  1. 29 Mar 2000

    Oscar Dalton to Russ Porter, Benjamin Rogers and 10 more

    Rochester, Mn (LM-6000 Deal)

    I was informed today by Rochester that they will not be working with Enron (or General Electric) on the LM-6000 Project. The following are key points: 1. Based on a GE ev…

  2. 28 Mar 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Please find attached the 2000 Peaker cost summary for the week ending 3/24/00. If you have any questions, please give me a call. Thanks Amy 3-7805

  3. 21 Mar 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 19 more

    2000 Weekly Cost Summary

    Attached please find the 2000 Weekly Cost Summary for activity through 3/17/00. If you have any questions, please give me a call. Thanks Amy 3-7805

  4. 13 Mar 2000

    Oscar Dalton to Ozzie Pagan, Russ Porter, Benjamin Rogers and 2 more

    Rochester

    I spoke with Rochester this morning and they advised that they will present a recommendation to their Board on 3/28 as to the party they will negotiate with. At this poin…

  5. 13 Mar 2000

    Stuart Zisman to Oscar Dalton and 10 more

    Re: GT Bid matrix

    Was this xls spreadsheet sent to all bidders? If so, we might have some explaining to do regarding how we undercut our supplier and more importantly how we could be in a …

  6. 13 Mar 2000

    Oscar Dalton to Ozzie Pagan, Benjamin Rogers, Russ Porter and 6 more

    GT Bid matrix

    FYI ENA was low bidder for the LM-6000 deal with Rochester. I will be calling Rochester today to determine next actions steps. Please note that our proposal is contingent…

  7. 7 Mar 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Attached are the 2000 Weekly Cost Summary reports for the week ending 3/3/00. If you have any questions, please give me a call. Thanks Amy 3-7805

  8. 29 Feb 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Attached please find the 2000 Weekly Cost Summary Reports for the week ending February 25th. If you have any questions, please give me a call. Thanks Amy 3-7805

  9. 25 Feb 2000

    Oscar Dalton to Russ Porter, Benjamin Rogers and 2 more

    rochester

    I spoke with Wally Schlink of Rochester today in follow up to our c-call. He thought the call went well; however, he still fees the main point is the price for the PPA. R…

  10. 23 Feb 2000

    Oscar Dalton to Benjamin Rogers, Russ Porter, Ozzie Pagan and 1 more

    RPU-Enron Conference Call

    Attached are questions we need to be prepared to answer for our conference call tomorrow with Rochester. We will be in 3125-A (lets meet at 8:45 a.m.)

  11. 22 Feb 2000

    Benjamin Rogers to Ozzie Pagan, Oscar Dalton, Russ Porter

    (no subject)

    The meeting with Rochester on Thursday at 9:00 am will be held in 3125a. Thanks Ben

  12. 18 Feb 2000

    Oscar Dalton to Benjamin Rogers, Russ Porter and 2 more

    Rochester

    Rochester was interested in our proposal. As such, they want to do a conference call and meeting as follows: 1. Conference call on Thursday 2/24 at 9:00 a.m. (their gener…

  13. 15 Feb 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 21 more

    2000 Weekly Cost Summary

    Attached are the 2000 Weekly cost reports. If you have any questions, please give me a call. Thanks Amy 3-7805

  14. 9 Feb 2000

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 35 more

    2/8 Weekly Cost Summary & Draw Schedule - 99 Peakers

    Attached is the Final January 00 Weekly Cost Summary & Draw Schedule for the 99 Peakers with actuals through February 4, 2000. The next report will come out the beginning…

  15. 8 Feb 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Attached please find the 2000 Weekly Cost reports with actuals through 2/4/00. If you have any questions please call. Thanks Amy 3-7805

  16. 2 Feb 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Please find attached the 2000 Weekly Cost reports for the for the week ending 1/28/00. If you have any questions, please give me a call. Thanks Amy 713-853-7805

  17. 28 Jan 2000

    Oscar Dalton to Ozzie Pagan, Janet Dietrich, Michael L Miller and 4 more

    Lincoln

    We conducted a conference call with Lincoln today and they advised they are no longer interested in working with Enron on the LM-6000 opportunity that had been under cons…

  18. 19 Jan 2000

    Kay Chapman to sandra.mcdonald@enron.com, Gil Muhl, Wendy King and 48 more

    CTG Presentation

    Please find attached the CTG Presentation that Billy Lemmons as asked me to forward to you. Thanks, and if you have any questions, please feel free to call. Kay 3-0643

  19. 12 Jan 2000

    Benjamin Rogers to Rodney Malcolm, Ozzie Pagan

    (no subject)

    The meeting with Peco will be at 1:00pm in 3125b. Thanks Ben

  20. 11 Jan 2000

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    1/11/00 Weekly Cost Summary and Draw Schedule - 99 Peakers

    Attached are the Final 1999 Weekly Cost Summary and Draw Schedule for the 99 Peakers. Going forward, I will only be issuing these reports once a month since the Peakers a…

  21. 11 Jan 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Attached are the 2000 Cost Reports. These reports only include actuals through 12/31/1999, January cost will not be posted until all year end Project Tracking has been pu…

  22. 10 Jan 2000

    Benjamin Rogers to Rogers Herndon, berney.aucoin@enron.com, Ozzie Pagan

    Genco Meeting

    The meeting has been switched to 2:00pm over near room 3125 - TBA. Let me know if this doesn't work for any of you. Thanks Ben

  23. 5 Jan 2000

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    Re: 99 Peakers Weekly Cost Summary & Draw Schedule

    I will not be sending out a cost summary or draw schedule this week for the 99 Peakers since there was no change from the prior week's reports. Next week I will be issuin…

  24. 5 Jan 2000

    Amy Copeland to David W Delainey, Mike J Miller, Ozzie Pagan and 20 more

    2000 Weekly Cost Summary

    Due to Month/ Year End closing and updating of scope changes, this weeks report will not go out until next week. Sorry for any inconvenience this may cause. If you have a…

  25. 30 Dec 1999

    Theresa Wiesmann to David W Delainey, Mike J Miller, Ozzie Pagan and 33 more

    99 Peakers 12/29 Weekly Cost Summary & Draw Schedule

    Attached is the 12/29 Weekly Cost Summary & Draw Schedule for the 99 Peakers updated with actual expenditures through 12/24. Please call me if you have any questions. Tha…