36 more fall outside these years.
to:mark.fisher@enron.com means Mark Fisher (mark.fisher@enron.com).
-
10 Apr 2002
-
10 Apr 2002
Kurt Anderson to Matt Allsup and 10 more
Re: Monthly Reports
Thanks for the feedback Matt, I understand why the format needed to change. Now we need to decide how we will incorporate the data from the revised curtailment report int…
-
10 Apr 2002
Ronald Brzezinski to dan.lindquist@enron.com and 12 more
Mill Run WTG 8 and 9 Counter Discrepancies
Dan, I've supplemented Mark's status with additional detail of the issue. I've included recommendations, including how we avoid this in the future. Please contact me if a…
-
10 Apr 2002
Matt Allsup to Kurt Anderson and 10 more
Monthly Reports
Kurt, We changed from the Feb. curtailment format to the new format because curtailments are being recorded more accurately now. Take this example of a typical curtailmen…
-
10 Apr 2002
Kurt Anderson to bo.thisted@enron.com, george.griese@enron.com, Mike Abbott and 10 more
Monthly Reports
Hey guys, the attached is the curtailment page from the Feb. Clear Sky monthly report. This format is one that I would like to stick with but if it not practical to provi…
-
9 Apr 2002
Hollis Kimbrough to Val Artman and 6 more
Re: FAR MR/SS, FARE #01502.
Val, We will have this done and back to you and Philo tomorrow. We will try to put the data into Excel but, due to size, we may have to put it into Access, If that is und…
-
9 Apr 2002
-
9 Apr 2002
Hollis Kimbrough to dan.lindquist@enron.com and 12 more
WR585 Mill Run Production Data
Dan, This includes some additional comments and explanation of the lost data around the time of the manual counter re-sets. Regards, Hollis
-
9 Apr 2002
Kurt Anderson to bo.thisted@enron.com, george.griese@enron.com, Mark V Walker and 1 more
March Curtailment
I assume that Ward's note below means that we will receive a call very soon from someone looking for the curtailment numbers for March. We have the raw data from George, …
-
9 Apr 2002
Kevin Cousineau to Mark Fisher
Re: Clear Sky SCADA testing
Mark: We have not yet started the Final SCADA test. I will keep you informed when we start this test. Regards KLC
-
8 Apr 2002
Mark V Walker to Hollis Kimbrough and 4 more
Manual Log Data Recieved For March 2002
The attached file shows the Manual Log Data (in red) that is overdue and required to complete Owner Reports. The SCADA data is still under review. It will be added to thi…
-
8 Apr 2002
FAR MR/SS - Urgent
Please see the attached Work Request. This is an urgent work request. Thanks, Hollis
-
8 Apr 2002
Cabazon Data
Hi Mark, I was able to get the data that I needed for Cabazon to evaluate performance of the derated operation, and should not require additional data analysis at this ti…
-
8 Apr 2002
Paul Landers to Mark Fisher and 2 more
Re: WR527 Pitch System Faults
Mark, Back In January approximately Visualpro was updated a new file was created called old errstat.db we also have about 20 turbines off-line at Trent Mesa due to leanin…
-
8 Apr 2002
Hollis Kimbrough to Mark Fisher
Re: WR238 & WR257 SL Ride through
Okay, Let's send it to Marion and Barry. Please provide a "cc" to Dave Schulgen, Jeff Maurer and Ben Bell. Thanks, Hollis
-
5 Apr 2002
Hollis Kimbrough to Mark Fisher
Re: WR238 & WR257 SL Ride through
Mark, Who was the cutomer that requested this? HK
-
5 Apr 2002
Re: WR574 Wind and Production data
Cool, I am glad you are involved, just let me know and we can get together.
-
4 Apr 2002
Re: WR574 Wind and Production data
Thank you for your help on this issue. You came through with the data for us which is expected. Your assistance, patience and understanding while dealing with me is very …
-
4 Apr 2002
Power consumption counter
Mark, I'm sorry I didn't get to this issue today. I will work on it tomorrow and will also ask Paul Landers to help gather this information. -Garth
-
4 Apr 2002
Kurt Anderson to wcmarshall@aep.com and 14 more
WR574 Clear Sky Wind data
Ward, As per your request, attached is the wind data, and curtailment information from Clear Sky for the month of January. Please note that due to a lack of 10 min. data …
-
4 Apr 2002
Ronald Brzezinski to dave.sweet@enron.com, Mike Abbott, Jimmy Chandler and 17 more
SCADA Daylight Savings Time information
On Sunday, April 7 2002 at 2am, Daylight Savings Time begins. Please ensure your windfarm is in the following configuration. Plant PCs should have "Automatically adjust c…
-
4 Apr 2002
Kurt Anderson to Mark Fisher and 2 more
Re: WR574 Wind and Production data
Well, we need it for the month of January because the owner has requested it, I need to get together with you and call Bo to figure out our strategy for telling the owner…
-
4 Apr 2002
Hollis Kimbrough to Mark Fisher
Re: WR583 1.5 Parasitic Loads
Mark, We may get a comment on the page 1 footnote 1 regarding "information not being available". Did you check with Engineering SCADA for this information? If you did the…
-
4 Apr 2002
Hollis Kimbrough to Mark Fisher, Mark V Walker
Re: Substation Data
Mark, Please compare these substation values to the SCADA transducer values. Thanks, Hollis
-
3 Apr 2002
Mark V Walker to Hollis Kimbrough, marion.horna@enron.com, Kurt Anderson and 5 more
Detailed Guidance On 1.5 Availability Computation. Do not send Procedure to owners until Field Ops approves it for release to the Owners
Executive Summary Marion Horna and Kurt Anderson requested an explanation of how the EW 1.5 Availability was computed. In addition, Barry Riffe and Jeff Duff have express…