 2 more
RE: GE LM-6000 purchase contract for Las Vegas Cogeneration II pr oject
---------------------- Forwarded by Kay Mann/Corp/Enron on 03/13/2001 08:24 AM --------------------------- lee.johnson@ss.ps.ge.com on 03/12/2001 04:17:06 PM To: Dale.Ras…
-
7 Mar 2001
Re: Revised Documents
Well, that's one reason why I don't think there's a lot of risk to it. I know in previous deals the GE frame guys have agreed that we could give three redacted copies to …
-
7 Mar 2001
Kay Mann to Dale Rasmussen and 2 more
Re: Revised Documents
Neither have us have spoken to GE. I think Sheila spoke to Lee, but I don't know the substance of the conversation. We asked his permission on the Intergen deal, I believ…
-
7 Mar 2001
Kay Mann to Jake Thomas, Stephen Thome and 8 more
The Project in need of a name documents
Here's the latest drafts: Kay
-
6 Mar 2001
Re: LV Co Gen - the next generation... (hey, is that a pun?)
I don't know who started the initialling kick, and I don't know if I care if it continues. I don't know if Lee cares. It is probably an EECC artifact. If GE doesn't care,…
-
6 Mar 2001
Kay Mann to Dale Rasmussen and 2 more
LV Co Gen - the next generation... (hey, is that a pun?)
Dale, Has GE initialled all the pages of the break out contract? If so, it would be very helpful if you could ship me the originals. That way, we only have to change the …
-
6 Mar 2001
Re: GE Breakout Contracts
They haven't signed the other ones. We moved the equipment straight out of TurboPark and into the llc, then on the same day sold down the equity of the llc. Please call t…
-
1 Mar 2001
Kay Mann to Sheila Tweed, Dale Rasmussen
RE: CA Energy Development LLC documents
As I mentioned, I think the "new and improved" versions are better starting points, but here's what we used. I don't recall whether the concept of a development fee has b…
-
1 Mar 2001
Kay Mann to Sheila Tweed, Dale Rasmussen
Amendments to Letter Agreements
We had to amend the agreements to give us more time. The new version I sent you fixed that.
-
1 Mar 2001
Kay Mann to Sheila Tweed, Dale Rasmussen
Closing Checklist
I don't know if this was the final one...
-
1 Mar 2001
-
1 Mar 2001
Kay Mann to Sheila Tweed, Dale Rasmussen
LLC Agreement for Turbine LLC sale
Here is the form of LLC agreement we used for the Intergen deal, tweaked a bit for lessons learned. I will forward the updated letter agreement which has been improved al…
-
28 Feb 2001
Kay Mann to Dale Rasmussen, Sheila Tweed
Panda
Hi. Please let me know how you would like to proceed. Kay
-
27 Feb 2001
-
27 Feb 2001
Kay Mann to Sheila Tweed, Dale Rasmussen
Re: Panda Energy
I've just learned that this is a "West" deal for the sale of the LV Co Gen units. This deal was described as being the same as the Intergen deal. King & Spalding helped m…
-
16 Jan 2001
Kay Mann to Sheila Tweed, Alan Larsen, Dale Rasmussen and 1 more
ABB override
Here's my stab at it: I'll be in an off site the rest of the day. I have no pride of authorship. I'm unclear which entity will be signing the agreements, so I've left som…
-
16 Jan 2001
Kay Mann to Sheila Tweed, Alan Larsen, Dale Rasmussen
GE override letter
I'm thinking that the 1st paragraph of the GE override letter needs massaging, since it refers to the master agreement. I'll be glad to do it when I can, but I'm knee dee…
-
12 Jan 2001
Kay Mann to Peter J. Thompson and 10 more
RE: Fountain Valley/GE Facility Agreement
I agree. Please revise the form accordingly. Thanks, Kay "Thompson, Peter J." <peterthompson@akllp.com> on 01/12/2001 09:35:53 AM To: <Kay.Mann@enron.com> cc: "Pipitone, …
-
12 Jan 2001
Kay Mann to Alan Larsen and 4 more
Re: GE override letter
The practice has been for someone from Enron familiar with the project (not a lawyer) initials each of the pages for both contracts, inlcuding exhibits. So, we need to ma…
-
11 Jan 2001
Kay Mann to Sheila Tweed, Alan Larsen, Dale Rasmussen and 2 more
GE override letter
Attached is the GE override letter to accompany the facility agreements. I'm trying to figure out the ABB form. Kay
-
11 Jan 2001
Kay Mann to Sheila Tweed, Dale Rasmussen, Peter J. Thompson and 1 more
FW: ENRON - Meeting - Training Scope
Here's what I have on H-2. Sorry Pete, I thought I had sent it to you previously. Kay
-
8 Jan 2001
Kay Mann to Peter J. Thompson and 6 more
Override letter for ABB
Peter, I can't recall if I've sent you this override letter before. Essentially, it is a letter which is in effect for as long as the equipment is owned by E-Next Generat…
-
4 Jan 2001
Kay Mann to Peter J. Thompson, Dale Rasmussen, Alan Larsen
Contract comments
For your information and contemplation. Kay
-
4 Jan 2001
CA Development agreements
Hi Dale, Just got your email re assignment out of TurboPark. Here are the draft documents being reviewed by the lender for the movement of equipment out of TurboPark. Kay