from:gary.spraggins@enron.com means Gary Spraggins (gary.spraggins@enron.com).
-
25 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
Kermit #1 Turbine
The fuel valve for #1 turbine will not be in until around Feb 11th. During this time #1 turbine will not be available. Gary
-
25 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com, team.sunray-compressor@enron.com and 6 more
FW: GPM/Duke Dumas Plant - POI 18058
FYI, Here is the latest information on the GPM Dumas Plant. As I understand this gas will not be coming back to us. Gary
-
25 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com, team.carlton@enron.com
Great Lakes Testing Monday
Great Lakes will be doing testing on a unit at their Station 5 next Monday, Jan. 28th. for 6 hours. They will start around 8:00 A.M. Their pressure will be fluctuating up…
-
22 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
E-mail
FYI Do Not delete any e-mail even the junk mail.
-
22 Jan 2002
Gary Spraggins to Shelley Corman
NNG - Northend Loads
Norm Temp Actual North Load Friday 18th 13 14 3420 Saturday 19th 13 23 3170 Sunday 20th 14 26 3020 Monday 21st. 14 30 2900 Tues. 22nd. 14 34 3000 Wed. 23 21 3360 Thurs. 2…
-
18 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
FW: Abnormal Operations Report 1/17/02
-----Original Message----- From: NorthBranch, Team Sent: Friday, January 18, 2002 8:15 AM To: Pipeline Safety; Nelson, John; Odneal, Dave; Rinke, Mark; Quint, Danny; Spra…
-
17 Jan 2002
Gary Spraggins to Dale Ratliff, Darrell Schoolcraft, Jerry Graves and 5 more
RE: Verifier Training
Works for me . Gary
-
14 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
FW: CMS DAILY OBA REPORT FOR JANUARY 12, 2002
FYI, It looks like we owe CMS 32,000 between the A,B & Beaver 2 for current month. Lets start over delivering to to them on the B-line by 3 or 4 a day till we are balance…
-
9 Jan 2002
-
9 Jan 2002
-
8 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com, team.holcomb-oper@enron.com
CIG Smart pig run
Feb. 5th. CIG is wanting to run another smart pig which will affect flow at Garden city for about 5 hour. CIG will work with the Holcomb Plant on cordinating the flow tim…
-
8 Jan 2002
-
7 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com and 2 more
El Paso Keystone SCADA Nitrogen reading
Will Fernandes ( Monahans Team) is scheduled to meet El Paso personal January 15th. to fix the nitrogen reading coming into gas control. Gary
-
7 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
TW/NNG Imbalance
Looks like we made up gas NNG owed TW the last few days, so lets stayed balanced on a daily basis. Gary
-
7 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com, team.spearman@enron.com, Randy LeBeau
Cargray Plant Flow Increase
FYI Oneok is making changes in their field behind Cargray Plant this week which will increase flow by 8,000 mmbtu/d and by the end of the month they plan to be up to 20,0…
-
2 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
Cont. C-line receipt
Continental Beaver process plant has come back on line processing gas . This gas has been rerouted to go to Beaver suction and back up the bypass stream. Gary
-
2 Jan 2002
Gary Spraggins to controllers.dl-ets@enron.com
FW: Eagle Flow Control - January
-----Original Message----- From: Sebesta, Chris Sent: Wednesday, January 02, 2002 10:14 AM To: Spraggins, Gary; January, Steve Cc: Semin, Frank; Gilbert, Tom Subject: Eag…
-
28 Dec 2001
Out of Office AutoReply: Carlton Resolution - PLEASE READ!!!!
vacation Dec. 22 through Dec. 31
-
14 Dec 2001
Gary Spraggins to Michael G. Stage, Penny McCarran, Steve January and 2 more
FW: Gas Tariff Issues at Winkler Co. Point - DRN 42599
Here is what I received from El Paso in reference to the Nitrogen issue at Keystone interconnect. Gary.
-
27 Nov 2001
Gary Spraggins to Steve January and 8 more
Spraggins vacation
I plan to take one day vacation Friday Nov. 30th.
-
20 Nov 2001
Gary Spraggins to Sherry Forbish, Lynn Blair, Steve January and 7 more
RE: Hobbs System Conversation -- Gas Control Meeting, 11/20
If they were to schedule their gas directly to Golden Spread POI- 71395, operations could put them on the suction side of Plains turbine if we got full. Also Golden Sprea…
-
29 Oct 2001
Gary Spraggins to Darrell Schoolcraft
Out of Office AutoReply: TRAILBLAZER OUTAGE
Vacation Oct.29th through Nov.5
-
26 Oct 2001
Gary Spraggins to controllers.dl-ets@enron.com and 6 more
Spraggins Vacation
I will be on vacation starting Monday Oct.29th through Friday Oct. 2 nd. Call Darrell this weekend and next weekend for operational problems and allocations. Gary
-
22 Oct 2001
Gary Spraggins to Tom Rice and 6 more
RE: Pierz Compressor
Gas Control looks at the 3 receipt/delivery points we have with Viking and net everything out at Pierze. Dependant on pressures on both sides at the Pierze point determin…
-
19 Oct 2001