to:stuart.zisman@enron.com means Stuart Zisman (stuart.zisman@enron.com).
-
16 Nov 2000
Re: Gas Turbine Purchase Agreement.DOC
You are right on all points (especially the punting one!). You should have the list of specific "fill in the blank" stuff which I forwarded recently. Also, we had a discu…
-
16 Nov 2000
-
16 Nov 2000
Kay Mann to Dale Rasmussen, Stuart Zisman and 2 more
Gas Turbine Purchase Agreement.DOC
This is the most current clean version of the GE breakout contract. You have also received a list of site specific references in the contract to assist in the preparation…
-
16 Nov 2000
Westinghouse
---------------------- Forwarded by Kay Mann/Corp/Enron on 11/16/2000 08:59 AM --------------------------- Enron North America Corp. From: Mitch Robinson 11/16/2000 08:17…
-
13 Nov 2000
Kay Mann to Stuart Zisman, Dale Rasmussen, Sheila Tweed and 2 more
FW: Compared document
Ok, I'm almost done forwarding emails.
-
13 Nov 2000
-
13 Nov 2000
Kay Mann to kent.shoemaker@ae.ps.ge.com, lee.johnson@ss.ps.ge.com, Lisa Bills and 5 more
FW: Compared Document
Here's the blacklined version. Kay
-
13 Nov 2000
Kay Mann to Shoemaker, Kent (GEAE), lee.johnson@ss.ps.ge.com, Sheila Tweed and 3 more
Gas Turbine Purchase Agreement.DOC
Blackline to follow. Kay
-
13 Nov 2000
Kaye Ellis to Alan Aronowitz, Joya Davis, Sandi M Braband and 56 more
Holiday Luncheon Sign-Up
Please don't forget to sign-up to bring a dish for our Holiday Luncheon on Thursday, November 17. The turkey is provided but we need more volunteers to bring the side dis…
-
13 Nov 2000
Authorization for Haul & Install Option at Austin Project
If it says Austin, it must be yours.... Kay
-
10 Nov 2000
Kay Mann to Stuart Zisman, Dale Rasmussen, Lisa Bills and 2 more
GE break out contract
We had a very good work session with GE today to iron out the details of the break out contract. We expect to have a draft on Monday, which should be close to final as fa…
-
10 Nov 2000
JOANNE RUTKOWSKI to hhaltom@andrews-kurth.com, Stuart Zisman, JOHN G KLAUBERG and 5 more
Re:
Regulatory Approval: 1) Buyer represents that no approval or consent is required from any state commission for the proposed acquisition and related financing (collectivel…
-
10 Nov 2000
Janette Elbertson to Alan Aronowitz, Roger Balog, Peggy Banczak and 85 more
Performance Evaluation Program ("PEP") System
Many of you have received requests for feedback through the Performance Evaluation Program ("PEP") system. This feedback is used by the Performance Review Committee in co…
-
10 Nov 2000
Linda J Noske to Alan Aronowitz, Roger Balog, Peggy Banczak and 155 more
Law Conference Binders
Sheri Cromwell and I will be sorting through the binders that were left in the Houston Room after the conference. If you left your binder on the table and never got it ba…
-
10 Nov 2000
Kay Mann to thetherinton@bracepatt.com and 4 more
SWPC Agreement for Gleason
As usual, the lawyers are the last to know. Stuart is working on a transaction to sell the asset (Gleason), and therefore this ageement needs to be documented asap, which…
-
9 Nov 2000
JOANNE RUTKOWSKI to hhaltom@andrews-kurth.com, Don Miller, Mark E. Haedicke and 3 more
Re: 1935 Act Approval
Genco is a subsidiary of A, a registered holding company under the 1935 Act. Under Section 6 of the 1935 Act, companies in a registered system (that is, Genco and A) requ…
-
7 Nov 2000
Linda J Noske to Margaret Doucette, Angeline Poon, Suzanne Kelly and 123 more
Pictures - ENA Legal Conference
ENJOY! PICTURES FROM LAW CONFERENCE THAT MICHELLE CASH TOOK.
-
6 Nov 2000
Ben Jacoby to Sheila Tweed, Stuart Zisman, Kay Mann and 1 more
LM6000 Contract Payment Allocations
Folks: Based on our meeting with GE last Friday, we have decided to allocate post Nov. 15th payment obligations to the stand-alone LM6000 turbine purchase agreements as s…
-
3 Nov 2000
Kay Mann to Dale Rasmussen, Stuart Zisman
Blacklines, etc for GE Form Turbine Agreement
---------------------- Forwarded by Kay Mann/Corp/Enron on 11/03/2000 05:19 PM --------------------------- "FAYE STEDMAN" <STEDF@andrews-kurth.com> on 11/03/2000 05:01:29…
-
3 Nov 2000
Kay Mann to Stuart Zisman, Dale Rasmussen, Shoemaker, Kent (GEAE)
GE Turbine Form Facility Agreement
I'll send the blackline when I get it. Kay
-
3 Nov 2000
Kay Mann to Stuart Zisman, Dale Rasmussen, Sheila Tweed and 1 more
Update on GE facility agreement for LM's
I just completed a lengthy call with A & K concerning the form facility agreement. A revised draft should be out mid-day today. I have once again called ABB, but haven't …
-
3 Nov 2000
Twanda Sweet to Alan Aronowitz, Joya Davis, Roger Balog and 86 more
Thanksgiving Luncheon
Please note on your calendars that our Annual Thanksgiving Luncheon is scheduled for Thursday, November 16th. For those of you who would like to participate by bringing i…
-
2 Nov 2000
Pat Radford to Barbara N Gray, Jeffrey T Hodge, Shonnie Daniel and 33 more
November Calendar
Please send me any dates you plan to be out during the month of November by 5:00 pm today. The Group Calendar will be distributed tomorrow. Thanks for your help.
-
2 Nov 2000
Mitch Robinson to Don Miller, Stuart Zisman and 4 more
Gleason (Shelby) Transmission Upgrade
Larry Soderquist has forwarded to me a TVA schedule of the Shelby upgrade. If it's not already in Deal Bench, let me know and I'll forward it down. Scheduled completion i…
-
1 Nov 2000
Kay Mann to Stuart Zisman, Shoemaker, Kent (GEAE), Ben Jacoby and 1 more
GE Contract
Gentlemen: Attached is a draft of the facility agreement, without reference to WestLB. It just came in, so I haven't reviewed it. It looks like 330 tomorrow will work for…